36C26027Q0072 RFQ Fuel Tank Testing.docx
DOCX document 1 MB Posted
- Attached to
- Fuel Tank Testing
- Solicitation number
- 36C26027Q0072
About this file
This is a Request for Quote (RFQ) for aboveground storage tank (AST) and underground storage tank (UST) inspection, testing, cleaning, fuel polishing, sampling, and analysis services at two VA Puget Sound Health Care System (VAPSHCS) locations: American Lake Division in Tacoma, Washington and Seattle Division in Seattle, Washington. The solicitation number is 36C26027Q0072, issued by the Department of Veterans Affairs Veterans Health Administration through the Network Contracting Office 20 on November 20, 2026, with an offer due date of December 4, 2026 at 10:00 EST. The contract period is five years, consisting of a base year plus four option years. Responsive quotes must include a vendor quote, signed SF 1449, completed B.3 Price/Cost Schedule, and proof of certified inspectors. The contract is unrestricted and not set aside for small business.
The scope requires monthly and annual inspections and testing of multiple ASTs and USTs across both facilities, including external and internal visual inspections, nondestructive testing using ultrasonic and radiography equipment, fuel cleaning and polishing with biocide treatment, sampling and laboratory analysis per ASTM D975 standards, and documentation of all findings and corrective actions. The contractor must meet specific qualifications, including minimum three years of experience, valid STI SP001 certifications for AST inspectors, and appropriate certifications per WAC 173-360A-0930 for UST inspectors. The contractor must provide all necessary equipment, materials, personnel, and certified laboratory services. Work is performed Monday through Friday, 7:30 AM to 4:00 PM Pacific time, requiring three-day advance notice for planned visits and VA facility escort requirements. The principal NAICS code is 561210 (Facilities Support Services), and invoicing is submitted monthly in arrears. The contracting officer is Robyn Akins at robyn.akins@va.gov, and questions may be submitted until November 27, 2026 at 10:00 EST.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Determination Fuel Tank Testing Seattle.pdf | ||
| Wage Determination Fuel Tank Testing American Lake.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. UEI: EFT:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
663-27-1-581-0005
36C26027Q0072 11-20-2026
Robyn Akins robyn.akins@va.gov 12-04-2026
10:00 EST
36C260 Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
X
X
561210
$47 Million
N/A
X
Puget Sound VA Healthcare System Seattle VA Medical
1660 South Columbian Way Seattle WA 98108
36C260
Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
Dept of Veterans Affairs
FMS-VA-2(101)
Financial Services Center
PO BOX 149971
Austin TX 78714-9971
See CONTINUATION Page
Contractor shall provide aboveground storage tank (AST) and underground storage tank (UST) inspections, testing cleaning fuel polishing, sampling and analyze. To be performed at the Seattle VA Medical Center and American Lake VA Medical Center (see SOW for addresses).
Questions can be emailed to robyn.akins@va.gov until 11/27/2026 at 10:00 EST.
A responsive quote shall include VENDOR QUOTE, a SIGNED SF 1449, a COMPLETED B.3 PRICE/COST SCHEDULE. and PROOF of
CERTIFIED INSPECTORS.
Period of performance will be 5 years from date of award.
See CONTINUATION Page
36C26027Q0072
Table of Contents
SECTION A
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
B.2 STATEMENT OF WORK
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES (OCT 2025) (DEVIATION)
C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
C.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2025) (DEVIATION)
........................................................................................ Error! Bookmark not defined.
