36C26118B0266-027.pdf
PDF 153 KB Posted
- Solicitation number
- 36C26118B0266
About this file
36C26118B0266 33 40 00_Storm Sewer Utilities.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26118C0043-000.docx | DOCX document | |
| 36C26118B0266-00002001.pdf | ||
| 36C26118B0266-00002000.docx | DOCX document | |
| 36C26118B0266-00001001.pdf | ||
| 36C26118B0266-00001000.docx | DOCX document | |
| 36C26118B0266-00001002.pdf | ||
| 36C26118B0266-015.pdf | ||
| 36C26118B0266-022.pdf | ||
| 36C26118B0266-017.pdf | ||
| 36C26118B0266-012.pdf | ||
| 36C26118B0266-008.pdf | ||
| 36C26118B0266-005.pdf | ||
| 36C26118B0266-009.pdf | ||
| 36C26118B0266-014.pdf | ||
| 36C26118B0266-024.pdf | ||
| 36C26118B0266-013.pdf | ||
| 36C26118B0266-003.docx | DOCX document | |
| 36C26118B0266-020.pdf | ||
| 36C26118B0266-016.pdf | ||
| 36C26118B0266-007.pdf | ||
| 36C26118B0266-006.pdf | ||
| 36C26118B0266-021.pdf | ||
| 36C26118B0266-002.pdf | ||
| 36C26118B0266-023.pdf | ||
| 36C26118B0266-011.pdf | ||
| 36C26118B0266-010.pdf | ||
| 36C26118B0266-025.pdf | ||
| 36C26118B0266-001.docx | DOCX document | |
| 36C26118B0266-019.pdf | ||
| 36C26118B0266-018.pdf | ||
| 36C26118B0266-026.pdf | ||
| 36C26118B0266-004.pdf | ||
| 36C26118B0266-000.docx | DOCX document |
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS Project No.: 640-18-146
PALO ALTO HEALTH CARE SYSTEM
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
2015-08-11 STORM SEWER UTILITIES
33 40 00-1
SECTION 33 40 00
STORM SEWER UTILITIES
PART 1 - GENERAL
1.1 DESCRIPTION
This section specifies materials and procedures for construction of outside, underground storm sewer systems that are complete and ready for operation. This includes piping, structures and all other incidentals.
1.2 RELATED WORK
A. All Sections listed in the Table of Contents are a Condition of this
Section.
1.3 ABBREVIATIONS
A. HDPE: High-density polyethylene
B. PE: Polyethylene
1.4 DELIVERY, STORAGE, AND HANDLING
A. Do not store plastic manholes, pipe, and fittings in direct sunlight.
B. Handle manholes catch basins and stormwater inlets according to manufacturer's written rigging instructions.
1.5 COORDINATION
A. Coordinate connection to storm sewer main with the Public Agency providing storm sewer off-site drainage.
B. Coordinate exterior utility lines and connections to building services up to the actual extent of building wall.
1.6 QUALITY ASSURANCE:
A. Products Criteria:
1. When two or more units of the same type or class of materials or equipment are required, these units shall be products of one manufacturer.
2. A nameplate bearing manufacturer's name or trademark, including model number, shall be securely affixed in a conspicuous place on equipment. In addition, the model number shall be either cast integrally with equipment, stamped, or otherwise permanently marked on each item of equipment.
1.7 SUBMITTALS
A. Manufacturers’ Literature and Data shall be submitted, as one package, for pipes, fittings and appurtenances, including jointing materials, hydrants, valves and other miscellaneous items.
