This document is an Amendment to a Previous Combined Solicitation for a one-time ADA modular ramp installation project at the Department of Veterans Affairs Greater Los Angeles VA Healthcare System Medical Center.

Solicitation Details and Requirements: Solicitation Number 36C26227Q0113 is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBC). The response deadline is November 20, 2026, at 1:00 PM Pacific Time. The contracting office is located in Long Beach, California (ZIP 90815), with performance at 11301 Wilshire Boulevard, Los Angeles, California. The Product Service Code is J054 (construction services) and NAICS Code is 238990. The scope requires installation of an ADA-compliant modular ramp over existing concrete landing to cover entrance steps and allow accessibility. The ramp platform shall be installed on the existing grade/concrete surface with both sides protected from falling/tripping hazards and covered by smooth transitions. Contractors must field-measure and verify site dimensions, design the ramp per VA Technical Information Library (TIL) standards and applicable ADA accessibility standards, submit shop drawings showing ramp layout and specifications, and provide warranty documentation (minimum one year after completion). No permits are required, though the on-campus safety team will confirm completion. Performance and Payment bonds are required. Comparable ADA-compliant ramp systems from manufacturers other than the PVI Inc. sample reference are acceptable if manufacturer cut sheets are submitted.

Schedule, Pricing, and Qualifications: The anticipated award date is December 1, 2026, with a 45–60 calendar day completion period (extendable for material lead time). Work hours are 7:00 AM to 5:00 PM Monday through Friday. Contractors must provide best pricing with no government-stated magnitude range. Offer prices must remain firm for 60 calendar days. A California contractor's license or manufacturer authorized-installer certificate satisfies the qualifications factor; a licensed subcontractor may perform installation. Past performance should demonstrate similar ADA modular ramp installations, and prime contractors may include proposed subcontractor experience when demonstrating ability to perform. The government will provide a staging area on the south side of the building; contractors must haul off all packaging material disposal. Contract Specialist Marco Ramos (marco.ramos1@va.gov) is the point of contact.

View the file

Other files

File Type Posted
S02 - RFQ Solicitation 36C26227Q0113.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment to a Previous Combined Solicitation

*= Required Field Amendment to a Previous Combined Solicitation

SUBJECT B258 ADA Ramp Project B258 ADA Ramp

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE 90815

SOLICITATION NUMBER 36C26227Q0113

RESPONSE DATE/TIME/ZONE 11-20-2026 13:00 PACIFIC TIME, LOS ANGELES, USA

ARCHIVE 30 DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS N

SET-ASIDE SDVOSBC

PRODUCT SERVICE CODE J054

NAICS CODE 238990

CONTRACTING OFFICE ADDRESS Department of Veterans Affairs

Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815

POINT OF CONTACT Contract Specialist Marco Ramos marco.ramos1@va.gov

PLACE OF PERFORMANCE

ADDRESS Department of Veterans Affairs

Greater Los Angeles VA Healthcare System Medical Center 11301 Wilshire Blvd.

Los Angeles CA

POSTAL CODE 90073

COUNTRY USA

DESCRIPTION

Question 1. Exhibit B (PVI drawing XP3BR2936) shows a 29 in rise and a 30 ft 4 in ramp ending at a through/open landing. Is that the intended layout, and what landing size should quoters assume? If the landing connects to the existing entry porch through the existing porch railing, may the contractor open that railing?

Answer: The exhibit included in the Statement of Work (SOW) is intended as a sample cut sheet for reference purposes only.

The actual site dimensions and layout must be field-measured and verified to ensure an accurate design. The required ramp rise can be preliminarily estimated based on the number and height of the existing steps, while the ramp run, slope, landings, and other accessibility requirements must be determined in accordance with applicable ADA standards and VA requirements.

The final design and all associated specifications must comply with the VA Technical Information Library (TIL), including applicable design criteria, accessibility standards, and regulations.

Question 2. The SOW calls for a through/open gate at the landing pad. Is a gate required on the landing, or does through/open describe the landing's open-ended configuration?

Answer: A gate may not be necessary. The primary objective is to ensure the safety and accessibility of individuals using the ADA ramp when entering and exiting the building.

The final design should prioritize safe pedestrian circulation, minimize potential hazards, and comply with applicable ADA standards and VA TIL requirements.

Question 3. Will the VA hold a site visit before quotes are due?

Answer: No, there will be no site visit for this requirement.

Question 4. The Past Performance factor refers to maintenance and repair on sterilizing equipment, and the Qualifications factor asks for a California license to service OEM equipment or an OEM registration certificate. Should past performance cover ADA modular ramp installations, and will a California contractor (CSLB) license or a ramp manufacturer's dealer/installer certificate satisfy the Qualifications factor?

