_SOW_ 570-27-112 - Sidewalks Fresno.pdf
PDF 2 MB Posted
- Solicitation number
- 36C26127R0012
About this file
This is a Statement of Work (SOW) for a Design-Build project to replace damaged sidewalks and flat-work throughout the VA Central California Health Care System Fresno Campus (Project #570-27-112).
The Design-Build Contractor is responsible for all Architect-Engineer (A/E) design services, construction services, labor, materials, equipment, supervision, permitting, and other resources necessary to deliver a fully functional, code-compliant project. The contractor must conduct a comprehensive investigation and assessment of all concrete pedestrian pathways, including sidewalks, curb ramps, pedestrian ramps, accessible routes, landings, crosswalks, and detectable warning surfaces. The design must achieve full compliance with the Architectural Barriers Act (ABA), Uniform Federal Accessibility Standards (UFAS), VA Barrier-Free Design Requirements, VA Design Manuals, VA Master Specifications, NFPA standards, and all applicable Federal, state, and local building codes. The project is located at 2615 E. Clinton Ave., Fresno, CA 93703-2286, with a Period of Performance of 330 days from Notice to Proceed.
The design deliverables are phased as follows: Phase 1 (Design Development) requires a 35% submission including existing conditions assessment, accessibility and code-compliance assessment, design narrative, preliminary drawings, construction phasing plan, engineering analyses, cost estimate, and at least three viable design alternatives. Phase 2 (Construction Documents) requires 65%, 95%, and 100% submissions, each including coordinated drawings for all disciplines, full technical specifications meeting VA standards, design calculations, code and accessibility compliance documentation, updated construction phasing and logistics plans, itemized cost estimates, design and construction schedules, utility investigation and coordination documentation, constructability reviews, required models and renderings, and consolidated comment-response matrices. The contractor must obtain an independent Fire and Life Safety review from a qualified Certified Independent Technical Peer (CITP) experienced in healthcare facility design. Government review comments will be provided within 21 calendar days of complete submission, and the contractor must resolve all comments and resubmit within 10 calendar days or as directed. All submissions must be provided electronically in searchable PDF format and native editable formats, with hard copies as requested. Construction activities are limited to Monday through Friday, 7:00 a.m. to 4:30 p.m. Pacific Time, excluding Federal holidays, unless prior written approval is obtained. The contractor must provide weekly site visits during construction, respond to design-related RFIs within 14 calendar days, review all submittals within 14 calendar days, and perform acceptance testing for all building and utility systems. Payment will not be made until at least seven business days after receipt of submission and COR approval of the percentage of work completed. The contractor is responsible for all costs associated with asbestos and lead evaluations, infection control measures, permits, temporary facilities, testing, commissioning, and warranty corrections.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26127R0012.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 21, 2026
Statement of Work (SOW) Design-Build Services Project # 570-27-112
Title: Replace Damaged Sidewalks and Flat-work throughout Facility Grounds
I. Project Overview: This is a Design-Build project for the VA Central California Health Care System (VACCHCS)
Fresno Campus. The selected Design-Build Contractor is responsible for providing all Architect-Engineer (A/E) design services, construction services, labor, materials, equipment, supervision, coordination, any permits, and other resources necessary to complete the project in accordance with this Statement of Work (SOW), the contract, and all applicable codes, standards, and VA requirements.
The specifications included in the solicitation establish the minimum project requirements and are provided as the basis for design. The Contractor is fully responsible for developing the complete design and producing all full and final length project-specific drawings, calculations, specifications, and construction documents necessary to deliver a fully functional, constructible, and code-compliant project. As a design deliverable, the Contractor must prepare and submit a complete set of project-specific VA specifications for Government review and approval.
The Contractor bears full responsibility for the adequacy, accuracy, completeness, coordination, constructability, and code compliance of the design and construction for this project. The Contractor is responsible for identifying and incorporating all work necessary to satisfy the project objectives and deliver a complete and operational project, regardless of whether every requirement is specifically identified in this SOW. VA review, comment, acceptance, or approval does not relieve the Contractor of responsibility for both the design, construction, or performance of the project.
This Statement of Work document establishes the minimum requirements for design and construction deliverables under the contract along with the minimum specifications. The Design-Build Contractor, including its Architect- Engineer (A/E) team, is fully responsible for all design, engineering, coordination, field verification, permitting, and construction services necessary to complete the project in accordance with all contract requirements. All services will be performed for the VA Central California Health Care System, located at 2615 E. Clinton Ave., Fresno, CA 93703- 2286. The Contractor bears full responsibility for the adequacy, accuracy, and completeness of all A/E design and construction activities required to deliver a complete and functional project.
The Period of Performance for this Design - Build project will be 330 days from NTP.
The Place of Performance: VA Central California Healthcare System (VACCHCS) campus located at the Fresno VA Medical Center, 2615 E. Clinton Ave. Fresno CA 93703-2286.
A. The Design-Build Contractor, including its Architect-Engineer (A/E) team, is fully responsible for all professional architectural, engineering, investigative, evaluation, assessment, design, and construction support services required to complete this project. The Contractor mush furnish all labor, supervision, expertise, project management, site investigations, field verifications, surveying, testing, analyses, calculations, engineering studies, design development, drawings, specification, cost estimates, equipment, tools, travel, specialty services, and other resources necessary to fulfill the requirements of this SOW and specifications.