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-2
1.8 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. American Society for Testing and Materials (ASTM):
A185/A185M-07...........Steel Welded Wire Reinforcement, Plain, for
Concrete
A242/A242M-04(2009).....High-Strength Low-Alloy Structural Steel
A615/A615M-09b..........Deformed and Plain Carbon-Steel Bars for
Concrete Reinforcement
A760/A760M-10...........Corrugated Steel Pipe, Metallic-Coated for
Sewers and Drains
A798/A798M-07...........Installing Factory-Made Corrugated Steel Pipe for Sewers and Other Applications
A849-10.................Post-Applied Coatings, Paving, and Linings for
Corrugated Steel Sewer and Drainage Pipe
A929/A929M-01(2007).....Steel Sheet, Metallic-Coated by the Hot-Dip
Process for Corrugated Steel Pipe
B745/B745M-97(2005).....Corrugated Aluminum Pipe for Sewers and Drains
B788/B788M-09...........Installing Factory-Made Corrugated Aluminum
Culverts and Storm Sewer Pipe
C33/C33M-08.............Concrete Aggregates
C76-11..................Reinforced Concrete Culvert, Storm Drain, Pipe
C139-10.................Concrete Masonry Units for Construction of
Catch Basins and Manholes
C150/C150M-11...........Portland Cement
C443-10.................Joints for Concrete Pipe and Manholes, Using
Rubber Gaskets
C478-09.................Precast Reinforced Concrete Manhole Sections
C506-10b................Reinforced Concrete Arch Culvert, Storm Drain, and Sewer Pipe
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-3
C507-10b................Reinforced Concrete Elliptical Culvert, Storm
Drain, and Sewer Pipe
C655-09.................Reinforced Concrete D-Load Culvert, Storm
Drain, and Sewer Pipe
C857-07.................Minimum Structural Design Loading for
Underground Precast Concrete Utility Structures
C891-09.................Installation of Underground Precast Concrete
Utility Structures
C913-08.................Precast Concrete Storm Drain Structures
C923-08.................Resilient Connectors between Reinforced
Concrete Manhole Structures, Pipes, and
Laterals
C924-02(2009)...........Testing Concrete Pipe by Low-Pressure Air Test
Method
C990-09.................Joints for Concrete Pipe, Manholes, and Precast
Box Sections Using Preformed Flexible Joint
Sealants
C1433-10................Precast Reinforced Concrete Monolithic Box
Sections for Culverts, Storm Drains, and Sewers
C1479-10................Installation of Precast Concrete Sewer, Storm
Drain, and Culvert Pipe Using Standard
Installations
D448-08.................Sizes of Aggregate for Road and Bridge
Construction
D698-07e1...............Laboratory Compaction Characteristics of Soil
Using Standard Effort (12 400 ft-lbf/ft3 (600 kN-m/m3))
D1056-07................Flexible Cellular Materials—Sponge or Expanded
Rubber
D1785-06................Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-4
D2321-11................Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
D2751-05................Acrylonitrile-Butadiene-Styrene (ABS) Sewer
Pipe and Fittings
D2774-08................Underground Installation of Thermoplastic
Pressure Piping
D3034-08................Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings
D3350-10................Polyethylene Plastics Pipe and Fittings
Materials
D3753-05e1..............Glass-Fiber-Reinforced Polyester Manholes and
Wet wells
D4101-11................Polypropylene Injection and Extrusion Materials
D5926-09................Poly (Vinyl Chloride) (PVC) Gaskets for Drain, Waste, and Vent (DWV), Sewer, Sanitary, and
Storm Plumbing Systems
F477-10.................Elastomeric Seals (Gaskets) for Joining Plastic
Pipe
F679-08.................Poly (Vinyl Chloride) (PVC) Large-Diameter
Plastic Gravity Sewer Pipe and Fittings
F714-10.................Polyethylene (PE) Plastic Pipe (SDR-PR) Based on Outside Diameter
F794-03(2009)...........Poly (Vinyl Chloride) (PVC) Profile Gravity
Sewer Pipe and Fittings Based on Controlled
Inside Diameter
F891-10.................Coextruded Poly (Vinyl Chloride) (PVC) Plastic
Pipe with a Cellular Core
F894-07.................Polyethylene (PE) Large Diameter Profile Wall
Sewer and Drain Pipe
F949-10.................Poly (Vinyl Chloride) (PVC) Corrugated Sewer
Pipe with a Smooth Interior and Fittings
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-5
F1417-11................Installation Acceptance of Plastic Gravity
Sewer Lines Using Low-Pressure Air
F1668-08................Construction Procedures for Buried Plastic Pipe
C. American Association of State Highway and Transportation Officials
(AASHTO):
M190-04.................Bituminous-Coated Corrugated Metal Culvert Pipe and Pipe Arches
M198-10.................Joints for Concrete Pipe, Manholes, and Precast
Box Sections Using Preformed Flexible Joint
Sealants
M252-09.................Corrugated Polyethylene Drainage Pipe
M294-10.................Corrugated Polyethylene Pipe, 12 to 60 In. (300 to 1500 mm) Diameter
D. American Water Works Association(AWWA):
C105/A21.5-10...........Polyethylene Encasement for Ductile iron Pipe
Systems
C110-08.................Ductile-Iron and Gray-Iron Fittings
C219-11.................Bolted, Sleeve-Type Couplings for Plain-End
Pipe
C600-10.................Installation of Ductile iron Mains and Their
Appurtenances
C900-07.................Polyvinyl Chloride (PVC) Pressure Pipe and
Fabricated Fittings, 4 In. Through 12 In. (100 mm Through 300 mm), for Water Transmission and
Distribution
M23-2nd ed..............PVC Pipe Design and Installation”
E. American Society of Mechanical Engineers (ASME):
A112.6.3-2001...........Floor and Trench Drains
A112.14.1-2003..........Backwater Valves
A112.36.2M-1991.........Cleanouts
F. American Concrete Institute (ACI):
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-6
318-05..................Structural Commentary and Commentary
350/350M-06.............Environmental Engineering Concrete Structures and Commentary
G. National Stone, Sand and Gravel Association (NSSGA): Quarried Stone for
Erosion and Sediment Control
1.9 WARRANTY
The Contractor shall remedy any defect due to faulty material or workmanship and pay for any damage to other work resulting there from within a period of one year from final acceptance. Further, the
Contractor will furnish all manufacturers’ and suppliers’ written guarantees and warranties covering materials and equipment furnished under this Contract.