C.4 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
C.5 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) ...25
C.6 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS
(DEVIATION APR 2026)
C.7 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025)
(DEVIATION)
C.8 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS
SECTION E - SOLICITATION PROVISIONS
E.1 52.212-1 INSTRUCTIONS TO OFFERORS COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (OCT 2025) (DEVIATION)
E.2 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
E.3 52.212-2 EVALUATION COMMERCIAL PRODUCTS AND COMMERCIAL
SERVICES (OCT 2025) (DEVIATION)
E.4 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (NOV 2025)
(DEVIATION)
E.5 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS
AND CERTIFICATIONS (NOV 2025) (DEVIATION)
E.6 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C260 Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
[X] 52.232-33, Payment by Electronic Funds Transfer System for Award Management, or
[] 52.232-36, Payment by Third Party
3. INVOICES: Invoices shall be submitted in arrears:
a. Quarterly []
b. Semi-Annually []
c. Other [X] Monthly
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
AMENDMENT NO DATE
B.2 STATEMENT OF WORK
STATEMENT OF WORK (SOW)
Contract Title
VA Puget Sound Health Care System (VAPSHCS) Seattle and American Lake Campuses:
Aboveground Storage Tanks (AST), Underground Storage Tanks (UST) Management.
Background
The VA Puget Sound Health Care System (VAPSHCS) is required to comply with federal and state environmental regulatory requirements that oversee specific activities and/or equipment. The following regulatory requirements are enforced through unannounced audits / inspections by the Environmental Protection Agency (EPA), Department of Ecology (ECY), Joint Commission, and VA Veterans Integrated Services Networks (VISN). Financial penalties are issued by the EPA and/or ECY when out of compliance.
Below is the applicable environmental regulations and requirements VA PSHCS must comply with regarding the generation, use, handling, storage, and release of Petroleum, Oil (petroleum & nonpetroleum-based oils), and Lubricants (POL). This list is not exclusive.
o 40 CFR 112 Oil Pollution Prevention o STI Standard SP001 (STI001) - Standard for the Inspection of Aboveground Storage tanks.
o WAC 173-180-330 Storage Tank Requirements o International Fire Code (IFC) o 40 CFR 280 Technical Standards & Corrective Action Requirements for Owners &
Operators of Underground Storage Tanks o WAC 173-360A Underground Storage Tank Regulations o VAPSHCS Directive 7707 Green Environmental Management System & Governing
Environmental Policy.
VAPSHCS is also required to clean and disinfect the inside of tanks. Polish, sample, and analyze fuel from all applicable Aboveground Storage Tanks (AST), Underground Storage Tanks (UST), Belly Storage Tanks (BST) and Day Tanks (DT) for contaminants (i.e.,) biological, physical, & chemical), quality of fuel, and water content.
Requirements, treatment, and testing standards are listed below. This list is not exclusive.
o VAPSHCS Directive 1028 Facility Electrical Power Systems o NFPA 99 Health Care Facilities Code o NFPA 110 Standard for Emergency & Standby Power Systems o ASTM D975 Standard Specification of Diesel Fuel Oils o Microbial/Fungus Growth
Scope
The following Aboveground Storage Tanks (AST) & Underground Storage Tanks (UST), Belly Tanks, and Day Tanks will be inspected, tested, cleaned, fuel polished, sampled, and analyzed at the following locations:
VA Puget Sound Health Care System (VAPSHCS) American Lake Division 9600 Veterans Drive Southwest, Tacoma, WA 98493
AST Tanks:
AST 1 - 3,000-gallon Tank #2 Diesel: BLDG 200 500kw Generator o 300 gallons #2 Diesel: BLDG 200 500kw Generator Belly Tank
AST 5 - 12,000-gallon Tank #2 Diesel: 2 Meg Generator o 2500 gallons #2 Diesel: 2 Meg Generator Belly Tank
AST 4 - 10,000-gallon Tank Vehicle Fueling Station Tank.
UST Tanks:
UST 1 - 4,600 gallons #2 Diesel: 750kw and 800kw Generator o 1 ea. 750kw and 1 ea. 800kw generator 250 gallons #2 Diesel: Day Tank UST 4 & 5 2000 gallons Split Tank: 1000 gallons unleaded and 1000 gallons diesel UST 8 - 30,000 gallons #2 Diesel: Boiler Plant Tank UST 9 - 30,000 gallons #2 Diesel: Boiler Plant Tank UST 11 - 8000 gallons #2 Diesel: 2 Meg Generator back up fuel.
Any new, not identified, and/or currently not in use ASTs & USTs per Facilities Management request.
