VA Response to the RFI Questions.docx

DOCX document 15 KB Posted

Attached to
J056--Flooring Installation Federal contract opportunity
Solicitation number
36C26225Q0332
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22

About this file

This is a Q&A document containing VA responses to 15 contractor questions regarding a flooring installation project at VA Greater Los Angeles Healthcare System Building 222. Key details include specifications for two flooring systems: Flowcrete Flowfresh SL 1/8" Cementitious Urethane Floor System for the first floor and Key Resin Key Mortar SLT 1/8" Decorative Floor System (color code 506) for second-floor restrooms, with no substitutions allowed.

The VA clarified that work can occur 24/7, personnel will relocate to the second floor during construction, ICRA requirements are Category C- Low Risk - Level II, and as-built floor plans will be provided. The VA confirmed corner guards must be removed and reinstalled, hazmat/ACM reports will be provided at contract start, no substantial floor leveling is anticipated, and contractor background checks are required. The VA will provide electrical panel access and wage determinations, while transition strips should follow manufacturer recommendations and industry standards.

View the file

Other files for this federal contract opportunity

Other files attached to J056--Flooring Installation, newest first.
File Type Posted
36C26225Q0332 0003_1.docx DOCX document
36C26225Q0332 0002_1.docx DOCX document
S04-Job Walk Sign-in sheet.pdf PDF
36C26225Q0332 0001_1.docx DOCX document
Flooring Installation Service Enclosure 2.docx DOCX document
36C26225Q0332.docx DOCX document
Flooring Installation Service Enclosure 1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Response to the RFI Questions

1. Will the VA specify the working hours for this project? Will this be an “after-hours” project?

Yes, and working hours can be day or night, 7 days a week.

2. Will the VA specify the ICRA requirements for this project?

Yes, this should be, Category C- Low Risk – Level II, please see VHA-ICRA-2023-1.0

3. In order to provide the most responsive bid possible, will the VA provide the as-built floor plans depicting the areas for this work? If possible, will the VA provide shading on the drawings for the areas to receive new flooring?

As-Builts can be provided from Project Staff upon request and the VA can color in floor area to be completed.

4. Will the VA provide the current HAZMAT Surveys for the areas scheduled for new flooring / grinding?

Yes, will provide report at start of contract.

5. Will the VA clarify if any ACM is expected to be encountered in the existing flooring system sched for removal?

Yes, report will be provided at start of contract.

6. The specifications for the designated resinous flooring products to be utilized are insufficient for an accurate bid. For the Floor Crete (or equal) products, a specific product line, the color(s), flakes or not, all need to be specified. For the Key Resin (or equal) products, a specific product line, the color(s), flakes or not, AND ANY PATTERNS (on a drawing) all need to be specified. Will the VA provide this information to facilitate the best possible value for the VA?

Manufacturer: Flowcrete System: Flowfresh SL 1/8” Cementitious Urethane Floor System 1st floor. Key Resin System: Key Mortar SLT 1/8” Decorative Floor System color code 506. NO SUBSTITUTIONS SHALL BE ACCEPTED.

7. Since the areas to receive new flooring are in “high traffic” areas, will the VA provide a brief description of how the preferred phasing is to take place?

Personnel will be relocated to the second floor during period of performance and utilize alternate entry points to eliminate interference to the contractor.

8. Does the VA anticipate any flooring substrate leveling beyond that of a minor nature? If so, or if determined during demolition, will this be considered a Differing Condition and eligible for a price modification?

No

9. Will the VA require any flooring substrate moisture, or other testing, prior to new flooring installation?

No

10. Will the VA supply the Wage Decision that will be applicable to this project?

Yes

11. RFP, pages 4 & 5, Part 2.6-d specify risk categories with requirements for Contractor paid background checks for all personnel ranging from Low ($231.00) to High ($3,465.00). Will the VA clarify if this requirement applies to this project and if so, will the VA clarify which Background Investigation Level will be applicable?

Yes

12. Will the Contractor be provided nearby access to electrical panels to provide hook-ups for the power required for the grinding equipment?

Yes

13. The RFQ mentions a "1/8” Decorative Floor System" for the second-floor restrooms but does not provide further specifications. Could you kindly provide more details on the specific type, material, or any other requirements for the decorative flooring system? This information will help us provide a more accurate estimate and ensure we meet all project specifications.

Key Resin System: Key Mortar SLT 1/8” Decorative Floor System color code 506.

14. The area scheduled for new flooring has multiple steel corner guards (see attached photo) that extend to the actual finished floor level. These corner guards will be below the cove base level. Will the VA clarify if the Contractor should remove these corner guards and reinstall them after the flooring is finished?

Yes, remove and reinstall.

15. Will the VA specify the type and basis of design for the transition strips at doors where the new flooring system meets the existing system (see attached photo)?

No, the transition strip shall be what is recommended from the manufacturer and used in the industry standard.