VA will provide available as-built drawings for reference only. The Contractor is solely responsible for independently verifying all existing field conditions, dimensions, elevations, grades, slopes, utilities, obstructions, site features, and other conditions that may affect the design or construction of the project. The Contractor may not rely on the accuracy, completeness, or suitability of VA-provided drawings, records, or information without independent verification.
The Contractor must:
(1) Perform a comprehensive investigation and assessment of all concrete pedestrian pathways, including sidewalks, curb ramps, pedestrian ramps, accessible routes, landings, crosswalks, detectable warning surfaces, and associated accessibility features within the project area.
DRAFT
(2) Identify all existing accessibility, safety, design, construction, and code deficiencies and all conditions that do not comply with applicable Federal accessibility requirements. E.g. ABA UFAS etc.
(3) Prepare complete, coordinated, and constructible drawings, specifications, any calculations, details, schedules, and cost estimates necessary to correct all identified deficiencies.
(4) Develop a design that brings all affected pedestrian pathways and associated accessibility features into full compliance with the Architectural Barriers Act (ABA), Uniform Federal Accessibility Standards (UFAS), VA Barrier-Free Design Requirements, VA Design Manuals, VA Master Specifications, NFPA standards, applicable building and life-safety codes, and all other Federal, state, local, and VA requirements applicable to the project.
(5) Identify and incorporate all work necessary to achieve a complete, functional, code-compliant, and fully accessible pedestrian circulation system, regardless of whether such work is specifically identified in this SOW.
The Contractor bears full responsibility for the adequacy, accuracy, completeness, coordination, constructability, and code compliance of all investigations, analyses, designs, drawings, specifications, calculations, and deliverables. The Contractor is responsible for identifying and incorporating all requirements necessary to deliver a complete and fully compliant design package. Any errors, omissions, conflicts, discrepancies, design deficiencies, coordination failures, constructability issues, or additional work required to satisfy applicable codes, standards, regulations, or project requirements remain the sole responsibility of the Contractor and do not constitute grounds for additional compensation, schedule adjustment, or relief from performance obligations under the contract.
B. A pre-proposal site visit is not mandatory but is strongly encouraged, any site visit information will be attached to the solicitation. The Design-Build Contractor is solely responsible for obtaining all information necessary to prepare its proposal and perform the work, including independently verifying all existing site conditions, dimensions, elevations, utilities, accessibility features, and other field conditions affecting the project. VA will provide available as-built drawings and facility information for reference only; the Contractor may not rely on the accuracy or completeness of such information without independent verification and is responsible for requesting any available records needed to perform the work. The Contractor must comply with all applicable safety requirements during site investigations and immediately notify the COR of any hazardous materials, hazardous conditions, utility conflicts, or other site conditions affecting project scope, safety, cost, or schedule. Any errors, omissions, discrepancies, rework, redesign, or additional work resulting from the Contractor's failure to adequately investigate or verify existing conditions remain the sole responsibility of the Contractor and do not constitute grounds for additional compensation or schedule adjustment.
C. The evaluation report and design development phase must advance the design to a minimum of 35% completion. The construction document phase must include 65%, 95%, and 100% design submissions. Each submission must be complete, coordinated, and suitable for review at the specified design stage. The Contractor may not proceed to the next design phase until written approval of the current submission is received from the COR. Any revisions, corrections, or additional information required as a result of review comments must be incorporated into the subsequent submission at no additional cost to the Government. The Contractor remains fully responsible for the accuracy, completeness, coordination, and code compliance of all design documents regardless of VA review or approval.
II.SCOPE OF WORK:
Background & Project Overview; Sidewalks: Existing pedestrian pathways within the VA Central California Health Care System (VACCHCS) Fresno campus contain deteriorated, unsafe, and accessibility-deficient conditions, including cracking, settlement, displacement, excessive running slopes, cross-slope deficiencies, and other conditions affecting pedestrian access. The Design-Build Contractor is responsible for evaluating all sidewalks, curb ramps, pedestrian ramps, accessible routes, landings, detectable warning surfaces, and related pedestrian circulation features within the project area; identifying all deficient, unsafe, and noncompliant conditions; and preparing complete, coordinated, and constructible design and construction documents necessary to correct all deficiencies and achieve full compliance with current Architectural Barriers Act (ABA) Accessibility Standards, ADA, Uniform Federal Accessibility Standards (UFAS)((http://www.access-board.gov/ufas/ufas-html/ufas.htm ), any VA Design Requirements, and all other applicable Federal, state, local, and Department of Veterans Affairs codes, standards, criteria, and regulatory requirements.
Phase #1 – Existing Conditions Assessment and Design Development, 35%: The Design-Build Contractor must investigate, evaluate, and document all sidewalks, curb ramps, pedestrian ramps, accessible routes, entrances, canopies, and related pedestrian circulation features within the project area.
The evaluation must identify deteriorated, unsafe, inaccessible, damaged, or noncompliant conditions and define all corrective work required by the contract.
The 35 percent submission must include, at a minimum:
(1) Existing conditions assessment, including field measurements and supporting documentation.
(2) Accessibility and code-compliance assessment identifying each deficiency.
(3) Design narrative describing the proposed corrective work.
(4) Preliminary drawings, site plans, details, and schematics.
(5) Preliminary construction phasing and logistics plan.
(6) Preliminary engineering analyses and calculations.
(7) Itemized construction cost estimate.
(8) Assessment of impacts on pedestrian and vehicular circulation, emergency access, facility operations, utilities, adjacent facilities, and campus appearance.