PART 2 - PRODUCTS
2.1 FACTORY-ASSEMBLED PRODUCTS
A. Standardization of components shall be maximized to reduce spare part requirements. The Contractor shall guarantee performance of assemblies of components, and shall repair or replace elements of the assemblies as required to deliver specified performance of the complete assembly.
2.2 CONCRETE PIPE AND FITTINGS
A. Non-Reinforced-Concrete sewer pipe and fittings shall be ASTM C14, Class
3, with bell-and-spigot or tongue-and-groove ends and gasketed joints with ASTM C443, rubber gaskets sealant joints with ASTM C990, bitumen or butyl-rubber sealant
B. Reinforced-Concrete sewer pipe and fittings shall be ASTM C76 or ASTM
C655.
1. Bell-and-spigot or tongue-and-groove ends and gasketed joints with
ASTM C443, rubber gaskets sealant joints with ASTM C990, bitumen or butyl-rubber sealant.
2. Class III: Wall A
2.3 CLEANOUTS
A. Cast-Iron Cleanouts: ASME A112.36.2M, round, gray-iron housing with clamping device and round, secured, scoriated, gray-iron cover. Include gray-iron ferrule with inside calk or spigot connection and countersunk, tapered-thread, brass closure plug.
1. Top-Loading Classification(s): Heavy Duty
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-7
2. Pipe fitting and riser to cleanout shall be same material as main pipe line.
3. Plastic Cleanouts shall have PVC body with PVC threaded plug. Pipe fitting and riser to cleanout shall be of same material as main line pipe.
2.4 MANHOLES AND CATCH BASINS
A. Standard Precast Concrete Manholes:
1. Description: ASTM C478 (ASTM C478M), precast, reinforced concrete, of depth indicated, with provision for sealant joints.
2. Diameter: 48 inches (1200 mm) minimum unless otherwise indicated.
3. Ballast: Increase thickness of precast concrete sections or add concrete to base section as required to prevent flotation.
4. Base Section: 6 inch (150 mm) minimum thickness for floor slab and 4-inch (102 mm) minimum thickness for walls and base riser section, and separate base slab or base section with integral floor.
5. Riser Sections: 4 inch (102 mm) minimum thickness, and lengths to provide depth indicated.
6. Top Section: Eccentric-cone type unless concentric-cone or flat-slab-top type is indicated, and top of cone of size that matches grade rings.
7. Joint Sealant: ASTM C990 (ASTM C990M), bitumen or butyl rubber.
8. Resilient Pipe Connectors: ASTM C923 (ASTM C923M), cast or fitted into manhole walls, for each pipe connection.
9. Steps: If total depth from floor of manhole to finished grade is greater than 60 inches (1500 mm). ASTM A615, deformed, 1/2 inch (13
mm) steel reinforcing rods encased in ASTM D4101, width of 16 inches
(400 mm) minimum, spaced at 12 to 16 inch (300 to 400 mm) intervals.
10. Adjusting Rings: Reinforced-concrete rings, 6 to 9 inch (150 to 225
mm) total thickness, to match diameter of manhole frame and cover, and height as required to adjust manhole frame and cover to indicated elevation and slope.
B. Manhole Frames and Covers:
1. Description: Ferrous; 24 inch (610 mm) ID by 7 to 9 inch (175 to 225
mm) riser with 4 inch (102 mm) minimum width flange and 26-inch (600
mm) diameter cover. Include indented top design with lettering cast into cover, using wording equivalent to "STORM SEWER."