VA Puget Sound Health Care System (VAPSHCS) Seattle Division 1660 South Columbian Way, Seattle, WA 98108
UST Tanks:
UST A - 30,000 gallons #2 Diesel: Boiler Plant Tank UST B - 30,000 gallons #2 Diesel: Boiler Plant Tank UST Building 100 25,000 gallons #2 Diesel: Generator Tank UST Building 16 15,000 gallons #2 Diesel: Generator Tank o 4 ea. 220-gallon #2 Diesel: Generator Belly Tanks Any new, not identified, and/or currently not in use USTs per Facilities Management request.
General Requirements
Prime Contractor and Sub-Contractor Qualifications:
The following are minimum prime contractor and subcontractor qualifications for this contract:
Has a minimum of three (3) years of experience providing services similar in scope as described.
Has not received a corporate criminal conviction within the past three (3) years.
Is not currently rendered ineligible for doing business or receiving monetary benefits with a government agency because of debarment or suspension by EPA or Department of Ecology.
Must be an established business with all the required licenses, fees, bonding, facilities, equipment, and trained personnel necessary to meet all requirements and perform the work as specified in the solicitation.
Use of subcontractors
Prior to performance, the contractor must identify all subcontractors who will perform services in fulfillment of contract requirements. Additionally, contractors may be required to identify contact information as well as federal tax identification number (TIN), and anticipated dollar value of each subcontract.
The contractor must provide the POC for each of the subcontractors to the CO at a minimum 5 business days prior to the start date of the project.
The CO reserves the right to approve or reject all subcontractors that are who are engaged by the contractor, must be pre-approved, in writing, by the GEMS Program Manager (Housed in the Safety Department) and Contracting Officer.
The contractor agrees to be responsible for all actions of any subcontractors in the performance of this contract. The contractor shall be responsible for ensuring that all requirements of the contract shall flow down to all subcontractors. In no event shall the existence of a subcontract operates to release or reduce the liability of contractor to
The contractor must not assign or otherwise transfer its obligations or any claim arising under this contract without the prior written consent of the CO. Such consent will not be unreasonably withheld. The contractor shall provide a minimum of 30 calendar days advance notification of intent to assign or otherwise transfer its obligations under this contract. Violations of this provision may be considered a material breach and be grounds for contract termination. Assignment or transfer of contract shall not relieve the contractor from its responsibilities and obligations under the contract.
Insurance
The contractor shall, at its own expense, obtain and keep insurance in force as follows until completion of the contract. Upon request, the contractor shall furnish evidence in the form of a certificate of insurance as required by law, in the following kinds and minimum amounts have been secured. Failure to provide proof of insurance, as required, will result in contract cancellation. The contractor shall include all subcontractors as insured under as required insurance policies or shall furnish separate Certificates of Insurance and endorsements for each subcontractor.
Sub.
Industrial Insurance Coverage
The contractor shall comply with the provisions of Title 51 RCW Industrial Insurance. If the contractor fails to provide industrial insurance coverage or fails to pay premiums or penalties on behalf of its employees as may be required by law, the CO may terminate this contract. This provision does not waive any of the Washington State Department of Labor and Industries (L&I) rights to collect from the contractor. Contractor(s) must comply fully with all insurance requirements stated herein.
Compliance with Health & Safety, Environmental, and Transportation Regulations
The contractor agrees to comply with all applicable federal, state, and local regulations as well as the conditions of any permits, as may be amended and that may be promulgated.
The contractor agrees to indemnify and hold harmless the VAPSHCS from all comply with all federal, state, and local regulations, permit conditions, and most current industry standards.
The contractor agrees that all services and items furnished under this contract shall comply with all federal, state, and local regulations, permit conditions, and most current industry standards. Said regulations including but are not limited to the following:
o Titles 10, 29, 40, and 49 of the Code of Federal Regulations; and o Chapters 173, 246, and 296 of the Washington Administrative Code.