(9) At least three viable design alternatives, each supported by cost, constructability, operational, maintenance, and compliance analyses.
(10) Written certification that the submission has been internally reviewed and coordinated among all applicable design disciplines.
The Contractor may not begin the 65% design stage until the COR provides written technical acceptance of the 35% submission.
Phase #2 – Construction Documents, 65%, 95%, and 100%: Following the Government’s written selection of a design alternatives, the Contractor must develop the selected alternative into complete, coordinated, code-compliant, and constructible contract documents. The Contractor must provide all architectural, civil, structural, mechanical, plumbing, electrical, fire-protection, accessibility, surveying, geotechnical, utility-coordination, and other professional services required to complete the design.
Each 65, 95, and 100 percent submission must include, as applicable:
(1) Coordinated drawings for all design disciplines.
(2) Full Technical specifications. Meet VA standards.
(3) Design calculations and supporting analyses.
(4) Code and accessibility compliance documentation.
(5) Updated construction phasing and logistics plan.
(6) Updated itemized construction cost estimate with all divisions.
(7) Updated design and construction schedule.
(8) Utility investigation and coordination documentation.
(9) Constructability and interdisciplinary coordination review documentation.
(10) Required models, renderings, or other visual representations.
(11) A consolidated comment-response matrix documenting the disposition of every previous Government review comment.
(12) Written certification that the submission has been internally reviewed, quality controlled, and coordinated among all applicable design disciplines.
The Contractor may not proceed to the next design stage until the COR provides written technical acceptance of the current submission. Written technical acceptance does not authorize a change to contract price, schedule, scope, or other contract terms. Only the Contracting Officer may modify the contract.
Submission Format and Copies
The Contractor must provide each submission electronically in searchable PDF format and in the editable native formats used to prepare the drawings, specifications, calculations, estimates, schedules, and other deliverables. Files must be complete, legible, properly indexed, and free of passwords or other access restrictions. At the COR’s request, the Contractor must provide the number of full-size or reduced-size hard-copy sets and additional PDF copies specified by the COR, at no additional cost to the Government. Electronic and hard-copy versions must be identical.
Government Review and Resubmission
The Government will provide written review comments within 21 calendar days after receipt of a complete submission for each percentage. The review period begins only after the COR determines that the submission contains all required deliverables and is sufficiently complete for review. VA identification or VA questions of an incomplete submission does not constitute technical acceptance and does not extend the contract completion date.
The Contractor must resolve every VA comment and submit a completed comment-response matrix with the next submission. If directed by the COR, the Contractor must revise and resubmit the affected design package within 10 calendar days, or within another period established in writing by the Contracting Officer or COR. COR review, comments, or technical acceptance does not constitute final Government acceptance of the work.
Contractor Responsibility
The Contractor remains fully responsible for the accuracy, adequacy, completeness, coordination, constructability, quality, and regulatory compliance of all investigations, designs, all calculations, drawings, specifications, models, cost estimates, schedules, and other deliverables. VA review, comment, technical acceptance, approval, or failure to identify an error does not waive any contract requirement or relieve the Contractor of responsibility for errors, omissions, conflicts, deficiencies, code violations, or required corrective work.
The Contractor must correct deficiencies attributable to its performance at no additional cost to the Government and without an extension of the contract schedule, except when authorized in writing by the Contracting Officer under the contract’s applicable changes provisions and clauses.
SCHEDULE FOR DESIGN BUILD:
ACTION CALENDAR
DAYS
AFTER …
Kick-Off Mtg/Preliminary Site Review 10 Notice to Proceed
35% Design Submittal & Mtg 28 Kick Off Meeting
35% VA Comments 28 35% Design Submittal & Mtg
65% Design Submittal & Mtg 21 35% VA Comments *Start Site Preparation for Trailer after 65% turn in
65% VA Comments 28 65% Design Submittal & Mtg
100% Design Submittal & Mtg 21 65% VA Comments
100% VA Comments 28 100% Design Submittal & Mtg
100% Final Documents Submittal 15 100% VA Comments
*Start Site Preparation for Trailer after 65% turn in 10 *65% Design Submittal & Mtg (Note Schedule Overlap)
Trailer Ready for Occupation 10 Start Site Preparation for Trailer Parking Project Area is Available for Construction Activities. 5 Trailer Ready for Occupation
Project Area Construction Completed and Operational. 150
Parking Area is Available for Construction Activities. Piping, reservoir, and water tower installed.
Vacate and Decommission Trailer 10 Certify Compliance and Commissioning
Contract End Date 7 Remove Trailer from Site and Return Site to Pre-existing Condition
TOTAL CONSECTUTIVE DAYS 330
GENERAL REQUIREMENTS:
A. SITE INVESTIGATION: VA-provided as-built drawings and other existing documentation are provided for reference only. The Design-Build Contractor team is responsible for independently verifying all existing field conditions and for locating and confirming all aboveground and underground utilities, structures, and site features that may be affected by the project. The Contractor bears full responsibility for the accuracy and completeness of its site investigation and field verification efforts and for identifying and resolving utility conflicts and existing conditions affecting the design or construction of the project.
B. DEMOLITION: The project demolition work may include some architectural, structural, mechanical/ plumbing, electrical, and removal of existing equipment. Work inside and outside of the construction project area(s) may need to be phased and completed as part of this project.
