36C26119B0005-0003000.docx

DOCX document 28 KB Posted

Attached to
459-16-103: Install Realtime Water Monitoring System
Solicitation number
36C26119B0005
Issued by

About this file

36C26119B0005 0003 36C26119B0005 0003.docx

View the file

Other files

File Type Posted
36C26119B0005-0003001.pdf PDF
36C26119B0005-0002000.docx DOCX document
36C26119B0005-0002004.pdf PDF
36C26119B0005-0002001.pdf PDF
36C26119B0005-0002005.pdf PDF
36C26119B0005-0002002.pdf PDF
36C26119B0005-0002003.pdf PDF
36C26119B0005-0001011.docx DOCX document
36C26119B0005-0001001.pdf PDF
36C26119B0005-0001007.pdf PDF
36C26119B0005-0001000.docx DOCX document
36C26119B0005-0001003.pdf PDF
36C26119B0005-0001008.pdf PDF
36C26119B0005-0001006.pdf PDF
36C26119B0005-0001010.pdf PDF
36C26119B0005-0001005.pdf PDF
36C26119B0005-0001004.pdf PDF
36C26119B0005-0001009.pdf PDF
36C26119B0005-0001002.pdf PDF
36C26119B0005-003.pdf PDF
36C26119B0005-002.docx DOCX document
36C26119B0005-004.pdf PDF
36C26119B0005-001.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION

OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADM

INISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and d ate specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 3

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO

MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 06-14-2019 459-19-2-893-001 459-16-103 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Pacific Islands Health Care System Koapaka Street, Suite F250 Honolulu, HI 96819 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Pacific Islands Health Care System 3375 Koapaka Street, Sui459 Patterson Rd Honolulu, HI 96819 To all Offerors/Bidders

36C26119B0005 04-05-2019

X X X

459-368/90162-897-854200-3223 23NRNR000

X one (1) Install Realtime Water Monitoring System Amendment 0003 is issued to:

Response to RFI questions and to add the attached Drawings.

The Bid Opening Due Time/Date of 3:00 p.m., local Hawaiin time, Friday, June 28, 2019 remains unchanged.

No other changes are made at this time; All other Terms andConditions remain unchanged.

Claude Humphrey Contracting Officer

PCOE16L2-3302

CONTINUATION PAGE

AMENDMENT 0003

RFO Response/Clarification:

The following questions have been submitted to the Contracting Officer regarding this solicitation. The questions and responses represent all questions submitted to the Contracting Officer prior to the deadline established in the Solicitation. The following clarification is hereby being provided regarding the solicitation for bidder’s information and use. No response will be furnished to questions submitted hereafter. Bidders are instructed to submit their bids in response to the solicitation “as-is”. Any remaining issues will be addressed with the successful bidder. Questions and responses are provided for bidder’s information and use.

RFI 1. Clarification is required on the following:

As reflected on construction drawings sheets A-101/102/103 there are approximately (91) points where existing electrical is to be reused. In previous RFI/ Responses, the electrical sheets provided only gave an overlay of where new work is needed without any reference to existing circuitry. Please provide information on existing electrical circuitry (where the power originates from) for the existing electrical to be reused. Please note that this information will substantially improve cost-effectiveness by reducing the time needed to perform the electrical work.

Response: All the sink has sensors. Electrical is located directly under the sinks.

RFI 2. Section 01 00 00, Paragraph 1.16 calls for a Phigenics WME-1175 PWA continuous monitoring system, but Section 22 40 00 Paragraph 2.8 calls for a Nalco Aquapath system. Please clarify which manufacturer and model monitoring system we are to provide.

Response: Go with the Phigenic WME-1175.

RFI 3. Please provide the following missing drawing sheet; E-103 – Wing “B” & “C” Electrical Plan.

Response: See attached E-103 Wing “B” and “C” Electrical Plan.

attached document: E-103 Wing “B” and “C” Electrical Plan.

All other solicitation requirements remain as is and unchanged.

END OF AMENDMENT 0003