This is a Vendor Questions and Answers document for VA Solicitation 36C26226Q0606, an LED lighting replacement project for Parking Lot P1 at the LA ACC Medical Center located at 351 East Temple Street, Los Angeles, California 90012. The solicitation is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with Firm Fixed Price contract terms, a 180-day period of performance, and NAICS code 335139 (Electric Lamp Bulb and Other Lighting Equipment Manufacturing).

The project scope encompasses a complete LED Type-B lighting fixture replacement for a two-level parking structure serving the VA Greater Los Angeles Healthcare System. Key requirements include fixtures with selectable lumens (8000L/10000L/12000L), selectable color correlated temperature (3500K/4000K/5000K), and UL/DLC approval, with BAA and TAA compliance mandatory. Wall-mounted entrance ramp fixtures must provide 2000 lumens at 5000K. Emergency backup is not required as some existing fixtures already have emergency circuitry; motion sensors are not required; and contractors may replace existing 8-foot fixtures with new 8-foot LED equivalents rather than downsizing to 4-foot units. The project covers only the P1 parking lot and entrance ramp from the guard shack and excludes stairwell step lights. Payment shall be monthly in arrears per FAR 52.212-4, electrical plans will be provided post-award, and a designated staging area for removal and storage will be provided by the VA. The job walk occurred April 29, 2026, and vendor questions had a deadline of May 6, 2026.

View the file

Other files

File Type Posted
36C26226Q0606 0002_1.docx DOCX document
S04-Job Walk Sign-in Sheet.pdf PDF
36C26226Q0606 0001.docx DOCX document
LED Lighting Replacement Enclosure 2.docx DOCX document
36C26226Q0606.docx DOCX document
Attachment 1 - Oracle Light Fixture.pdf PDF
LED Lighting Replacement Enclosure 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Response to the Vendor Questions

1. How many fixtures require emergency backup? Answer: Emergency back up not required per scope of work as some of the light fixtures already on building emergency circuitry

1. How many fixtures require motion sensors? None

1. Additionally, based on the specifications, it appears that both Elite fixtures include emergency backup. Refer to Answer to Question 1.

1. Could you please confirm whether emergency backup is required for all fixtures? If so, we will make sure to include that when quoting equivalent products. Refer to Answer to Question 1.

1. The vapor tight fixture specification includes a motion sensor option; however, the scope of work does not mention motion sensors. Refer to Answer to Question 2.

1. Should motion sensors be included with each ceiling fixture, or should the fixtures be standard (always on)? Refer to Answer to Question 2.

1. Lastly, the scope of work calls for a minimum of 3000 lumens per fixture, but the Elite wall mount specification lists a maximum of 2000 lumens. Answer: provide 2000 lumens for wall mounts OW2B-LED or equal entrance ramp only Color temperature: 5000K (daylight white).

1. Would this disqualify the Elite wall mount, or should we propose alternative fixtures that meet the 3000-lumen requirement? Answer: Refer to Answer to question 7

1. Is progress billing an option for this project? Answer: Payment shall be made on a monthly arrears for services provided during the billing month in arrears in accordance with FAR 52.212-4, para. (i)

1. Are alternative work hours, such as after-hours during weekdays, acceptable to help minimize disruption to operations? No

1. Is this project for the first floor only? There is a ramp leading down to the 2nd floor that had wall mounts, but Mr. Manoukian didn’t know if it is part of this project.

Answer: The project is for the P1 parking lot and the entrance ramp from the guard shack to the P1 parking lot level.

1. Do you have the electrical plans and if so, can you share them with us? Answer: yes. Electrical plans will be provided after contract award.

1. I want to confirm that we can propose alternatives if the fixtures we propose conform to the requirements. Answer: Per scope of work requirements OWVS1-LED or equal with selectable Lumens 8000L/10000L/12000L, selectable CCT 35k/40k/50k.

1. Would an ETL/DLC approved fixture be accepted, or only UL/DLC approved? Answer: UL/DLC approved

1. Is there any requirement for BAA or TAA compliance? Answer: Yes

1. What is the primary focus of this project? Energy savings? Increased Safety? Something else? Answer: both

1. Do you know the approximate start date for this project? Answer: Notice to Proceed will be issued after contract award

1. Could you please confirm if the VA will provide a designated staging area for dump and storage containers to support the removal and replacement of the existing fixtures? Answer: Yes

1. Light Fixture Discrepancy The existing light fixtures on site are 8-foot fixtures; however, the provided specifications call out 4-foot fixtures as the replacements. Please confirm the intended replacement fixture length or advise whether the scope should include modifications to accommodate 4-foot fixtures in place of the existing 8-foot units. Answer: Contractor can replace 8 ft light with new 8 ft LED light

1. Ramp Lighting Specification No specification was provided for the replacement of the ramp lighting. Please provide the intended fixture spec (manufacturer, model, lumen output, mounting, finish, etc.) so we can include accurate pricing in our estimate.

Answer: Refer to Answer to question 7

1. Emergency Power / Dual-Fed Fixtures Please confirm whether the existing fixtures are dual-fed emergency fixtures backed up by the hospital's generator. This will affect the wiring scope, fixture type, and any required emergency transfer/sensing devices in the replacement scope. Answer: refer to Answer 1. No dual wiring.

1. Parking Structure Stairwell Step Lights Please confirm whether the step lights in the parking structure stairwells leading to street level are to be included in the scope of this project. If so, please provide the applicable fixture specification. Answer: Not part of project