View the file

Other files

File Type Posted
MASTER ELEVATOR-VTU INVENTORY_VA SAN DIEGO.xlsx XLSX spreadsheet
MASTER ELEVATOR-VTU INVENTORY_VA SAN DIEGO.pdf PDF
36C26221Q0006 0001_1.docx DOCX document
WAGE DETERMINATION RATES SCA WDN 1986-0431 REVISION 52.pdf PDF
SF1449 RFQ 36C26221Q0006.pdf PDF
ELEVATOR-VTU LISTING.pdf PDF
36C26221Q0006_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI FORM

Contractor Name:

Address:

Phone/Fax:

Send to: cecil.nichols@va.gov

RFI

(REQUEST FOR INFORMATION)

PROJECT NO.:

RFI NO.:

PROJECT NAME:

SERVICE to PERFORM Semi-Annual & Annual

Inspection & Certification of

Elevators, VA San Diego

DATE REQUESTED:

09/17/2020

SOLICITATION NO.:

36C26221Q0006

REFERENCE:

DRAWING:

SPECIFICATION

SECTION:

DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED

Please be specific as possible:

1. Per SOW, [paragraph] 5. BACKGROUND: Please confirm that all units require 5-year testing?

2. Please confirm when 5-year testing is due.

3. What month is the current schedule for annual and semi-annual testing?

PROJECT MANAGER’S RESPONSE

1. Yes; all units listed require testing.

2. The 5-year load test is due June 2021.

3. June and December.

AMENDMENT NO.:

VA PROJECT ENGINEER/MANAGER:

TIM CONROY, Engineering Technician / COR

DATE:

09/29/2020 mailto:cecil.nichols@va.gov