SOW 5-1-26 DRAFT Install Parking Shades.pdf
PDF 828 KB Posted
- Solicitation number
- 36C26126R0055
About this file
This is a Statement of Work (SOW) for design-build services for the VA Southern Nevada Healthcare System (VASNHS) located at 6900 Pecos Road, North Las Vegas, Nevada. The project (593-26-306) involves installing parking shade canopies and reconfiguring parking lots to address unsafe pedestrian conditions and extreme heat exposure affecting patients, staff, and Veterans.
The Design-Build contractor must provide all architectural and engineering (AE) services, design, materials, supplies, equipment, investigations, project supervision, construction period services, and complete construction. Design must comply with VA Design Guides, Design Criteria, and VA Master Specifications at the Technical Information Library (TIL), as well as International Building Codes (IBC), National Fire Protection Association (NFPA), and OSHA standards. The project covers four parking lots: Lot A (127 uncovered stalls), Lot D (466 uncovered stalls), Lot E (177 uncovered stalls), and Lot F (178 uncovered stalls). Technical specifications include minimum 12-foot clearance under canopies, maximum 27-foot canopy width, 5-degree roof slope, 18-foot by 9-foot standard stall dimensions, and 24-foot two-way aisles. Lightning protection and corrosion-resistant finishes matching the campus color palette are required.
The scope includes parking lot reconfiguration incorporating protected pedestrian paths, speed bumps at drive inlets, striped crosswalks with LED Rectangular Rapid Flashing Beacon (RRFB) signage, targeted infill in landscape islands, and flagpole roundabout reconfiguration. All work must maintain hospital operations with phased lot closures minimized to one lot at a time. The overall Period of Performance runs approximately 515-555 calendar days (17-18.5 months) with parallel design and construction activities. The design and preconstruction phase targets 120 calendar days to 65% completion, followed by a separate construction Notice to Proceed with 320-340 calendar days for completion. Design submittals are required at 35%, 65%, 95%, and 100% phases, with supporting technical reports including geotechnical analysis, structural calculations, drainage analysis, utility survey, and parking lot reconfiguration plans. Cost estimates must break out by individual parking lot with prioritized implementation lists and deduct alternates for infill parking stalls. Minimum investigative site visits include topographic verification, utilities coordination, and geotechnical coordination. Construction period services require 14-calendar-day response times for RFIs, submittals, and field clarifications. All contractor and subcontractor personnel must obtain Non-PIV Cards through a process taking 30-45 days, with fingerprinting conducted at the facility's PIV Office. Normal work hours are 8:00 AM to 4:30 PM, Monday through Friday, excluding Federal Holidays.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26126R0055.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
For Design-Build Services
Project 593-26-306
Install Parking Shades & Reconfigure Lots
VA Southern Nevada Healthcare System
6900 Pecos Road, N. Las Vegas, NV 89086
1.0. PROJECT SUMMARY & INTENT
1.1. The VA Southern Nevada Healthcare System (VASNHS) campus in North Las
Vegas experiences two critical challenges impacting patient/staff safety and comfort:
1.1.1. Unsafe Pedestrian Conditions: Existing parking lots require pedestrians to navigate active driving aisles and cross the Loop Road without adequate protection. Current layouts lack sufficient dedicated walking paths, traffic-calming measures, and high-visibility crossings, creating conflict points between vehicles and pedestrians. These conditions increase the risk of accidents and impede ADA accessibility for Veterans and visitors with mobility limitations.
1.1.2. Exposure to Extreme Heat: The campus is located in a desert climate where summer temperatures routinely exceed 100°F. Veterans and staff walking from vehicles to the facility face prolonged sun exposure, elevating the risk of heat exhaustion and heat stroke, particularly for elderly and medically vulnerable populations.
1.2. This Design-Build (DB) project will deliver a comprehensive solution by using parking lot improvement documents (see Section 10.0 Reference Material) as basis of design to reduce vehicle-pedestrian conflicts, enhance accessibility, and protect Veterans and staff from extreme heat, supporting VA’s mission to provide a safe, accessible, and comfortable healthcare environment.
