This amendment modifies solicitation 36C26121R0044 to provide responses to request for information questions and extend the proposal due date to April 26, 2021. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21 is seeking to modernize elevators at Building 100. The amendment allows retaining the existing cab and frame rather than replacing as originally specified. An equivalent non-proprietary wall panel material can be substituted. The contractor will be responsible for interim maintenance of all elevators within a bank once work on the first elevator begins through warranty period completion for that bank. The schedule is extended to 800 days total to allow simultaneous work across elevator banks rather than consecutive completion.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C26121R0044 Amendment 0002

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

04-17-2021

640-21-2-5212-0008

640-19-100 36C261 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Health Care System 975 Kirman Avenue Reno NV 89502-2597

36C261 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Health Care System 975 Kirman Avenue Reno NV 89502-2597 To all Offerors/Bidders

36C26121R0044 03-23-2021

X

X

April 26, 2021 at 3:00 PM Pacific Time

640-21-2-5212-0008

The purpose of this amendment is to provide responses to request for information (RFI) and to extend the offer due date to April 26, 2021 at 3:00 PM Pacific Time.

All other terms and conditions shall remain unchanged.

RFI 1 - Page 7, section D.3 states “Remove cab frame and cab in hoistway.” To do this, we would also need to replace the hoistway rails. This would add a significant amount of time and associated cost to this project, as it far exceeds to original intent of the scope of work. Upon inspection of the cab frame and cab, both are still in good shape and can be retained. Retaining the cab and cab frame would also be more cost effective for the VA. Would the VA consider allowing the contractor to retain these components?

Answer 1 - Remove cab and frame per SOW then replace the hoistway rails.

RFI 2 - Drawing A-401 states that contractors must use Diamalite vivispectra Spectrum Light weight glass with custom image interlayer for the wall panels which are proprietary materials. However, Specification’s document PAD B100 B101 States “Wall panels: Forms & Surfaces LEVELe-106 Elevator Interiors, or equal.” Please confirm that an equivalent, nonproprietary wall panel material can be used in place of Diamalite vivispectra. – Answer 2 - An equivalent product that match the performance and look as described in the salient characteristics is fine.

RFI 3 - Drawing A-401 shows a side mounted COP. However, this does not match the current cab layout for the elevators. We believe this is an error. Please confirm that the current elevator layouts will be retained. – Answer 3 - Not sure what is the COP you refer to? Please advise.

RFI 4 - Specifications Page 9, Section F: Scope of Work States, “One elevator shall be performed to government turnover prior to beginning the next to avoid negative impact to the facility and patient operations.” This section also defines the schedule for this project as 410 days from NTP. 410 days is not enough time to successfully complete each modernization consecutively. Performing multiple modernizations simultaneously within the separate banks of elevators would greatly cut down on the overall timeline. If performing just one elevator modernization at a time, we would like to propose the alternate schedule below for the VA’s consideration:

Answer 4 - I would change this to 800 days just to be on the safe side.

Submittals: 60 days Approval for Submittal: 14 days Material Lead Time: 130 days Construction of six cars: 480 days (80 days per car) Final Inspections: 7 days Turnover: 7 days Total: 698 days

RFI 5 - Page 11 of the solicitation section G: Pre-test/Tests/Turnover Acceptance of Work States “The one year warranty shall commence after final inspection, completion of performance test and upon full acceptance of the installation and run concurrent with the guarantee period of service” Due to the interconnectivity of elevators within the same bank, it is industry standard that the modernization company take over responsibility for maintenance and repairs on all elevators within the same bank as soon as the first car is removed from services. Please confirm that the awarded contractor will be responsible for the interim maintenance for the duration of the entire modernization of each respective bank of elevators, and full warranty service of one year from the date of turnover to the facility of the final elevator in each bank.

Answer 5 - I agree. The contractor will take over responsibility for maintenance and repairs on all elevators within the same bank as soon as the first car is removed from services. I agree. The awarded contractor will be responsible for the interim maintenance for the duration of the entire modernization of each respective bank of elevators, and full warranty service of one year from the date of turnover to the facility of the final elevator in each bank.