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-8
2. Material: ASTM A536, Grade 60-40-18 ductile iron unless otherwise indicated.
2.5 CONCRETE FOR MANHOLES AND CATCH BASINS
A. General: Cast-in-place concrete according to ACI 318, ACI 350/350R, and the following:
1. Cement: ASTM C150, Type II.
2. Fine Aggregate: ASTM C33, sand.
3. Coarse Aggregate: ASTM C33, crushed gravel.
4. Water: Potable.
B. Concrete Design Mix: 4000 psi (27.6 MPa) minimum, compressive strength in 28 days.
1. Reinforcing Fabric: ASTM A185, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A615, Grade 60 (420 MPa) deformed steel.
C. Manhole Channels and Benches: Channels shall be the main line pipe material. Include benches in all manholes and catch basins.
1. Channels: Main line pipe material or concrete invert. Height of vertical sides to three-fourths of pipe diameter. Form curved channels with smooth, uniform radius and slope. Invert Slope: Same slope as the main line pipe. Bench to be concrete, sloped to drain into channel. Minimum of 6 inch slope from main line pipe to wall sides.
2.6 POLYMER-CONCRETE, CHANNEL DRAINAGE SYSTEMS
A. General Requirements for Polymer-Concrete, Channel Drainage Systems:
Modular system of precast, polymer-concrete channel sections, grates, and appurtenances; designed so grates fit into channel recesses without rocking or rattling. Include quantity of units required to form total lengths indicated.
B. Sloped-Invert, Polymer-Concrete Systems:
1. Channel Sections:
a. Interlocking-joint, precast, modular units with end caps.
b. 4-inch (102 mm) inside width and deep, rounded bottom, with built-in invert slope of 0.6 percent and with outlets in quantities, sizes, and locations indicated.
c. Extension sections necessary for required depth.
d. Frame: Include gray-iron or steel frame for grate.
2. Grates:
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-9
a. Manufacturer's designation “Heavy Duty," with slots or perforations that fit recesses in channels.
b. Material: Gray iron.
3. Covers: Solid gray iron if indicated.
4. Locking Mechanism: Manufacturer's standard device for securing grates to channel sections.
C. Narrow-Width, Level-Invert, Polymer-Concrete Systems:
1. Channel Sections:
a. Interlocking-joint, precast, modular units with end caps.
b. 5 inch (127 mm) inside width and 9-3/4 inch (248 mm) deep, rounded bottom, with level invert and with NPS 4 (DN 100) outlets in quantities, sizes, and locations indicated.
2. Grates:
a. Slots or perforations that fit recesses in channels.
b. Material: Gray iron.
3. Covers: Solid gray iron if indicated.
4. Locking Mechanism: Manufacturer's standard device for securing grates to channel sections.
D. Wide-Width, Level-Invert, Polymer-Concrete Systems:
1. Channel Sections:
a. Interlocking-joint, precast, modular units with end caps.
b. 8 inch (203 mm) inside width and 13-3/4 inch (350 mm) deep, rounded bottom, with level invert and with outlets in quantities, sizes, and locations indicated.
2. Grates:
a. Slots or other openings that fit recesses in channels.
b. Material: Gray iron.
3. Covers: Solid gray iron if indicated.
4. Locking Mechanism: Manufacturer's standard device for securing grates to channel sections.
E. Drainage Specialties: Precast, polymer-concrete units.
1. Large Catch Basins:
a. 24 by 12 inch (610 by 305-mm) polymer-concrete body, with outlets in quantities and sizes indicated.
b. Gray-iron slotted grate.
c. Frame: Include gray-iron or steel frame for grate.
2. Small Catch Basins:
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-10
a. 19 to 24 inch by approximately 6 inch (483 to 610 mm by approximately 150 mm) polymer-concrete body, with outlets in quantities and sizes indicated.
b. Gray-iron slotted grate.
c. Frame: Include gray-iron or steel frame for grate.
F. Supports, Anchors, and Setting Devices: Manufacturer's standard unless otherwise indicated.
G. Channel-Section Joining and Fastening Materials: As recommended by system manufacturer.
2.7 PIPE OUTLETS
A. Head walls: Cast in-place reinforced concrete, with apron and tapered sides.
B. Riprap basins: Broken, irregularly sized and shaped, graded stone according to NSSGA's "Quarried Stone for Erosion and Sediment Control."