1.2.1. The Design Build (DB) contractor must furnish:
1.2.1.1. Design: All design Architect and Engineering (AE) services, materials, supplies, equipment, investigations and project supervision, and construction period services associated with this contract. Design must meet Veteran’s Affair (VA) Design
Guides and Design Criteria and VA Master Specifications at the Technical Information Library (TIL) (www.cfm.va.gov/TIL), including providing parking that meets VA parking requirements, physical security design guide requirements, and access requirements per VA Design guide. Design shall follow all current applicable codes, including, but not limited to, International Building Codes (IBC), National Fire Protection
Association (NFPA), and Occupational Safety and Health
Administration (OSHA).
1.2.2. Construction: All labor, materials, supervision, and administration for the complete construction of the project.
1.2.3. The Design Build Contractor must consider the site in its entirety and develop designs for parking shade canopies and reconfiguration of lots to include pedestrian walkways that fit within the site constraints.
2.0. SCOPE
The DB contractor’s AE team will design and construct shade canopies and associated parking lot improvements as follows, in accordance to VA Design Guides, Design Criteria, and VA
Master Specifications found in the TIL:
2.1. General Basis-Of-Design
The following information shall be verified by the DB contractor’s AE via provided as-builts and site investigation. Intent of information will be to match existing campus canopy appearance, proportions, and detailing as described in
Assignment 44 – Conceptual Design for Carports and 593-14R-200 – Existing
Carport Design; omit PV modules and optimize canopy dimensions & footings for shade-only loading.
2.1.1. Minimum clearance: 12 ft under all canopies.
2.1.2. Max canopy width: 27 ft per section; interior modules approx. 40 ft long;
perimeter stalls, see below.
2.1.3. Roof slope: 5° toward south for drainage.
2.1.4. Stall dimensions: 18 ft × 9 ft typical; maintain VA standard geometry and
24 ft two-way aisles.
https://vaww.aams.ecms.va.gov/AAMS_Production/DAV/dwhyyyymyy015yvy/www.cfm.va.gov/TIL
2.1.5. Lightning Protection: Ensure new shade canopies have lightning protection designed for implementation in construction.
2.1.6. Aesthetic: The aesthetic must be pre-approved by the VA Facility
Engineering Department and match existing canopy system aesthetic but optimize for shade-only loading.
2.1.7. Perimeter stalls: Use cantilevered systems with footings on one side (as opposed to centered like existing carports) to minimize impacts to loop roads and utilities; AE to confirm feasibility and propose alternatives as needed.
2.1.8. Parking Lot Reconfiguration – Infill & Pedestrian Safety:
Use Assignment 21 – Draft Schematic Design and Report, Assignment 44
– Parking Study, and ED Parking Expansion for basis-of-design. For lots that do not have detailed drawings associated, apply the same basis-of-design details for implementation into those lots.
2.1.8.1. Incorporate protected pedestrian paths, speed tables, and/or crosswalks where canopy installation affects walkways.
VA Request: In lieu of speed tables in parking lots, implement striped pedestrian paths with speed bumps at drive inlets to enforce safe speeds. Implement this combination where feasible in all lots and determine best locations for speed bumps in relation to striped crossings. See figure below for example:
Figure 1: (Left) Shown in Assignment 21 Report; (Right) Design Intent Described in 2.1.8.2.
2.1.8.2. Implement targeted infill in feasible landscape islands, between-lot areas, and ED parking lot preserving stall/aisle standards, slopes, and positive drainage. Maintain established runoff paths and smooth grade transitions to avoid ponding.
2.1.8.3. Infill and parking stall additions should include shaded canopies.
2.1.8.4. Assess flagpole roundabout on northeast side of campus
(between lot A and B). Design reconfiguration of roundabout for better pedestrian and vehicle flow.
2.1.8.5. Ensure compliance with PG-18-10, ADA, ABAAS, and FHWA
RRFB signage standards.
