Attachment 1- SOW 668-23-101 Construct Chiller Plant and Cooling Tower.docx

DOCX document 26 KB Posted

Attached to
Y1NB--CON-NRM 668-23-101 Construct Chiller Plant & Cooling Towers FY26 Tier 2
Solicitation number
36C26026R0003
Issued by

About this file

This document is a Statement of Work (SOW) for a construction project at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The project involves building a new 4,000 gross square foot chiller plant with cooling towers, with a total project duration of 630 calendar days. The SOW provides detailed technical specifications for drafting and drawing standards, including requirements for CAD software (Autodesk Revit or AutoCAD), file formatting, text specifications, and document transmission protocols.

Key technical requirements include adherence to National CAD Standards, specific drawing and text formatting guidelines, and comprehensive documentation standards. The contractor must deliver as-built drawings and an owner's manual within 30 days of substantial completion, with the manual requiring detailed step-by-step instructions for operating plant equipment and complex chiller plant automation systems. The related federal contract opportunity indicates this is currently a Sources Sought announcement for small businesses in the Commercial and Institutional Building Construction sector (NAICS 236220), with an estimated project value between $10-20 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR CONSTRUCTION SERVICES

Construct Chiller Plant and Cooling Towers Project No. 668-23-101 Mann-Grandstaff VA Medical Center Spokane, WA July 18, 2025

Attachments to this document include the following. Contact the CO if any items are missing.

•Drawings_668-23-101_Construct Chiller Plant and Cooling Tower
•Specs_668-23-101_Construct Chiller Plant and Cooling Tower

1. General Provide construction services to include labor, materials, tools, equipment, transportation, supervision, and other services necessary for “Project 668-23-101, “Construct Chiller Plant and Cooling Towers” at the Mann-Grandstaff VA Medical Center, Spokane, Washington. Scope of work is indicated below. Total project duration shall be 630 calendar days.

2. Statement of Work

2.1 This NRM-IM project will build a new 4000 gross square foot chiller plant with cooling towers in accordance with the provided project drawings and project specifications.

3. Performance of Work

3.1. Where conflicts exist between this SOW and the project specifications, this SOW takes precedence.

3.2. Drafting and Drawing Standards

3.2.1. Adhere to the National CAD Standards (NCS) are available at the website of the National Institute of Building Sciences, Building Smart Alliance. Standards include, but are not limited to: layer naming, sheet naming, file naming, and organization of drawing sets.

3.2.2. Text

3.2.2.1. Text shall be 1/8”minimum height. 3/32” is allowed for details. Do not use stacked fractions. This applies to all notes and dimensions.

3.2.2.2. Where practicable, avoid special AutoCAD characters (i.e. Use “DIA” instead of the special character for diameter: %%C.)

3.2.2.3. Use font: Calibri or Arial; or submit a similar font to the COR for approval.

3.2.3. Miscellaneous

3.2.3.1. All drawings must be set up using Paper space / Model space. Everything must be drawn to scale at full scale (i.e. A 36" door must be drawn 36" wide)

3.2.3.2. The colors of all entities should be BY LAYER with few exceptions.

3.2.3.3. Drawing files with external references or special fonts are not acceptable.

3.2.3.4. When blocks are created, the elements of the block should be drawn with color BYLAYER on layer 0. Blocks shall be drawn to scale.

3.2.3.5. When keyed notes are used, provide leaders pointing to an appropriate place. It is not enough for the keyed note to be near the item. It should point to it.

3.2.3.6. Each drawing file shall be completely independent of any data in any other file, including fonts and shapes not included with the basic CAD software program utilized.

3.2.4. Software

3.2.4.1. Use the current version of Autodesk Revit or AutoCAD for design and provide the files in .dwg to the VA if requested. Test the exporting process to ensure that the exported .dwg will be usable by the VA and will comply with these drafting standards.

3.2.5. VA CAD Tools

3.2.5.1. The following tools are available at the website of the VA Office of Construction & Facilities Management, Technical Information Library. [http://www.cfm.va.gov/til/projReq.asp]

3.2.5.2. NCS.ctb is a plot style table containing all VA and National CAD Standard compliant Pen Weights and Colors. Use of .ctb is required.

3.2.5.3. NCS.lin is a line type definition file that contains special linetypes like “fire alarm,” “high pressure steam,” “fence,” etc. Using this line type file is optional.

3.2.6. Title Block

3.2.6.1. Use the standard Spokane VAMC title block on the TIL

3.2.6.2. Include Project Title.

3.2.6.3. Provide the date with this format: MM/DD/20YY (i.e. 02/16/2016)

3.2.7. Drawing Sheet Dates and Revisions

3.2.7.1. The date for a submittal is to be consistent throughout the entire set.

3.2.7.2. The date on the Title Block is to correspond to the submittal date and change with each submittal.

3.2.7.3. After this time when a drawing is re-issued, the REV section on the Title Block is to be used.

3.3. When a drawing is re-issued the next highest revision number is to be used for all drawings, even though most sheets will skip some revision numbers.

3.4. Document transmission.

3.4.1. VA email servers limit file sizes to 5MB per message.

3.4.2. Construction Contractor shall provide a secured File Transfer Protocol (FTP) site to transfer all contract electronic submittals. The contractor shall send a corresponding email to the COR stating a file is ready for review for each electronic submittal FTP upload, an automatic email from the FTP site is sufficient. The FTP site shall be accessible by VA staff using Government Furnished Equipment (GFE).

3.4.3. AutoCAD Drawings

3.4.3.1. Use "eTransmit" to package all AutoCAD files into file folders. (Use “eTransmit to file folder” rather than “eTransmit to zip file.”)

3.4.4. File Organization

3.4.4.1. File names are to be self-explanatory.

3.4.4.2. Data must be organized into clearly labeled file folders. Folder names must begin with the issue date and include the status of the project.

3.4.5. PDFs

3.4.5.1. PDF drawing files should be created with one PDF file for each discipline (civil, architectural, etc.)

3.4.5.2. If the file exceeds the 25-megabyte limit, break it down into smaller pieces with logical breaking points.

3.4.5.3. PDF drawings must be up-side up.

3.5. As-Built Drawings and Owner’s Manual.

3.5.1. The contractor shall deliver the as-built drawings and owner’s manual to the COR no later than thirty (30) days after substantial completion.

3.5.1.1. The owner’s manual shall contain detailed step by step instructions for the operation of all plant equipment as a system. Manufacturers’ operation manuals are not sufficient as they do not pertain to how the equipment is operated as a system. The chiller plant automation will be very complex therefore, the manual shall explain all plant settings, their adjustable ranges, and the settings at time of beneficial occupancy.

3.5.1.2. The supporting electrical gear shall be supplied with the owner’s manual of similar detail to the chiller plant owner’s manual.

Project 668-23-101, Construct Chiller Plant and Cooling Towers Page 1 of 11