C. GEOTECHNICAL / CIVIL: Evaluation of existing and post construction rainwater run off / drain.
D. STRUCTURAL: The Design-Build Contractor is responsible for evaluating all existing structures and structural systems affected by the project and determining with VA COR input and final approval, the extent of structural analysis required. All new structural work and modifications to existing structural elements must be designed, analyzed, and stamped by a licensed Professional Engineer registered in the project state. The Contractor must perform and provide all calculations, analyses, and supporting documentation necessary to verify the adequacy of existing structures and the effects of all new, revised, temporary, and permanent loads resulting from the project.
E. ARCHITECTURAL: The Design-Build Contractor is responsible for independently verifying all existing elevations, building locations, dimensions, accessibility features, and other architectural conditions affecting the project. Existing drawings are provided for reference only and may not be relied upon without field verification. The Contractor bears full responsibility for the accuracy and completeness of all measurements, site conditions, and architectural information incorporated into the design documents.
F. INTERIOR DESIGN: N/A
G. PLUMBING: The Design-Build Contractor is responsible for evaluating existing plumbing, drainage, stormwater, and underground utility systems to the extent affected by the project. Modifications, relocations, replacements, or additions to these systems may be required to support the proposed design and achieve a complete, coordinated, and code-compliant project. The Contractor is responsible for identifying and incorporating all costs etc. required for plumbing and drainage improvements necessary to support the final design.
H. HVAC (Heating, Ventilating & Air Conditioning): N/A I. ELECTRICAL: The Design-Build Contractor is responsible for evaluating all existing electrical systems, equipment, and infrastructure affected by the project. The Contractor must identify electrical conflicts, capacity limitations, and required modifications and incorporate all relocations, replacements, additions, and upgrades necessary to support the proposed design. The Contractor must perform and provide all electrical load, demand, feeder, and equipment-sizing calculations required for the project and ensure the final design is complete, coordinated, and compliant with the latest adopted edition of the National Electrical Code (NEC), VA design criteria, and all other applicable codes and standards.
J. EQUIPMENT: The Design-Build Contractor is responsible for coordinating with equipment manufacturers and suppliers to obtain all information necessary to complete the design. Applicable manufacturer requirements, drawings, schematics, utility requirements, and installation criteria must be incorporated into the construction documents. The Contractor is responsible for identifying and clearly detailing all connections, interfaces, and modifications between existing and proposed equipment and systems necessary to provide a complete, coordinated, and operational project.
K. CERTIFIED INDEPENDENT THIRD-PARTY (CITP) SAFETY REVIEW: The Contractor must obtain an independent Fire and Life Safety review of the final design documents from a qualified Certified Independent Technical Peer (CITP) experienced in healthcare facility design and code compliance. The reviewer must be independent of the design team and must be a licensed Fire Protection Engineer (FPE) or Registered Professional Engineer with demonstrated expertise in NFPA codes and standards, VA Fire Protection Design Manuals, healthcare occupancies, and life-safety compliance. The review must verify compliance with all applicable NFPA codes and standards, VA fire and life safety requirements, and other applicable regulatory requirements. A signed certification letter and written review report documenting all findings, comments, and recommendations must be submitted on the reviewer's company letterhead. The Contractor must resolve and incorporate all review comments into the final design documents before final submission. VA review, acceptance, or approval does not relieve the Contractor of responsibility for the completeness of the review or compliance with applicable fire and life safety requirements.
L. ENERGY & RESOURCE CONSERVATION: The Design-Build Contractor is responsible for incorporating energy- and resource-efficient systems, equipment, and materials into the project whenever applicable. New and replacement equipment must comply with applicable Federal energy and sustainability requirements, VA design criteria, and Energy Star requirements where available. The design must incorporate all applicable energy conservation measures required by code, regulation, and VA standards.
Any exception requires prior written approval from the COR
M. ADDITIONAL DOCUMENTATION: The Design-Build Contractor is responsible for providing all calculations, analyses, reports, studies, code reviews, and supporting documentation necessary to substantiate the design and demonstrate compliance with contract requirements. Each design submission must include complete calculations and sizing analyses for all new, modified, and affected electrical, plumbing, drainage, utility, and structural systems, as applicable. Computer-generated calculations must include documented assumptions, methodologies, inputs, and outputs sufficient for independent review.
The Contractor must provide a code analysis identifying all applicable codes, standards, and design criteria and demonstrating compliance with each requirement. All documentation must be complete, coordinated, signed and sealed when required by law, or VA requires it, and submitted with the applicable design package. The Contractor bears full responsibility for the accuracy, completeness, and technical adequacy of all submitted documentation. Electronic PDF copies and hard-copy documentation requests must be provided upon request by the COR.
N. DESIGN SPECIFICATIONS / REQUIREMENTS: The Design Build firm will review all pertinent NRC recommendations and requirements applicable to this project, in addition VA construction criteria, standard details, specifications and recommendations will also be incorporated into the design of this project. The Design Build team may obtain copies of the complete VA Design Guides, Design Manuals, & other resources from the VA Facilities Management Technical Information Library at www.va.gov/facmgt/standard/standard.htm. The VA is mandated to follow the most stringent rules, codes & etc. when economically feasible; therefore, the Design Build team must also review all applicable VA, Federal, State, County, City, Industry design guides, codes, standards, regulations and policies.