Answer: The sterilizing equipment language is an error on my end, please disregard and just cover the ADA Modular ramp installments.

Question 5. Would you prefer picket rails on the ramp, or would a two-line railing be acceptable?

Answer: Please refer to the VA Technical Information Library (TIL) for applicable ADA accessibility standards, VA design criteria, and regulatory requirements.

Question 6. Based on the drawing, the rise appears to be approximately 29", which would require a 29' x 48" ramp.

Answer: Please refer to Question 1’s answer.

Question 7. The drawing specifies a two-line railing. Since the total rise is technically under 30", this may be acceptable; however, some local jurisdictions require picket railings.

Answer: Please refer to the VA Technical Information Library (TIL) for applicable ADA accessibility standards, VA design criteria, and regulatory requirements (all standards Local, State, Federal shall be followed).

1. Could you confirm the required ramp dimensions, elevation change, landing configuration, and whether detailed drawings or measurements are available?

Answer: The exhibit included in the Statement of Work (SOW) is intended as a sample cut sheet for reference purposes only.

The actual site dimensions and layout must be field-measured and verified to ensure an accurate design. The required ramp rise can be preliminarily estimated based on the number and height of the existing steps, while the ramp run, slope, landings, and other accessibility requirements must be determined in accordance with applicable ADA standards and VA requirements.

2. Could you provide or confirm the availability of the PVI Inc. product specifications referenced as Exhibit B?

Answer: Please reference TIL for additional specifications (as needed).

3. Does the contractor need to hold a California contractor’s license directly, or may the installation be performed by an appropriately licensed subcontractor?

Answer: Subcontractor licensed will suffice the need.

4. What is the required project completion timeframe following contract award? Answer: 45

– 60 calendar days. (can be extended in case of a long lead time for material)

5. Are any permits, engineering drawings, or site preparation activities required? Answer:

No specific permits are required. However, a shop drawing showing the ramp layout and specifications must be submitted, along with warranty documentation upon project completion. The work area must be properly secured during installation to ensure pedestrian safety.

6. Has the existing area been evaluated to determine whether any ground preparation or concrete work will be needed before installation?

Answer: No. I don’t believe any concrete work will be required.

7. I noticed the SOW references PVI Inc. Would comparable ADA-compliant ramp systems from other manufacturers be acceptable?

Answer: Yes, PVI Inc. product referenced in the SOW is a sample for the bidders to have an idea about the requested ramp.

8. Can you provide a little more detail on the “through/open” gate mentioned in the SOW?

Answer: A gate may not be necessary. The primary objective is to ensure the safety and accessibility of individuals using the ADA ramp when entering and exiting the building.

The final design should prioritize safe pedestrian circulation, minimize potential hazards, and comply with applicable ADA standards and VA TIL requirements.

9. Are there any permits or local approvals the contractor would be responsible for obtaining?

Answer: Not as far as I am aware. The TIL should be followed for the requirements and specs. The on-campus safety team will be asked to confirm the ramp’s completion.

10. Is the expectation to install the modular ramp on the existing surface, or should we account for additional construction work?

Answer: existing surface.

11. The evaluation section mentions a California license to service OEM equipment. Is there a specific license required for this installation, and can that requirement be satisfied by a licensed subcontractor?

Answer: Should be fine by a licensed contractor as far as the TIL requirements are met.

12. What is the anticipated start date, and how much time will the contractor have to complete the installation?

Answer: Early December. 45 – 60 calendar days.

13. Are there any restrictions on working hours or access to the installation area? Answer:

Please reference VA TIL and VA requirements. Work hours are from 7:00 AM to 5:00 PM Monday through Friday.

14. I noticed the past performance section references maintenance and repair of sterilizing equipment. I’m assuming that may have been carried over from another requirement.

Can you confirm whether similar ADA ramp installations or related construction projects are what you’re looking for?

Answer: Yes.

15. Lastly, can the prime contractor include the experience and past performance of its proposed subcontractor when demonstrating its ability to perform the work? Answer:

Yes.

16. Period of performance: No completion deadline or period of performance is stated in the solicitation. Please confirm how many calendar days after award the installation must be complete?

Answer: Early December. 45 – 60 calendar days.

17. Qualifications wording: The evaluation section asks for proof of a California license "to service OEM Equipment" or a Certificate of Registration from the OEM. Please clarify what license or certification is required for a contractor installing this ramp system.

Answer: Disregard the OEM Equipment as it was carried over from a previous solicitation on my end.