Spill Responsibilities
The contractor is solely responsible for all spills, leaks, or releases, which occur because of, or are contributed to be, the actions of its agents, employees, or subcontractors. In the event of a spill, leak, or release, the contractor agrees to take the following actions:
o Evacuate and warn those people that may be affected by the spill.
o Immediately contact Emergency Response Agencies (i.e., call 911).
o Contact VAPSHCS (GEM Program Manager) representative.
o Clean up the spill in a manner that complies with federal, state, and local regulations and current industry standards.
Company Health & Safety Plan shall apply to all work performed by the contractor and subcontractors that
The Health & Safety Plan shall consist of (at minimum) the following topics:
o Hazard Recognition (explosive risk, chemical exposure) o Personal protective equipment to be used on the job.
o Reporting unsafe conditions/activities and avoiding actions and conditions that may result in an accident.
o Site Control (stabilization work area, contamination control area, command control area) o Communication activities (notification of emergency response needs, fire, police, medical aid, and owner representative) o Decontamination procedures (used in the event of an emergency/contingencies) o Contingencies (Fire, detonation, spill, injury, personnel exposure) o Personnel qualifications and responsibilities methodology (How work is performed) o Site specific health & safety plan template o Emergency spill response procedure
Specific Requirements
The following requirements will be completed prior to the initiation of this contract and whenever there are new employees performing work on the site. All applicable certificates, credentials, and/or license must be active and current.
The contractor inspecting and/or testing ASTs will provide the Contracting Officer Representative (COR), Contracting Officer Technical Representative (COTR), and Safety Department copies of their active, unexpired, and valid STI SP001 Aboveground Storage Tank Inspector certifications.
The contractor inspecting and/or testing USTs will provide the Contracting
Officer Representative (COR), Contracting Officer Technical Representative (COTR), and Safety Department copies of their active, unexpired, and valid certifications, credentials, and/or licenses per WAC 173-360A-0930.
Once the contract is awarded, the prime contractor must provide the COR with the inspection and testing dates for the current fiscal year (FY 2026) within 30 calendar days of the award date. FY 2026 dates will be established off previous inspection and testing dates (communicate with the GEMS Program Manager for this information). For the following years (e.g., FY 2027), the prime contractor must publish the complete list of inspection and testing dates at least 30 calendar days before the beginning of the year.
If the established AST and/or UST timelines are not met, VAPSHCS reserves the right to seek alternate services at the cost to the contractor.
Specific Tasks
AST Inspection, Re-Inspection, & Testing:
The following AST inspections and/or tests will be completed on a Monthly basis by an authorized STI SP001 Aboveground Storage Tank Inspector using a Nondestructive
Prevention, Control, and Countermeasures Plan and after repairs using AST Walkthrough Inspections Checklist.
o No visible leaks, drips, or discoloration.
o Tank and piping show no signs of damage or corrosion.
o No vegetation growing around tank.
o Emergency spill response supplies kit available, inventoried and restocked if low.
Inspected supplies for deterioration.
o Provide documentation to COR or designated COR representative monthly
The following AST inspections and/or tests will be completed on an ANNUAL basis by an authorized STI SP001 Aboveground Storage Tank Inspector. Nondestructive and Countermeasures Plan and after repairs.
Externally: The contractor will visually inspect the aboveground storage tank and document findings and corrective actions per the STI SP001 standard guidelines.
o Significant cracks or spalling (flakes of broken off material) in concrete pads and concrete secondary containment structures.
o Excessive or uneven settlement of the tank foundation, such as distortion and cracks around anchor bolts that attach a tank to an underlying concrete pad.
o Rust, pitting, and other visual evidence of corrosion on the exterior of metal tanks and ancillary equipment, especially at grade level, roof areas, and connections o Deterioration of exterior coatings, such as rust spots and blisters o Damage to insulation o Evidence of leaks around the tank or ancillary equipment, such as discoloration of coatings o Cracks or evidence of leaks at joints and welds, especially at connections.
o Loss of metal thickness on the tank bottom and sides o Cracks on fiberglass tanks o Evidence of leaks around joints on concrete tanks and vaults o Tank system coatings and linings that have cracks, gaps, swelling, blistering, or crinkling.