O. ACCURACY OF FACILITY PROVIDED DATA: All drawings, as-built records, surveys, utility information, and http://www.va.gov/facmgt/standard/standard.htm other documents provided by the VA are furnished for reference only. The Design-Build Contractor is responsible for independently verifying all existing site conditions, dimensions, elevations, utility locations, and other information necessary to complete the design. The Contractor must base the design on verified field conditions and measurements and may not rely solely on Government-furnished as-built drawings or other existing documentation.
At each design submission, the Contractor must provide a marked-up set of the available as-built drawings for each discipline identifying discrepancies between documented and actual field conditions. The Contractor bears full responsibility for the accuracy and completeness of all field verification activities and for incorporating verified conditions into the design documents.
P. DRAWINGS: The Design Build team shall provide electronic copies of drawings at each review step.
The standard drawing size will be ARCH E1 [30” x 42”]. The format to be used in creating the CAD drawings (i.e. layer/level structure, fonts, font sizing, file naming conventions, etc) is the latest edition of the National CAD Standard {www.nationalcadstandard.org}. Drawings to be drawn from the VA’s “As Built” drawings updated by site verification, not scanned reproductions.
Q. CONSTRUCTION SPECIFICATIONS: The Design Build team may obtain a copy of the complete VA Construction Specifications from the VA Facilities Management Technical Information Library at web site/page: www.va.gov/facmgt/standard/standard.htm. The Design Build team must provide the final typed specifications on CD-ROM, t he format must be doubled-spaced, left justify, 1-sided, laser quality, and Arial-size 11 font. The project title and number will be on each page, top right-hand corner within the header section. The final copy will be in a purple, 3- “D” ring loose-leaf binder, with identification labels on the binding & cover so the project title and number are readily visible and with tabbed dividers between each specification section.
R. ELECTRONIC DOCUMENTS: Information requested in electronic form (digital, CD-ROM, etc) will be in the following formats:
1. Drawings and details: AutoCAD 2007
2. Written documents: Microsoft Word 2003
3. Spread sheets, charts, graphs: Microsoft Excel 2003
4. Reproductions of manufacturers specifications, blueprint “mark-ups”, pictures and similar items:
Adobe PDF (most current version).
5. CD-ROM’s will be “write-protected” and clearly labeled with Project Number, Project Name, Date and Contents before submission to the VA.
S. PROJECTED TIME FRAMES: Approximate time frames are projected to be:
(1) Begin Evaluation & Design Development – Notice to Proceed (NTP)
(2) First Submission Design Development (DD1- 35%) – NTP + 6 wks
(3) Review Meeting and Return DD1 Submission NTP + 7 wks
Phase 2 - Contract Document Stage “CD’s”
(4) Begin Contract Drawings NTP + 7 wks
(5) Second Submission Contract Documents (CD1-65%) NTP + 10 wks
(6) Review Meeting and Return Second Submission NTP + 11 wks
(7) Third Submission Contract Documents (CD2-95%) NTP + 14 wks
(8) Review Meeting and Return Third Submissions NTP + 15 wks
(9) Fourth Submission Final Contract Documents (CD3-100%) NTP + 16 wks
T. ESTIMATE SUBMISSION REQUIREMENTS: The Design Build team must submit a construction cost from an independent firm for all trade disciplines with the drawings at each project submission. This estimate
DRAFT
http://www.nationalcadstandard.org/ http://www.va.gov/facmgt/standard/standard.htm will show the cost of construction most likely to be reflected by the construction contractors' bids, if the bids were submitted on the same date as the estimate. The level of detail for this estimate must be consistent with the degree of completeness of the drawings being submitted. Simply shown, it must be priced; if it is shown in detail, it must be priced in detail. For detailed elements, "lump sum" or "allowance" figures will not be acceptable. Estimates must be broken down by AIA divisions. The first page will be a summary page showing deductive bid items, contractor mark-ups, overhead, profit, and bonding to reflect true construction costs.
U. ASBESTOS and LEAD: If asbestos-containing materials (ACM), lead-containing materials, or other hazardous materials are suspected or encountered within the project area, the Design-Build Contractor must notify the CO and COR immediately. Evaluation must be performed by a qualified Industrial Hygienist and, when required by applicable regulations, a California-licensed Asbestos Consultant. No investigation, disturbance, abatement, or additional work related to hazardous materials may proceed without prior written authorization from the CO and COR.
V. REVIEW MEETINGS: The Design Build contractor is required to attend a design review meeting after each submission during the design process. Design review meetings are estimated to require three (3) hours and include sufficient expertise to provide concise information regarding the information and drawings submitted.
III. PHASE 1 DESIGN DEVELOPMENT (DD)
A. FIRST REVIEW: [Design Development (DD-1) Submission - 35% complete.]
1. Submittals: Two (2) copies of preliminary plans (standard size), two (2) copies of cost estimates furnished by an independent firm; marked-up “as built” drawings; one (1) copy of calculations, computations, and engineering data. Above documents will also be provided in electronic format in the form of two (2) CD-ROM’s.
2. Specifications: Submit a cover letter and a list of VA master specifications intended for use on this project.
3. Drawings: The Design Build contractor will provide a full set of project drawings showing the scope and plan for each option and disciplines involved to the completion level described below.
a) All Disciplines:
• Demolition: Show what will remain during construction. Show means of protection.
• Provide one drawing to include Interim Life Safety Code Plan, Phasing Plan, Security and environmental controls/barriers.
• Show and identify existing conditions, sections, elevations, details, dimensions, and capacities. The Design Build contractor must site verify all items.
• Show items to be removed, all disciplines.