1. Average Size: NSSGA No. R-5, screen opening 5 inches (127 mm).
2.8 HEADWALLS
A. Headwalls: Cast in-place concrete with a minimum compressive strength of
3000 psi (20 MPa) at 28 days.
2.9 WARNING TAPE
A. Standard, 4-Mil polyethylene 3 inch (76 mm) wide tape detectable type, purple with black letters, and imprinted with “CAUTION BURIED STORM
SEWER BELOW”.
PART 3 - EXECUTION
3.1 PIPE BEDDING
A. The bedding surface of the pipe shall provide a firm foundation of uniform density throughout the entire length of pipe. Concrete pipe requirements are such that when no bedding class is specified, concrete pipe shall be bedded in a soil foundation accurately shaped and rounded to conform with the lowest one-fourth of the outside portion of circular pipe. When necessary, the bedding shall be tamped. Bell holes and depressions for joints shall not be more than the length, depth, and width required for properly making the particular type of joint. Plastic pipe bedding requirements shall meet the requirements of ASTM D2321.
Bedding, haunching and initial backfill shall be either Class IB or
Class II material. Corrugated metal pipe bedding requirements shall conform to ASTM A798.
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-11
3.2 PIPING INSTALLATION
A. Drawing plans and details indicate general location and arrangement of underground storm drainage piping. Install piping as indicated, to extent practical. Where specific installation is not indicated, follow piping manufacturer's written instructions.
B. Install piping as shown on the Drawings.
C. Install piping beginning at low point, true to grades and alignment indicated with unbroken continuity of invert. Place bell ends of piping facing upstream. Install gaskets, seals, sleeves, and couplings according to manufacturer's written instructions for use of lubricants, cements, and other installation requirements.
1. Do not lay pipe on unstable material, in wet trench or when trench and weather conditions are unsuitable for the work.
2. Support pipe on compacted bedding material. Excavate bell holes only large enough to properly make the joint.
3. Inspect pipes and fittings, for defects before installation.
Defective materials shall be plainly marked and removed from the site. Cut pipe shall have smooth regular ends at right angles to axis of pipe.
4. Clean interior of all pipe thoroughly before installation. When work is not in progress, open ends of pipe shall be closed securely to prevent entrance of storm water, dirt or other substances.
5. Lower pipe into trench carefully and bring to proper line, grade, and joint. After jointing, interior of each pipe shall be thoroughly wiped or swabbed to remove any dirt, trash or excess jointing materials.
6. Do not walk on pipe in trenches until covered by layers of shading to a depth of 12 inches (300 mm) over the crown of the pipe.
7. Warning tape shall be continuously placed 12 inches (300 mm) above storm sewer piping.
D. Install manholes for changes in direction unless fittings are indicated.
Use fittings for branch connections unless direct tap into existing sewer is indicated.
E. Install proper size increasers, reducers, and couplings where different sizes or materials of pipes and fittings are connected. Reducing size of piping in direction of flow is prohibited.
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-12
F. When installing pipe under streets or other obstructions that cannot be disturbed, use pipe-jacking process of micro tunneling.
G. Install gravity-flow, nonpressure drainage piping according to the following:
1. Install piping pitched down in direction of flow.
2. Install corrugated steel piping according to ASTM A798.
3.3 REGRADING
A. Raise or lower existing manholes and structures frames and covers in regraded areas to finish grade. Carefully remove, clean and salvage cast iron frames and covers. Adjust the elevation of the top of the manhole or structure as detailed on the drawings. Reset cast iron frame and cover, grouting below and around the frame. Install concrete collar around reset frame and cover as specified for new construction.
B. During periods when work is progressing on adjusting manholes or structures cover elevations, the Contractor shall install a temporary cover above the bench of the structure or manhole. The temporary cover shall be installed above the high flow elevation within the structure, and shall prevent debris from entering the wastewater stream.
3.4 CONNECTIONS TO EXISTING MANHOLES
A. Make pipe connections and alterations to existing manholes so that finished work will conform as nearly as practicable to the applicable requirements specified for new manholes, including concrete and masonry work, cutting, and shaping.
B. bottom and sides.
3.5 CATCH BASIN INSTALLATION
A. Construct catch basins to sizes and shapes indicated.
B. Set frames and grates to elevations indicated.
3.6 STORMWATER INLET INSTALLATION
A. Construct inlet head walls, aprons, and sides of reinforced concrete.
B. Construct riprap of broken stone.
C. Install outlets that spill onto grade, anchored with concrete.
D. Install outlets that spill onto grade, with flared end sections that match pipe.
E. Construct energy dissipaters at outlets.
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-13
3.7 CONNECTIONS
A. Connect nonpressure, gravity-flow drainage piping in building's storm building drains specified in Division 22 Section FACILITY STORM DRAINAGE
PIPING.