2.2. Parking Lots and Coverage Targets
AE shall verify counts and layout during design survey(s):
2.2.1. Lot A: 127 uncovered stalls (84 perimeter, 43 interior).
2.2.2. Lot D: 466 uncovered stalls (117 perimeter, 349 interior).
2.2.3. Lot E: 177 uncovered stalls (101 perimeter, 76 interior).
2.2.4. Lot F: 178 uncovered stalls (63 perimeter, 115 interior).
2.3. Structural and Site Considerations
2.3.1. Design foundations and structural systems per local wind/seismic codes and VA standards; consider geotechnical recommendations for pier embedment and uplift resistance.
2.3.2. Preserve existing drainage patterns; maintain positive flow and avoid ponding; integrate gutter/downspout systems as needed.
2.3.3. Perform utility conflict analysis (i.e ground-penetrating radar, SUE Level
A/B + potholing, etc.) before footing design.
2.3.4. Use corrosion-resistant finishes and match campus color palette.
2.3.5. Accessibility and Pedestrian Safety
2.3.5.1. Provide 6 ft minimum width for secondary walkways.
2.3.5.2. Install striped crosswalks, speed tables, and LED RRFB signage at crossings per FHWA and VA guidelines.
2.3.5.3. Ensure lighting for nighttime pedestrian activity along new paths.
2.3.5.4. Include striped crossings with speed bump protection across
Loop Road on west side of campus, connecting the outer parking lots A & F to the outer loop ring (see Assignment 21 – Draft
Schematic Design and Report, pg 12-16 for more information)
2.3.5.4.1. Apply lighting notes from General Note 4 to these
crossings across the Loop Road
2.4. Deliverables and AE Responsibilities
2.4.1. Design Submittals: 35%, 65%, 95%, 100% drawings/specifications.
2.4.2. Basis-of-Design Report: Document canopy system selection and deviations from existing details.
2.4.3. Technical Reports: Geotechnical, structural calculations, drainage analysis, utility survey, parking lot reconfiguration plan.
2.4.3.1. Parking Lot Reconfiguration Plan: At minimum, should detail:
targeted infill feasibility and implementation plans/drawings;
integration of protected pedestrian paths, speed tables, Loop
Road Crossings, and striped crossings with LED RRFB signage at conflict points, flagpole roundabout; proposed construction phasing plan and schedule; and verification of no conflicts with structural considerations.
2.4.3.1.1. If certain lots are identified to be infeasible to start construction on due to ongoing structural considerations, plan should include proposed phasing for those lots after 100% construction documents are submitted and approved
2.4.4. Cost Estimates: Use VA estimating standards. Break out costs by individual parking lot and provide a prioritized list for implementing shade structures and pedestrian-safety reconfiguration. Identify infill of additional parking stalls as deduct alternates to maintain the established construction limit
2.4.5. Schedule: Phased construction to maintain parking operations, minimized to one parking lot outage at a time.
3.0. Period of Performance (PoP) & Separate Construction NTP
3.1. Overall PoP (Parallel Design & Construction)
3.1.1. Design & Preconstruction (to 65%): Target ~120 calendar days from
Design NTP, including BOD/SUE/Geotech, QCP, and 35%/65% workshops.
3.1.2. Construction (separate NTP; parallel start): Target ~320–340 calendar days from Construction NTP (issued after VA acceptance of 65%).
3.1.3. Final Design (95%/100% IFC): Complete by ~Design NTP + 210 days, supporting early fabrication/field work.
3.1.4. Closeout: ~45 calendar days for as-builts, O&M, warranties, etc.
3.1.5. Total PoP (Design NTP → Final Acceptance): ~515–555 calendar days (~17–18.5 months), to be confirmed at 35% based on AE findings, utility conditions, and hospital operations.
3.2. Separate Construction NTP Provision
3.2.1. VA may issue a separate Notice to Proceed (NTP) for construction upon acceptance of the 65% design and associated investigative reports—
BOD, SUE Level A/B with potholing, Geotechnical Report— ensuring the parking lot reconfiguration plan will not be drastically affected by structural considerations.