• Provide symbol sheets and explanation of detail symbols used.
b) Site :
• Provide a campus site plan reflecting the locations of all building structures, roadways, and parking areas.
c) Architectural:
• Show a single line layout for all floors and roof areas with double line for exterior walls, and single line layouts for buildings, structures, roads, parking areas/spaces, and sidewalks at a scale not less than 1/8” = 1’-0”.
• Show floor plans that include rooms, windows, corridors, closets, mechanical, electrical, and other spaces. All rooms and spaces shall be labeled.
d) Civil/Structural: (if applicable)
• Show existing conditions and how new work interfaces.
• Show locations, layout, elevations and details. Provide preliminary loading calculations.
e) Plumbing:
• Show locations of existing water lines, to include fire protection and sanitary drain lines. Show all valves and all buildings/areas that may be affected by a shutdown.
• Show preliminary relocations and details of any utilities affected by the (3) proposed options.
f) HVAC:
• N/A
g) Electrical:
4. Show any existing electrical systems within the project area. Where applicable.
5. ESTIMATES: Submit one (1) printed copy of construction cost estimate and 2 digital copies on CD-ROM, from an independent firm (for all disciplines).
END OF PHASE 1 - DESIGN DEVELOPMENT (DD)
IV. PHASE 2 - CONTRACT DOCUMENTS (CD)
A. SECOND REVIEW: [First Contract Document Submission (CD-1) - 65% complete.]
1. Submittals: One (1) copy of calculations, computations, and engineering data for the basis of design. Two (2) copies of drawings (standard size). Two (2) copies of specifications with one original in a loose-leaf binder. Two (2) copies of cost estimate.
Updated as-built drawings for each discipline. Also provide 2-CD ROM’S with all submittal data. Return all marked up documents from the previous submissions.
2. Specifications: Submit original and one (1) copy of the marked-up sections to suit the project. Editing and mark-ups must easily identify modifications, deletions, and insertions.
"Catch-all" terms and generalizations must be avoided. Items not relative to the project shall be edited out. The specifications must be substantially complete as to content, checked and coordinated so that only an overall review will be necessary at the final working drawing submission. Original copy is to be in loose-leaf binder. In addition, provide two (2) copies on CD-ROM. Specifications may be placed on same CD’s as submittals.
3. Drawings: The drawings will be 65% complete and consist of the following:
a) All disciplines:
(1) Demolition work
(2) Show and identify existing, verified dimensions, conditions, and interfacing
(3) Show items to be removed
(4) Provide symbol sheets and explanation of symbols used
(5) Provide one plan to show Interim Life Safety / Fire Protection Plan, Phasing Plan, Security, and Environmental controls/barriers
(6) General Notes
b) Site:
(1) Ensure the contractor is aware of the limited parking and material staging areas at this location.
(2) Show the limits of construction area
(3) Provide a general site plan indicating the location of all Buildings, perimeter streets and parking lots.
c) Architectural:
(1) Floor plans, details and schedules shall be 65% complete
(2) Draw elevations, no less than 1/8” = 1’-0” scale. As necessary, show height dimensions and materials. Indicate any fire and smoke partitions
(3) Show and clearly identify connections of new work to old work
(4) Show general notes, door & hardware schedule, room finish schedule
(5) Show reflected ceiling plan
(6) Show location of new equipment
(7) Show environmental controls; location of any protective / dust barriers and appropriate signage
d) Civil/Structural:
(1) Show existing and new structural work and support details
(2) Determine the added floor loading, and show structural modifications, if required
e) Plumbing:
(1) Clearly show all existing, relocated, and new water lines, to include fire protection and sanitary drain lines. All piping shown shall include sizes
(2) Show temporary and permanent relocations or modifications
(3) Clearly show all points of connections for new water and drainage systems, to include connection and support details.
(4) Show all water, fire protection, and drainage piping, including type and sizes. Show all new valves, to include isolation, check, and backflow preventers
(5) Provide one-line diagram of all systems, and if a fire protection system (sprinkler system) is required, provide a complete plan layout with all required components and flow calculations
f) HVAC: N/A
g) Electrical:
1) Show all existing and/or new conduits, wire sizes, points of origination and termination, control/signal wiring and all other items necessary.
2) Provide electrical one-line power and lighting diagrams, as required.
3) Provide one-line fire alarm system diagram, as required.
4) Provide panel schedule, complete with circuit breaker sizes and equipment designation, as required.
5) Provide an equipment schedule for all equipment showing manufacturer or basis of design, voltage, amperage, phase, conduit size, and conductor size, as required.
6) Lighting must be energy efficient, fluorescent fixtures will use T-8 straight tubes, no U or circular tubes, if required.
4. Phasing: Present proposed phasing plans that will accomplish the construction work with a minimum of disruption to the normal operations of the hospital.
5. Code: Provide an investigation and explanation of any applicable regulatory/code requirements incorporated into the design. Furnish a copy of each code quoted or used in the design if requested by government
6. Estimate: See "Estimate Submission Requirements", Section III, Item T D. THIRD REVIEW: [Second Contract Document (CD-2) Submission 95%.]
1. Submittals: Two (2) copies of drawings (standard size). Two (2) copies of specifications, one (1) copy of updated cost estimates, and updated marked-up as-built drawings. Also provide 2-CD ROM’S with all submittal data.
