668-25-100 - Presol Contractor Questions and Answers.docx
DOCX document 19 KB Posted
- Solicitation number
- 36C26025R0002
About this file
This document is a Request for Information (RFI) with Questions and Answers for a federal contract opportunity to provide Architect-Engineering (A-E) services for the renovation of 3,000 square feet of vacant space in Building 2 at the Mann-Grandstaff VA Medical Center in Spokane, Washington.
The project is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB). The anticipated A-E contract award is planned for late December 2024, with a 315-calendar day period of performance for design completion. The construction value is estimated between $500,000 and $1,000,000. The RFI provides detailed submission requirements for the Standard Form (SF) 330 A-E qualifications package, including page limits, formatting, and evaluation criteria focused on professional qualifications, specialized experience, capacity, past performance, knowledge of the locality, and construction period services. The secondary selection criterion is geographic location. All offerors must be certified SDVOSBs in the Veteran Small Business Certification (VetCert) database.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26025R0002_1.docx | DOCX document | |
| 36C26025R0002.docx | DOCX document | |
| Presolicitation Notice - 668-25-100 - AE - SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information – Government Response
668-25-100 Renovate Bldg 2 for Admin Space Solicitation Number: 36C26024R0002 Spokane VAMC Below are questions that were submitted by potential Contractors for the above referenced project along with the Government’s answers to the Request for Information.
| Contractor Questions | Government Response | |
| 5. | ||
| Will the VA consider increasing the overall page limit to at least 50? Required pages (9 resumes, 3 projects, Part I, organizational chart) account for 14 of those pages, leaving little space to address Selection Criteria 3, 5, and 6, as well as the secondary selection criterion. | ||
| The SF 330 submission has been amended to read, “must not exceed a total of 35 pages.” |
Page | 2
File details come from the government source that posted it. Updated .