Internally: The contractor will visually inspect, and integrity test the aboveground storage tank and document findings and corrective actions per the STI SP001 standard guidelines.
o Using ultrasonic equipment to measure the thickness of the roof, wall, and bottom of metal tank.
o Using radiography equipment to detect cracks and voids in piping, repair welds, ancillary equipment, and other solid materials. (Operator must be trained in how to avoid excessive exposure to x-rays or gamma rays) o Liquid penetrant methods to detect the extent and size of surface cracks on the outside of a tank and cracks in welds that are not seen in visual inspection.
o Magnetic particle method to detect surface cracks on metal tanks and welds that are not observable by visual inspection.
o Hydrostatic test on existing tanks that have had major repairs or alterations
On completion, the contractor will provide all inspection and testing results to the COR, and Safety Department staff for recordkeeping and Department of Ecology (if required). If inspection and/or testing results determine repairs are required, the contractor will provide consultative services to include writing up a quote / statement of work detailing work that needs to be done and projected cost.
This can also be done by a third party.
If repairs or alterations are made to the tank that require reinspection and/or retesting, the contractor will complete this within 30 - 45 days after work has been completed.
AST Cleaning & Fuel Polishing
The following requirements will be completed on an ANNUAL basis:
The contractor will provide services to remove water and sediment from all applicable ASTs. Removal, and treatment will include (not exclusive to):
o Inspecting the tank lids and covers for microbial growth, clean spill buckets, and remove water from sumps (as needed) o Pumping out water and contaminants from the tank o Sweeping the bottom of the tank o Using a high-performance filter to remove all contaminants until fuel and filters run clean.
o Applying biocide treatment to treat future contaminants.
o Providing a photo-documented service report.
The contractor will provide services to circulate biocide preventative maintenance treatment to all applicable ASTs as needed. Treatment will include (not exclusive to):
o Applying and fully circulating fuel-soluble biocide treatment with fuel.
The contractor will conduct a 60 90-day follow-up on tanks with strong microbial activities to remove microbial growth killed by the biocide treatment and remove any pooled water introduced after cleaning service.
The contractor will remove all waste generated from AST cleaning & fuel polishing and dispose of it per federal, state, and local regulatory requirements.
AST Fuel Sampling & Analysis
The following AST requirements will be completed on an ANNUAL basis.
o The contractor will provide pre-and-post photographs reflecting the fuel polishing process for all applicable ASTs.
o The contractor will use a certified laboratory and/or State of Washington certified laboratory, when necessary, that shall strictly adhere to the prescribed methods, including provisions for sample preparation, prescribed equipment, detection limits, and QA/QC procedures.
o The contractor will handle, store, and analyze samples in accordance with ASTM D975 and any other applicable ASTM required standards and/or methods.
UST Inspection, Re-Inspection, & Testing
The following UST inspections and/or tests will be completed on a Monthly basis by contractors that meet qualification standards outlined in WAC 173-360A-0930 (Certification of Service Providers). The contractor will conduct a walk-through inspection of the Underground Storage Tanks to include spill buckets, leak monitor, and sumps while using the most current
Inspections will include documented findings and corrective actions per
WAC 173-360A.
o Spill bucket: checked for damage and cracks. Liquid and debris removed.
o Fill pipe(s): checked for obstructions. Removed if found.
o Fill cap(s): securely fitted and on fill pipe(s).
o Tank Monitor equipment: checked for alarms and normal operating conditions.
o Leak detection records: are reviewed for non-leaking results and kept for three years.
Suspected leaks are reported.
o Containment sump(s): checked for damage and presence of liquid. Liquid and/or debris removed.
o If using manual tank gauging checked condition of tank gauge stick is good (e.g.
readable at 1/8 increments throughout).
o Emergency spill response supplies: inventoried and restocked if low. Inspected supplies for deterioration.
o Inspected: loose fittings, deterioration, obvious signs of leaks, and improper function of dispenser hoses, nozzles, and breakaways.
o Record monthly Rectifier Operations.
o Monthly leak test reports, and leak sensor alarm reports.
o Provide documentation to COR or designated COR representative monthly.