3.2.1.1. Early construction NTP is contingent on validated reports and
65% acceptance. If utility conflicts, geotechnical findings, or
ADA/drainage constraints remain unresolved, early NTP shall be deferred to avoid foundation redesigns, utility strikes, ADA non-conformance, or schedule/cost impacts.
4.0. DESIGN & CONSTRUCTION COORDINATION
4.1. Meetings (Minimum Requirements)
Meeting Purpose Participants
(Minimum) Timing/Frequency
Kick-Off Confirm scope, BOD
Outline, Schedule, roles, risks
VA PM/COR
AE PM/Leads
DB/GC PM
Design NTP + 7 Days
35% Review Workshop
Mobilization plan, safety/QC; traffic & pedestrian control
VA PM/COR
AE PM/Leads
DB/GC PM
At 35% Submittal
Meeting Purpose Participants (Minimum)
Timing/Frequency
65% Review Workshop
Validate canopy typologies, footing concepts, drainage & paths
VA PM/COR
AE PM/Leads
DB/GC PM
Key Subs
At 35% Submittal
100%/ Pre- Construction
Finalize utilities, structural, drainage, accessibility layouts
Mobilization plan
VA PM/COR
AE PM/Leads
DB/GC PM
At 100% Submittal
Weekly Design Progress
Status, look-ahead, RFIs, changes
VA PM/COR
VA Contracting
AE PM/Leads
DB/GC PM
Weekly During
Design
Weekly Construction Progress
Status, look-ahead, RFIs, changes, safety
VA PM/COR
VA Contracting
AE PM/Leads
DB/GC PM
Superintendent
Weekly During
Construction
Pre-Installation Verify layout, clearances, pier locations, utilities
DB Structural
AE Structural
VA PM/COR
Per Design Phase
Substantial Completion Meeting
Punch-list; turnover planning
VA PM/COR
VA Contracting
AE PM
DB/GC PM
At Substantial
Completion
Final Closeout Meeting
Punch-list close, As-builts, O&M Training
Plan, Warranty
Acceptance
VA PM/COR
VA Contracting
AE PM
DB/GC PM
Before Final
Acceptance
4.2. Investigative Site Visits (Minimum Requirements)
Visit Purpose/Tasks Minimum Frequency
Topographic & Layout
Verification
Confirm stall counts, aisle widths, island dimensions, curb lines, ADA/ABAAS routes
2 visits (pre-BOD & pre-65%)
Utilities SUE/Potholing
Coordination
Witness test pits in planned pier zones; map conflicts/avoidance
2 visits (pre-BOD & pre-65%)
Geotechnical Coordination Coordinate borings; verify soils vs. design assumptions, validate drainage inlets & flow paths, identify low spots/ponding risks
As Needed; minimum 1 visit pre-65%
5.0. SUBMISSION REQUIREMENTS FOR DELIVERABLES
5.1. The Contractor shall furnish the required documents in accordance with the
Submittal Table below.
5.2. All deliverables submitted as PDF files shall be searchable and contain a bookmarked Table of Contents linked to respective sections, title pages, etc.
Drawings in PDF shall have bookmarks for each drawing page within a table of contents to allow quick navigation to individual drawing sheets. Drawings in DWG shall be drawn in AutoCAD 2025 or earlier.
5.3. All digital files shall be submitted via a File Transfer Protocol (FTP) website, such as Procore, Submittal Exchange, etc. Submittal title pages or labels shall contain at minimum the following; Project Name, Client Name (VA Southern Nevada
Health Care System), Contract Number, Project Number, Submittal phase, Name of Contractor/Designer, Submittal Date.
5.4. Provide hard copies of all submittals per the Submittal Table below.
5.5. All files, layers, naming conventions and standards should follow the VA BIM &
CAD Standards described on PG-18-13 of the TIL.
5.6. The Construction Contractor or assigned Architect-Engineer (A-E) shall develop
As-built drawings based on record drawings from construction.
5.7. All submittals via FTP website shall be zipped for archive at Substantial
Completion and sent to the VA for record.