18. Offer validity: The October 2025 deviation of FAR 52.212-1 states prices must be held firm for 60 calendar days, while the September 2023 text states 30 calendar days. Please confirm which period applies.

Answer: 60 calendar days.

19. Magnitude: Please confirm whether the Government will state an estimated value or magnitude range for this requirement?

Answer: Please provide your best pricing.

20. Landing platform: The scope calls for a "through/open" gate at the landing pad. Please confirm the required landing platform size, or whether the PVI standard platform shown in Exhibit B is acceptable.

Answer: Please refer to answer to question 8.

21. Landing size and placement: What is the required platform size? Will the platform sit on the existing concrete landing at the top of the steps, or stand free beside the steps?

Answer: The final configuration can be recommended by the contractor based on field conditions, particularly the size of the existing concrete landing at the main entrance.

Based on the available photos and approximate Google Maps measurements, the ramp platform shall be installed over the existing landing in a way to cover the step on the entrance to allow ADA access, both sides of the platform (finish surfaces differences between concrete and ramp platform on both sides) to be protected from falling/tripping and/or covered by a smooth transition.

22. Finish and width: Is standard mill-finish aluminum at 36" clear width acceptable, or is a powder-coat color or wider ramp required?

Answer: Please reference the VA TIL for additional specifications (requirements for outdoor ramps).

23. Equal products: What documentation is required to demonstrate an "equal or similar" product (e.g., manufacturer cut sheets submitted with the quote)?

Answer: Manufacturer cut sheet would be great. Please reference the VA TIL for additional specifications/requirements.

24. Utilities: Are there known underground utilities or irrigation lines within the ramp footprint? Will the VA provide utility locates?

Answer: Ramp should be anchored to existing sidewalk. The anchors are not expected to exceed sidewalk section depth so I wouldn’t anticipate a problem. VA as-builts can be provided (as needed) and VA shops would be available to assist if there were any utilities nearby.

25. Period of performance: The RFQ does not state a performance period. What is the required completion date or performance period after award?

Answer: We are expecting to have this award by 12/1/26. Expected POP: 45 – 60 calendar days.

26. Lead time: Will the schedule allow for manufacturer/shipping lead time on the modular ramp system?

Answer: Yes (depending on the lead time).

27. Bonds and warranty: Please confirm that no performance or payment bonds are required, and whether any warranty is required beyond the manufacturer's warranty.

Answer: All items are required. Performance and Payment bonds. Warranty will be required (minimum of 1 year after completion). Warranty documents will be required before the final payment.

28. The solicitation does not state a period of performance or required completion timeframe for the ramp installation. Can you please confirm the required completion time after award? Also, FAR 52.217-8 and the 52.212-2 addendum refer to option periods, but the

D.1 Price/Cost Schedule has a single CLIN 0001 (1 JB). Can you confirm there are no option periods to price?

Answer: No options.

29. The SAM.gov notice is titled “Water Treatment Services,” and the Addendum to 52.212- 1, paragraph 1, references “monthly preventive maintenance and repair.” The evaluation factors also reference sterilizing equipment and OEM equipment servicing. However, the SOW is for a one-time ADA modular ramp installation. Can you please confirm the scope is a one-time installation only, with no water treatment or recurring maintenance component?

Answer: You are correct, that was a mistake. No water treatment nor sterilizing for this solicitation.

30. Can you please confirm which license is required (e.g., a specific California CSLB contractor license classification) and whether a manufacturer authorized-installer certificate would satisfy this factor?

Answer: Yes, that would satisfy.

31. Will the Government provide a staging/laydown area, contractor parking, and access to electrical power and water at the B258 site? Is there a designated on-site location for disposal of packaging materials, or must the contractor haul off-site? Answer: Currently, there are many ongoing construction activities in the WLA campus. We can work with the contractor to provide a staging area on the south side of the building. Contractor must haul off all the disposal of packaging material.

32. Since the SOW requires protecting the existing concrete steps, handrails, and doorways in place, can you please confirm the intended ramp location and orientation relative to the existing steps, and confirm that no demolition is expected? Will the ramp and landing sit on existing grade or concrete, or must the contractor construct footings or a foundation?

Answer: The final configuration can be recommended by the contractor based on field conditions, particularly the size of the existing concrete landing at the main entrance.

Based on the available photos and approximate Google Maps measurements, the ramp platform shall be installed over the existing landing in a way to cover the step on the entrance to allow ADA access, both sides of the platform (finish surfaces differences between concrete and ramp platform on both sides) to be protected from falling/tripping and/or covered by a smooth transition.