The following UST inspections and/or tests will be completed on an ANNUAL basis (or after repair) by contractors that meet qualification standards outlined in WAC 173-360A-0930 (Certification of Service Providers).
The contractor will conduct a walk-through inspection of the Underground Storage Tanks to include spill buckets, leak monitor, and sumps while using the most current include documented findings and corrective actions per WAC 173-360A.
The contractor will test the underground storage tank and document findings and corrective actions per WAC 173-360A Underground Storage Tank regulatory requirements.
Testing will include o Release detection equipment operability testing o Automatic line leak detector testing (including ATG, alarms, battery backups, probes, sensors, cables, ALLDs, vacuum, etc.)
o Line tightness testing
On completion, the contractor will provide all inspection and testing results to the COR, COTR, and Safety Department staff for recordkeeping and Department of Ecology (if required).
If inspection and/or testing results determine repairs are required, the contractor will provide consultative services to include writing up a quote / statement of work detailing work that needs to be done and projected cost. This can also be done by a third party.
If repairs or alterations are made to the tank that require reinspection and/or retesting, the contractor will complete this within 30 - 45 days after work has been completed.
UST Testing
The following UST requirements and/or tests will be completed on a TRIENNIAL basis (or after repair) by contractors that meet qualification standards outlined in WAC 173-360A-0930 (Certification of Service Providers). This service will take place in FY30 only.
The contractor will test the underground storage tank and document findings and corrective actions per WAC 173-360A Underground Storage Tank regulatory requirements.
Testing will include o Cathodic protection testing (Both Galvanic & Impressed Current System) o Spill bucket testing o Overfill equipment testing (including Automatic Shut-off, Exterior Alarm, & Ball
(Float) o Containment sump testing
On completion, the contractor will provide all testing results to the COR, COTR, and Safety Department staff for recordkeeping and Department of Ecology (if required).
If repairs or alterations are made to the tank that require retesting, the contractor will complete this within 30 - 45 days after work has been completed.
UST Cleaning & Fuel Polishing
The following UST requirements will be completed on an ANNUAL basis. The contractor will provide services to remove water and sediment from all applicable USTs. Removal and treatment will include (not exclusive to) o Inspecting the tank lids and covers for microbial growth, clean spill buckets, and remove water from sumps (as needed) o Pumping out water and contaminants from the tank o Sweeping the bottom of the tank o Using a high-performance filter to remove all contaminants until fuel and filters run clean o Applying biocide treatment to treat future contaminants o Providing a photo-documented service report
The contractor will provide services to circulate biocide preventative maintenance treatment to all applicable USTs.
Treatment will include (not exclusive to):
o Applying and fully circulating fuel-soluble biocide treatment with fuel.
The contractor will conduct a 60 90-day follow-up on tanks with strong microbial activities to remove microbial growth killed by the biocide treatment and remove any pooled water introduced after cleaning service.
The contractor will remove all waste generated from UST cleaning & fuel polishing and dispose of it per federal, state, and local regulatory requirements.
UST Fuel Sampling & Analysis
The following UST requirements will be completed on an ANNUAL basis.
o The contractor will provide pre-and-post photographs reflecting the fuel polishing process for all applicable USTs.
o The contractor will use a certified laboratory and/or State of Washington certified laboratory, when necessary, that shall strictly adhere to the prescribed methods, including provisions for sample preparation, prescribed equipment, detection limits, and QA/QC procedures.
o The contractor will handle, store, and analyze samples in accordance with ASTM D975 and any other applicable ASTM required standards and/or methods.