DELIVERABLE
SUBMISSION
TIMING
(Relative to NTP or Design
Milestone)
HARD
COPIES TO
VA
PAPER SIZE
DIGITAL FILE
FORMATS
Basis of Design (BOD) report)
NTP + 35 Days
(Initial Concept)
0 Letter (8 ½ x 11 inch) PDF
Utility Survey Report
With BOD report 0 Letter PDF
Geotechnical Report
With BOD report 0 Letter PDF
Quality Control Plan
NTP + 45 Days 0 Letter PDF
35% Design Submittal
NTP + 60 Days 2
(Drawings, 1 Narrative)
Drawings: Arch E1 &
Half-Size
Narrative: Letter
PDF (all), DWG
(drawings)
65% Design Submittal
NTP + 120 Days 2
(Drawings, 1 Narrative)
Drawings: Arch E1 &
Half-Size
Narrative: Letter
PDF (all), DWG
(drawings)
95% Design Submittal
NTP + 180 Days 2
(Drawings, 1 Narrative)
Drawings: Arch E1 &
Half-Size
Narrative: Letter
PDF (all), DWG
(drawings)
100 % Construction Documents
NTP + 210 Days 2
(Drawings, 1 Narrative)
Drawings: Arch E1 &
Half-Size
Narrative: Letter
PDF (all), DWG
(drawings)
Construction Schedule
With
65%/95%/100%
Submittal
0 Letter PDF
Structural Calculations
With
65%/95%/100%
Submittal
0 Letter PDF
DELIVERABLE
SUBMISSION
TIMING
(Relative to NTP or Design
Milestone)
HARD
COPIES TO
VA
PAPER SIZE
DIGITAL FILE
FORMATS
Drainage Analysis
With
65%/95%/100%
Submittal
0 Letter PDF
Parking Lot Reconfiguration Plan
At 35%;
updated at 65%/95%/100%
(must be substantially complete/approv ed at 65%)
0 Letter PDF
As-Builts Drawings
30 Days after
Substantial
Completion
2 Arch E1 & Half-Size PDF, DWG
O&M Manuals
30 Days after
Substantial
Completion
1 Letter PDF
Warranty Documentation
30 Days after
Substantial
Completion
1 Letter PDF
6.0. HOURS OF OPERATION AND PHASING
6.1. Normal duty hours are 8:00 AM – 4:30 PM, Monday through Friday, excluding standard Federal Holidays. Federal Holidays can be obtained on OPM’s website
(www.opm.gov). All work shall be coordinated and scheduled through the COR.
6.2. All work carried out for this contract shall maintain hospital operations; phase work to keep maximum parking availability.
6.2.1. Sequence lot closures in short, managed segments with clear detours and temporary, accessible routes.
7.0. COST & SCHEDULE
7.1. Develop and update cost estimates and schedules in accordance with VA standards, following the Cost Estimating Manual found in the VA TIL
(www.cfm.va.gov/TIL).
7.1.1. Break out costs by individual parking lot and provide a prioritized list for implementing shade structures and pedestrian-safety reconfiguration.
Identify infill of additional parking stalls and/or lots as deduct alternates to maintain the established construction limit
8.0. CONSTRUCTION PERIOD SERVICES
8.1. RFI Response Time: 14 calendar days from receipt by AE and 14 calendar days from receipt by VA (individually); if the construction timeline is impacted, responses shall be expedited earlier to avoid delay.
8.2. Submittal Review: 14 calendar days by AE and 14 calendar days by VA
(individually) per submittal, unless schedule impacts require earlier action.
8.3. Field Clarifications/Directives: Provide written field clarifications within 14 calendar days unless safety/operations require immediate direction; coordinate through COR.
8.4. Shop Drawing Reviews: Meet the 14-day standard; prioritize canopy steel, foundations, traffic/pedestrian control, and drainage submittals to support phasing.
8.5. Change Order Pricing/Time Impact Analyses: Provide within 14 calendar days of request unless otherwise negotiated for critical path items.
