View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

640-23-1-548-0010

640-424

612MCP

Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Northern California HealthCare System 5342 Dudley Blvd, Bldg 209 McClellan CA 95652-2609

612MCP

Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Northern California HealthCare System 3230 Peacekeeper Way, Bldg. 209 McClellan CA 95652-1012

To all Offerors/Bidders

36C26123R0022

01-12-2023

X

X X

2:00PM PST on 1/20/2023

X 1

The purpose of this amendment is to answer offerors questions.

New RFP Response Date: 1/20/2023 at 2:00PM PST

All other terms and conditions remain unchanged and in full force.

Jose Hernandez Contracting Officer

RFI Responses Project: B710 VMU – Re-lamp Fluorescent Light Fixtures with Specialized LED’s Project No.: 640-424 Solicitation No.: 36C26122R0059

RFI No. 1 Question: Do the light fixtures in the Procedure rooms have red sleeves?

Answer: Only Fixture type VR1, which are the fixtures in the Animal Holding Rooms and other rooms where animals are kept for any length of time, have the red sleeves on the middle lamps.

The Procedure rooms all have VR2 fixtures, which are identical to VR1 except without the red sleeves.

RFI No. 2 Question: How many fixtures get the red sleeves?

Answer: Because of this, there are (24) FEWER fixtures (total of 91) which will need the red sleeves replaced. But they will still need to be re-lamped with LED fixtures.

RFI No. 3 Question: Will there be a staging area provide or will a storage container be required?

Answer: If you think this project will require a large storage area then budgeting for a container is a good idea (it can be installed in the loading dock parking lot). There are also storage rooms at the loading dock and vivarium which have some space.

RFI No. 4 Question: Recycling of old lamp and ballast will be contractors’ responsibility or VA?

Answer: We would like the contractor to recycle the old lamps and ballasts (excellent question!)

RFI No. 5 Question: Lock Out Tag Out can be done from the switch or must be from main breaker?

Answer: The VA prefers for it to be done from the circuit breaker (not the main breaker, just the breakers for lighting in the rooms in question).