Performance Monitoring
The contractor will provide the COR, COTR, and Safety Department with the following documents per tank type and time limitation requirements:
Aboveground Storage Tank Annual Requirements:
o Valid and active STI SP001 Aboveground Storage Tank Inspector certifications o Documented external visual inspection of the AST with findings and corrective actions per the STI SP001 standard guidelines.
o Documented internal visual inspection of the AST with findings and corrective actions per the STI SP001 standard guidelines to include any required testing (i.e., ultrasonic, radiography, liquid penetrant method, magnetic particle method, and hydrostatic test) o Before and after fuel sample photos for visual comparison report o Lab sampling and analysis results (to include Microbial/Fungus Growth) per ASTM
D975
Underground Storage Tank Annual Requirements:
o Valid and active certification(s) (outlined in WAC 173-360A-0930) o Documented walk-through inspection of the UST with findings and corrective actions per WAC 173-360A Underground Storage Tank regulatory requirements.
o Documented release detection equipment operability tests.
o Documented automatic line leak detector tests.
o Line tightness tests.
o Before and after fuel sample photos for visual comparison report o Lab sampling and analysis results (to include Microbial/Fungus Growth) per ASTM
D975
Triennial Underground Storage Tank Requirements o Valid and active certification(s) (outlined in WAC 173-360A-0930) o Cathodic protection tests o Spill bucket tests o Overfill equipment tests o Containment sump tests
Security Requirements
The contractor employees shall not have access to VA sensitive or computer information and will not require routine access to VA Facilities. The contractor employees shall require intermittent access only and will be escorted by VA employees while at VA Facilities. No background investigation is required.
Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI).
No Government-Furnished Equipment (GFE) / Government-Furnished Information (GFI) will be provided to the contractor. The contractor is responsible for providing all the necessary resources (i.e., manning, equipment, materials, access to a credited lab, etc.) too complete the outlined inspection and testing and sampling and analysis.
Other Pertinent Information or Special Considerations o Identification of Possible Follow-up Work.
o Possible extension of term of service with option years o Identification of Potential Conflicts of Interest (COI).
o Identification of Non-Disclosure Requirements.
o Contactors will not have access to sensitive or proprietary information.
o Packing and Shipping Instructions.
See section 4. General Requirements (Compliance with Health & Safety, Environmental and Transportation Regulations) for details o Inspection and Acceptance Criteria.
o Acceptance letter will be required at the end of the job, signed by both the VA POC and the contractor, stating the work is complete and up to standards.
Risk Control
All personnel performing services under this contract shall, at minimum, have training in the following areas: STI Standard (STI SP001) Standard for the Inspection of
Aboveground Storage Tanks and all applicable credentials outlined in WAC 173-360A- 0930.
For planned visits, the contractor must provide 3-day notice before the site visit.
Place of Performance
VA Puget Sound Health Care System (VA PSHCS) American Lake Division 9600 Veterans Dr. SW Tacoma, WA, 98493
VA Puget Sound Health Care System (VA PSHCS) Seattle Division 1660 South Columbian Way Seattle, WA, 98108
Period of Performance
Normal hours of operation are Monday through Friday from 7:30AM to 4:00PM Pacific time. All work is expected to be performed generally during normal hours of coverage unless requested or approved by the COR or his/her designee. Before commencement of work, the Contractor shall confer with the VA COR and Contracting Office to agree on a sequence of procedures; means of access to premises and building. All work performed, to include delivery of materials and equipment, shall be made with minimal interference to Government operations and personnel. Work performed outside the normal hours of coverage must be approved by the COR or his/her designee. All time shall be approved in his/her designee. Allow 5-days for approval of any alternate working hours needed.
sole responsibility of the Vendor and shall not be billed to nor reimbursed by the Government. When one of the Federal holidays falls on a Sunday, the following Monday will be observed as a National Federal Holiday. When one of the Federal holidays fall on a Saturday, the preceding Friday, will be observed as a National Federal Holiday. Vendor days to perform are reflected in Section 10.
Vendor is not required to provide service(s) on the following U.S. Government Federal holidays, nor shall the Vendor be paid for these days:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Check-in, Parking and Smoking Regulations
Check-in
Once on campus, contractor employees must check-in and be escorted by the COR or the COR's designee's office before starting work.
Parking
It is the responsibility of contract personnel to park in the designated parking areas.
Parking information is available from VA Police & Security Service Office. The Contractor assumes full responsibility for any parking violations.
Safety
All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering on VAPUGS shall comply with applicable Federal, State, and VA safety and fire regulations and codes, which are in effect during the performance period of the contract.