2. Specifications: The specifications must be in final draft, completely edited and checked.
3. Drawings: The drawings will be 100% complete in every respect for all applicable disciplines.
b) All disciplines:
(1) Demolition work
(2) Show and identify existing, verified dimensions, conditions, and interfacing
(3) Show items to be removed
(4) Provide symbol sheets and explanation of symbols used
(5) Provide one plan to show Interim Life Safety / Fire Protection Plan, Phasing Plan, Security, and Environmental controls/barriers
(6) General Notes
d) Site:
(1) Ensure the contractor is aware of the limited parking and material staging areas at this location.
(2) Show the limits of construction area
(3) Provide a general site plan indicating the location of all Buildings, perimeter streets and parking lots.
e) Architectural:
(1) Floor plans, details and schedules
(2) Draw elevations, no less than 1/8” = 1’-0” scale. As necessary, show height dimensions and materials. Indicate any fire and smoke partitions
(3) Show and clearly identify connections of new work to old work
(4) Show general notes, door & hardware schedule, room finish schedule
(5) Show reflected ceiling plan
(6) Show location of new equipment
(7) Show environmental controls; location of any protective / dust barriers and appropriate signage
f) Civil/Structural:
(3) Show existing and new structural work and support details
(4) Determine the added floor loading, and show structural modifications, if required
g) Plumbing:
(6) Clearly show all existing, relocated, and new water lines, to include fire protection and sanitary drain lines. All piping shown shall include sizes
(7) Show temporary and permanent relocations or modifications
(8) Clearly show all points of connections for new water and drainage systems, to include connection and support details.
(9) Show all water, fire protection, and drainage piping, including type and sizes. Show all new valves, to include isolation, check, and backflow preventers
(10) Provide one-line diagram of all systems, and if a fire protection system (sprinkler system) is required, provide a complete plan layout with all required components and flow calculations
f) HVAC: N/A
h) Electrical:
7) Show all existing and/or new conduits, wire sizes, points of origination and termination, control/signal wiring and all other items necessary
8) Indicate all circuiting of all systems on drawings, and show load balancing, if required.
9) Show final sizes, ratings, feeders, and identification of all electrical equipment, if applicable.
10) Provide electrical one-line power and lighting diagrams, if required.
11) Provide one-line fire alarm system diagram, if required.
12) Provide panel schedule, complete with circuit breaker sizes and equipment designation, if required.
13) Provide an equipment schedule for all equipment showing manufacturer or basis of design, voltage, amperage, phase, conduit size, and conductor size, if applicable.
4. Estimate: See "Estimate Submission Requirements", Section III, Item T. The estimate will be presented in complete form to reflect quantitative material cost, labor costs, and overhead and profit anticipated on date of bid opening.
D. FINAL SUBMISSION 100%: After material of the Third Review has been reviewed, the Design Build team shall make necessary changes to incorporate the review comments and furnish the following:
1. Specifications: Two (2) copies of typed specifications double-sided, bound
2. Drawings: Two (2) complete sets of blueprints (standard size) ready to issue for competitive bid
3. Certified Independent Third-Party (CITP) Safety Review comments on final design
4. One set of signed and sealed original Mylar drawings with each discipline separately sealed
5. 2-CD ROM’S with data listed above
END OF PHASE 2 - CONTRACT DOCUMENTS (CD)
VI. CONSTRUCTION PERIOD OF SERVICES (CPS):
A. The Design Build contractor team must review and respond to all design related RFI’s within (14) calendar days, review all submittals for the project within (14) calendar days, and perform acceptance testing on behalf of the VA for all building and utility systems.
B. The Design Build contractors’ team will review, evaluate, and respond to all contractor change order requests and value engineering proposals. The VA reserves the right for final approval/disapproval or acceptance of any modification.
C. As requested by the VA, the A/E from the Design Build contractors’ team will be required to make weekly site visits to monitor, inspect and review all aspects of the project to ensure compliance with the construction documents and other regulatory requirements. Detailed Written Reports will be submitted for all site visits.
D. At project completion, the Design Build contractors’ team will incorporate the “as-built” drawings from the contractor and furnish an updated set of CD’s and a set of "record" Mylar drawings. It is permissible for the A/E from the Design Build team to require the Construction team to provide the marked-up (red-line) "as-built" drawings.
VII. ADDITIONAL SERVICES:
If additional services are necessary to be performed by consultants not already covered in this statement of work (SOW), the contractor is required to submit criteria for the work to be performed to the VA Contracting Officer (CO) as soon as possible for a decision. Upon approval of the criteria by the Contracting Officer, submit proposals and qualifications of at least three (3) firms being considered for the work in accordance with the contract procedures in the contract, together with a proposal from the recommended firms and a brief justification for its selection, for VA final decision and approval.
Meeting Management and Meeting Minutes The Design-Build Contractor team is responsible for scheduling, coordinating, and facilitating all project progress meetings, design review meetings, and other meetings required to support performance of this contract. Meeting invitations, agendas, supporting materials, and meeting logistics must be coordinated with the VA COR and distributed to all required attendees in advance of each meeting.
The Design-Build Contractor team must prepare and distribute draft meeting minutes for all meetings conducted with the Department of Veterans Affairs (VA). Meeting minutes must accurately document attendees, discussions, decisions, action items, responsible parties, and due dates. Draft meeting minutes must be submitted to the COR within seven (7) calendar days after the meeting date.
Meeting minutes do not become official project records until reviewed and approved in writing by the COR. The Contractor must incorporate all COR/VA revisions and distribute the final approved meeting minutes to all meeting participants. Meeting Minutes must reflect true and accurate discussion of progress.