8.6. AE shall provide responses in less time within reason if the contract time of 14 days would cause a delay or other impact to the contract
9.0. ABBREVIATIONS
ABAAS – Architectural Barriers Act Accessibility Standard ADA – Americans with Disabilities Act AE – Architect/Engineer BOD – Basis of Design CM – Construction Manager COR – Contracting Officer’s Representative DB – Design–Build FHWA – Federal Highway Administration GC – General Contractor IBC – International Building Code https://vaww.aams.ecms.va.gov/AAMS_Production/DAV/dwhyyyymyy015yvy/www.cfm.va.gov/TIL
IFC – Issued for Construction LED – Light Emitting Diode MUTCD – Manual on Uniform Traffic Control Devices NTP – Notice to Proceed O&M – Operations and Maintenance OPM – Office of Personnel Management PG-18-10 – VA Design Manual Series (Site, Parking, Signage, etc.)
PoP – Period of Performance RFI – Request for Information RRFB – Rectangular Rapid Flashing Beacon SUE – Subsurface Utility Engineering VA – Department of Veterans Affairs VASNHS – VA Southern Nevada Healthcare System
10.0. REFERENCE MATERIAL (VA-PROVIDED)
REFERENCE DOCUMENT NAME
Assignment 21 – Draft Schematic Design and Report.PDF
Assignment 44 – Conceptual Desing for Carports.PDF
Assignment 44 – Parking Study.PDF
593-14R-200 – Existing Carport Design.PDF
ED Parking Expansion.PDF
11.0. VA SECURITY REQUIREMENTS FOR CONTRACTORS
All contractor’s and subcontractor’s personnel shall be subject to VA Directive 0735, Homeland
Security Presidential Directive 12 (HSPD-12) Program, Federal laws, regulations, standards, and VA Handbooks regulating VA personnel regarding information and information system security.
a. Non-Personal Identity Verification (PIV) Card requests shall be submitted to
VA COR (Contracting Officer Representative) by the contractor. Request submission is the contractor’s responsibility to properly fill out the documents identified below. These documents will become a package for submission of
Non-PIV Card application:
1. VA Fingerprinting form
2. Declaration for Federal Employment (OF306), if there are any questions that were answered “yes” on item 9-13 on this form, fill out the appropriate addendum and include in the package.
3. Authorization For Release of Information (VA Form 0710)
4. Self-Certification of Continuous Service
5. Contractor Background Investigation Request
b. Non-PIV Card process may take 30-45 days, depending on the contractor’s personnel background check, Special Agreement Check (SAC). SAC is an automated records check conducted by the Federal Bureau of Investigation in collaboration with the Office of Personnel Management (OPM).
c. Non-PIV Card Applicant is subject to National Agency Check with written
Inquiries (NACI) conducted by OPM. This investigation covers a period of 5 years and a review of current records in the OPM Security Investigation Index (SII), DOD Defense Central Investigations Index (DCII), FBI name check, and FBI fingerprint check as well as written inquiries from previous employers and references on the application for employment. It is used for Non-sensitive or Low
Risk positions in VA.
d. Once all documents are complete and properly filled out, hand carry and submit to VA COR. Do not send completed forms through email due to Personal
Identifiable Information.
e. VA COR will then provide all documents to Engineering Service’s VA PIV
Sponsor/Manager to initiate the Non-PIV process.
f. PIV Sponsor/Manager will notify each applicant when to proceed for fingerprinting appointment.
g. Each applicant shall be fingerprinted at VA Southern Nevada Healthcare
System’s PIV Office, located on the first floor in Building 6 (Administration
Building), 6900 N. Pecos Road, N. Las Vegas, NV 89086. Each applicant shall sign in at the Security Desk.
h. VA COR or PIV Sponsor/Manager will provide status of each applicant’s Non-PIV
Card.
i. Non-PIV Card is critical for the construction start date, as the contractor’s personnel without Non-PIV Card may result with a restricted, limited, or no access to the job site. See attached blank forms/documents that is required for submission of Non-PIV Card application for each of contractors/sub-contractors
Contractor shall not require access to the VA internal trusted network for this scope. The certification and accreditation (C&A) requirements do not apply, and a Security Accreditation
Package is not required.
– END OF STATEMENT OF WORK –