B. Encase entire connection fitting, plus 6 inch (150 mm) overlap, with not less than 6 inches (150 mm) of concrete with 28-day compressive strength of 3000 psi (20.7 MPa).
C. Make connections to existing piping and underground manholes.
1. Make branch connections from side into existing piping, NPS 21 (DN
525) or larger, or to underground manholes and structures by cutting into existing unit and creating an opening large enough to allow 3 inches (76 mm) of concrete to be packed around entering connection.
Cut end of connection pipe passing through pipe or structure wall to conform to shape of and be flush with inside wall unless otherwise indicated. On outside of pipe, manhole, or structure wall, use epoxy-bonding compound as interface between new and existing concrete and piping materials.
2. Protect existing piping, manholes, and structures to prevent concrete or debris from entering while making tap connections. Remove debris or other extraneous material that may accumulate.
D. Pipe couplings, expansion joints, and deflection fittings with pressure ratings at least equal to piping rating may be used in applications below unless otherwise indicated.
1. Use nonpressure-type flexible couplings where required to join gravity-flow, nonpressure sewer piping unless otherwise indicated.
a. Flexible couplings for same OD pipes.
b. Unshielded, increaser/reducer-pattern, flexible couplings for pipes with different OD.
c. Ring-type flexible couplings for piping of different sizes where annular space between smaller piping's OD and larger piping's ID permits installation.
2. Use pressure-type pipe couplings for force-main joints.
3.8 CLOSING ABANDONED STORM DRAINAGE SYSTEMS
A. Abandoned Piping: Close open ends of abandoned underground piping indicated to remain in place. Include closures strong enough to withstand hydrostatic and earth pressures that may result after ends of abandoned piping have been closed. Use either procedure below:
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-14
1. Close open ends of piping with at least 8 inch (203 mm) thick, concrete
2. Close open ends of piping with threaded metal caps, plastic plugs, or other acceptable methods suitable for size and type of material being closed. Do not use wood plugs.
3.9 IDENTIFICATION
A. Install green warning tape directly over piping and at outside edge of underground structures.
3.10 FIELD QUALITY CONTROL
A. Inspect interior of piping to determine whether line displacement or other damage has occurred. Prior to final acceptance, provide a video record of all piping from the building to the municipal connection to show the lines are free from obstructions, properly sloped and joined.
1. Submit separate reports for each system inspection.
2. Defects requiring correction include the following:
a. Alignment: Less than full diameter of inside of pipe is visible between structures.
b. Deflection: Flexible piping with deflection that prevents passage of ball or cylinder of size not less than 92.5 percent of piping diameter.
c. Damage: Crushed, broken, cracked, or otherwise damaged piping.
d. Infiltration: Water leakage into piping.
e. Exfiltration: Water leakage from or around piping.
3. Replace defective piping using new materials, and repeat inspections until defects are within allowances specified.
4. Reinspect and repeat procedure until results are satisfactory.
3.11 TESTING OF STORM SEWERS:
A. Submit separate report for each test.
B. Test new piping systems, and parts of existing systems that have been altered, extended, or repaired, for leaks and defects.
1. Do not enclose, cover, or put into service before inspection and approval.
2. Test completed piping systems according to requirements of authorities having jurisdiction.
3. Schedule tests and inspections by authorities having jurisdiction with at least 24 hours advance notice.
4. Submit separate report for each test.
MPD – REPAIR ROADWAY / UNDERGROUND UTILITIES
FINAL
33 40 00-15
5. Air test gravity sewers. Concrete Pipes conform to ASTM C924, Plastic
Pipes conform to ASTM F1417, and all other pipe material conform to
ASTM C828 or C924, after consulting with pipe manufacturer. Testing of individual joints shall conform to ASTM C1103.
6. Test force-main storm drainage piping. Perform hydrostatic test after thrust blocks, supports, and anchors have hardened. Test at pressure not less than 1-1/2 times the maximum system operating pressure, but not less than 150 psi (1035 kPa).
C. Leaks and loss in test pressure constitute defects that must be repaired. Replace leaking piping using new materials, and repeat testing until leakage is within allowances specified.
3.12 CLEANING
A. Clean interior of piping of dirt and superfluous materials. Flush with water.
--- E N D ---