Audio recordings, video recordings, transcript services, Super intelligence (SI) meeting transcription tools, and any other form of meeting recording are prohibited unless specifically authorized in writing by the Contracting Officer (CO). The approved meeting minutes constitute the official record of project meetings.
The Contractor is responsible for maintaining all approved meeting minutes as part of the project record and submitting copies upon request by the COR.
Site-Specific Requirements – VA Central California Health Care System (Fresno) The VA Central California Health Care System (VACCHCS) Fresno campus is an active healthcare facility operating 24 hours per day, 7 days per week. The Design-Build Contractor team must perform all work in a manner that minimizes disruptions to patient care, facility operations, staff, visitors, emergency services, and campus traffic. Construction activities must be coordinated, planned, phased, and coordinated to maintain safe access to buildings, pedestrian routes, emergency egress paths, fire lanes, and operational utility systems at all times.
Work generating excessive noise, vibration, dust, odors, utility interruptions, or other operational impacts will be restricted to off-hours, weekends, or other periods designated by the VA. The Contractor is responsible for coordinating all disruptive activities with the COR and facility stakeholders at least 24 hours ahead of time or as soon as known and for incorporating approved restrictions into the project schedule.
Any activity affecting utilities, life-safety systems, fire alarm systems, fire protection systems, medical gas systems, telecommunications systems, roadways, pedestrian pathways, building access, or facility operations requires a written Method of Procedure (MOP). The Contractor must submit the MOP to the COR for review and approval a minimum of fourteen (14) calendar days before the planned activity unless otherwise approved by the COR. Work may not proceed until written approval is received. MOPs must identify the scope of work, affected systems, outage duration, contingency measures, restoration procedures, responsible personnel, and any required testing or commissioning activities. See Specifications for attached.
Planned utility shutdowns, road closures, building access restrictions, and other operational interruptions must be coordinated with the COR and affected facility personnel. Utility outages are generally limited to periods approved by the VA and may be restricted to evenings, weekends, Federal holidays, or other times designated by the Government/VA. The Design-build Contractor is responsible for providing all temporary services, notifications, protection measures, testing, restoration activities, and personnel necessary to maintain facility operations and patient safety throughout the outage period.
The Design-build Contractor is responsible for implementing all required infection control, dust control, noise mitigation, traffic control, pedestrian protection, site security, and safety measures necessary to protect patients, staff, visitors, and Government/VA property throughout the duration of the project.
Government review or approval of schedules, MOPs, phasing plans, or shut down requests does not relieve the Contractor of responsibility for maintaining safe and continuous facility operations.
Construction Working Hours The VA Central California Health Care System (VACCHCS) Fresno campus is an active healthcare facility operating 24 hours per day, 7 days per week. Unless otherwise authorized in writing by the Contracting Officer (CO), construction activities are limited to Monday through Friday, 7:00 a.m. to 4:30 p.m. Pacific Time, excluding Federal holidays identified by the U.S. Office of Personnel Management (OPM)( https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/ ).
Work outside of these hours, including evenings, weekends, and Federal holidays, requires prior written approval from the CO and COR and may be required for activities that affect patient care, facility operations, excessive noise, utilities, roadways, pedestrian access, life-safety systems, or other critical functions. The Design-build contractor is responsible for coordinating all such work with the COR and for incorporating any approved restrictions into the project schedule.
The Design Build Contractor must include all costs associated with off-hours, weekend, holiday, phased, or restricted-access work in its proposal. Approval to perform work outside normal working hours does not entitle the Contractor to additional compensation, time extensions, or other contract adjustments. Activities generating excessive noise, vibration, dust, odors, utility interruptions, or traffic impacts may be further restricted as directed by the VA.
Construction Submittals The Contractor is responsible for preparing, reviewing, approving, and submitting all shop drawings, product data, samples, manufacturer literature, test reports, certifications, commissioning documentation, and other submittals required to support construction. VA review does not relieve the Contractor of responsibility for the accuracy, completeness, coordination, or contract compliance of any submittal.
Project Closeout Before final acceptance, the Contractor must provide complete record drawings, operation and maintenance manuals, warranties, test reports, training records, commissioning documentation, permit closeout records, final inspections, and all other turnover documents required by the contract to the COR.
Contractor must complete a final acceptance inspection form provided by the VA, however use of an alternate form is also acceptable as long as its approved by the COR instead. Final payment will be withheld until all closeout requirements are complete and accepted.
Warranty The Contractor is responsible for correcting defects in design, materials, equipment, workmanship, and installation identified during the applicable warranty period. Warranty periods begin upon Government acceptance in writing unless the contract establishes a different commencement date.
Utility Outages and Service Interruptions Any interruption affecting patient care, building operations, electrical service, water, sanitary systems, fire protection, fire alarm, communications, security, or other critical systems requires an approved Method of Procedure (MOP) and prior written authorization. The Contractor must provide temporary services, contingency measures, notifications, testing, and restoration at no additional cost unless otherwise authorized by the CO.
Contractor Quality Control (QC) Plan The Contractor must establish and maintain a project-specific Quality Control Program covering both design and construction. The program must include interdisciplinary design reviews, submittal control, preparatory and follow-up inspections, testing oversight, deficiency tracking, and verification that work complies with the contract before presentation to the VA.
Project-Specific Safety Requirements Before construction begins, the…