36C26220Q0742-0002001.docx
DOCX document Posted
- Attached to
- H147--Deaerator Tank Non-Destructive Test
- Solicitation number
- 36C26220Q0742
About this file
36C26220Q0742 0002 REQUEST FOR INFORMATION response 2.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26220Q0742-0002000.docx | DOCX document | |
| 36C26220Q0742-0001000.docx | DOCX document | |
| 36C26220Q0742-0001002.doc | DOC document | |
| 36C26220Q0742-0001001.docx | DOCX document | |
| 36C26220Q0742-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION
Project Name: Deaerator Tank Non-Destructive Test Solicitation Number: 36C26220Q0742
1. You have stated in the SOW that the inspector will:
· Remove doors to the tank.
· Remove old gaskets and replace with new gaskets.
· Install doors back with new gaskets These are not normal task for an inspector. The VA boiler room personnel or another contractor opens and cleans and closes the DA tank. Can you clarify if this is the VA's intent.?
VA Response: The contractor is responsible for providing all the required personnel needed to perform the duties as specified in the scope of work.