36C26118Q9529-0002001.pdf

PDF 23 KB Posted

Attached to
662-18-2-6449-0041 | VA261-18-AP-5325 | Specialty Clinic Painting (VA-18-00035093)
Solicitation number
36C26118Q9529
Issued by

About this file

36C26118Q9529 0002 36C26118Q9529-043 RFI Form answers.pdf

View the file

Other files

File Type Posted
36C26118Q9529-0004002.pdf PDF
36C26118Q9529-0004001.pdf PDF
36C26118Q9529-0004000.docx DOCX document
36C26118Q9529-0004003.pdf PDF
36C26118Q9529-0003000.docx DOCX document
36C26118Q9529-0003001.pdf PDF
36C26118Q9529-0002000.docx DOCX document
36C26118Q9529-0001001.pdf PDF
36C26118Q9529-0001000.docx DOCX document
36C26118Q9529-046.pdf PDF
36C26118Q9529-043.docx DOCX document
36C26118Q9529-048.doc DOC document
36C26118Q9529-042.docx DOCX document
36C26118Q9529-044.pdf PDF
36C26118Q9529-047.docx DOCX document
36C26118Q9529-045.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI FORM

Contractor Name: Acierto LLC Address: 2053 N. 2000 W. Farr West, Ut. 84404 Phone/eMail: 801 917 0070 Joe@acierto.us Send to: Pastaveia.st.john@va.gov AND Karen.smith3@va.gov

RFI

(REQUEST FOR INFORMATION)

RFQ#:

36C261-18-Q-9529 CONTRACTOR

RFI NO.:

PROJECT NAME:

Specialty Clinic Painting _ Electrical Wiring

DATE

REQUESTED:

08/23/2018

ACQUISITION

NO.:

VA261-18-AP-5325 REFERENCE:

DRAWING:

N/A

SPECIFICATION

SECTION:

N/A

DESCRIPTION OF PROBLEM OR INFORMATION BEING

REQUESTED

1. What is the level of finish 1-5 for sheet rock repairs? Level 5

2. Can you provide a count of wood doors and the number of steel doors?

• Module 1 – (1) wood, (11) steel

• Module 2 – (26) wood

• Module 3 – (8) wood, (5) steel

3. Mod space 3 has new wooden doors with an already approved finish. Do you still want these doors removed and lacquered? No, not reflected in answer 2.

4. Some of the walls have what looks to be a wall covering of some sort. We would like to see if the requirement to remove wall covering can be deleted from the scope?

Removing wall covering will be very time consuming and cause damage to existing sheet rock beyond just a skim coat. Will require removal and new sheet rock installed.

No need to remove wallcovering if you can still achieve a level 5 finish.

5. Scope indicates that the number of days to accomplish each phase is Friday and Saturdays. Can that be changed to read to include Saturday and Sunday for a total of 4 working days per phase instead of two days. Based on the comments we will expand the hours of work as follows:

• 3 – 11 p.m. Thursday and Friday, 6 a.m. – 12 p.m. Saturday

• 6 a.m. – 3 p.m. Friday – No odor and dust producing work.

mailto:Pastaveia.st.john@va.gov mailto:Karen.smith3@va.gov

• VA PROJECT MANAGER’S RESPONSE

VA TRACKING # FOR ALL RFI’S: AMENDMENT NO.:

VA PROJECT ENGINEER/MANAGER: Susan Ives DATE: 8/27/2018