Contractor shall perform work in strict accordance with existing relevant, accredited standards and codes to minimize the possibility of injury to personnel, or damage to Government equipment. Every effort shall be made to safeguard human life and property.
Contractor shall comply with all applicable Federal, State, and local requirements those found in Federal and State Occupational Safety and Health Act (OSHA) statutes and regulations, such as applicable provisions of Title 29, Code of Federal Regulations (CFR), Parts 1910 and 1926, NFPA 70E, Article 130.7 29 CFR 1910.132(d)(1)(iii), 29CFR1910.137. Contractors shall provide all necessary tools, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely.
Period of Performance
Delivery Schedule
See Performance Monitoring for details on what the contractor will provide.
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1.00 YR __________________ __________________
Base Year Aboveground Storage Tank inspection, testing, cleaning, fuel polishing, samplings, and analyzed for the American Lake VA Medical Center Contract Period: Base PRINCIPAL NAICS CODE: 561210 - Facilities Support Services PRODUCT/SERVICE CODE: J091 - Maintenance, Repair, and Rebuilding of Equipment - Fuels, Lubricants, Oils, and Waxes
Base Year Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the Seattle VA Medical Center Contract Period: Base PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Base Year Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the American Lake VA Medical Center Contract Period: Base PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 1 Aboveground Storage Tank inspection, testing, cleaning, fuel polishing, samplings, and analyzed for the American Lake VA Medical Center Contract Period: Option 1 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 1 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the Seattle VA Medical Center Contract Period: Option 1 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 1 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the American Lake VA Medical Center Contract Period: Option 1 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 2 Aboveground Storage Tank inspection, testing, cleaning, fuel polishing, samplings, and analyzed for the American Lake VA Medical Center Contract Period: Option 2 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 2 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the Seattle VA Medical Center Contract Period: Option 2 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 2 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the American Lake VA Medical Center Contract Period: Option 2 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 3 Aboveground Storage Tank inspection, testing, cleaning, fuel polishing, samplings, and analyzed for the American Lake VA Medical Center Contract Period: Option 3 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 3 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the Seattle VA Medical Center Contract Period: Option 3 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 3 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the American Lake VA Medical Center Contract Period: Option 3 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
1.00 JB __________________ __________________
Option Year 3 Triennial UST Testing
Contract Period: Option 3 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 4 Aboveground Storage Tank inspection, testing, cleaning, fuel polishing, samplings, and analyzed for the American Lake VA Medical Center Contract Period: Option 4 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 4 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the Seattle VA Medical Center Contract Period: Option 4 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
Option Year 4 Underground Storage Tank inspection, testing, cleaning, fuel polishing, sampled and analyzed for the American Lake VA Medical Center Contract Period: Option 4 PRINCIPAL NAICS CODE: 561210 - Facilities Support Services
GRAND TOTAL __________________
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES (OCT 2025) (DEVIATION)
(a) Definitions. The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference.
(b) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights
(1) Within a reasonable time after the defect was discovered or should have been discovered;
and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(c) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(d) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(e) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause FAR 52.233-1, Disputes, which is incorporated in this contract by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall
(1) Notify the Contracting Officer in writing as soon as possible;
(2) Remedy the delay as quickly as possible; and
(3) Notify the Contracting Officer when the occurrence is over.
(g) Invoice. The Government will handle invoices according to the Prompt Payment Act (31 U.S.C. 3903) and 5 CFR part 1315. The Contractor shall submit invoices to the address designated in the contract to receive invoices. An invoice must include the information required by 5 CFR part 1315.9(b).
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees, and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark, or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(4) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable;
(D) Contractor point of contact; and
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(5) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the
Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by FAR part 33 if
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see FAR part 32).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a termination for cause.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures for interest credits prescribed in FAR part 32 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. The Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered under this contract are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C.
chapter 87, Kickbacks; 49 U.S.C. 40118, Government-financed air transportation; and 41 U.S.C.
chapter 21 relating to procurement integrity.
(r) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Disputes, Payments, Invoice, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) Other…