36C26023Q0627_1.docx
DOCX document 15 KB Posted
- Solicitation number
- 36C26023Q0627
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Presolicitation Notice Presolicitation Notice
| SUBJECT* |
| Building 82 and Building 83 Replacement Batteries |
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 98661 |
| SOLICITATION NUMBER* |
| 36C26023Q0627 |
| RESPONSE DATE/TIME/ZONE |
| 05-25-2023 12:00 PACIFIC TIME, LOS ANGELES, USA |
| ARCHIVE |
| 90 DAYS AFTER THE RESPONSE DATE |
SET-ASIDE
| PRODUCT SERVICE CODE* |
| 6140 |
| NAICS CODE* |
| 335910 |
| PLACE OF PERFORMANCE |
| Boise VA Medical Center |
500 West Fort Street, Bldg. 34
Boise ID
| POSTAL CODE |
| 83702 |
| COUNTRY |
| USA |
CONTACT INFORMATION
| CONTRACTING OFFICE ADDRESS |
| Network Contracting Office 20 |
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
POINT OF CONTACT*
Contract Specialist Luke Nesse Luke.Nesse@va.gov
ADDITIONAL INFORMATION
| AGENCY’S URL |
| https://www.va.gov |
| URL DESCRIPTION |
| Dept. of Veterans Affairs |
| AGENCY CONTACT’S EMAIL ADDRESS |
| Luke.Nesse@va.gov |
| EMAIL DESCRIPTION |
| Contract Specialist |
DESCRIPTION
Statement of Work Building 82 and building 83 replacement batteries.
1. Provide all labor to remove, replace and recycle the building 82 batteries (92 cells).
2. Provide Battery-92, ENERSYS VARTA RM-140 1.2V 140AH NICD Flooded, Cells 1 per battery, (92 cells) for building 82.
3. Provide all labor to remove, replace, and recycle the building 83 batteries.
4. Provide Battery-60, Hoppecke Grid Power VL 2-215, Cell count 3 per battery total= (180 cells) for building 83.
5. The contractor will wear the appropriate PPE while providing the Boise VA Medical Center this service.
6. The contractor may be required to mask all staff while on campus.
7. The contractor will schedule work to be done with VA Facility Management Service prior to any work being done. No work will begin until the work is approved to proceed.
8. The contractor will check in with VA Facility Management Service, building 50, when they arrive on campus.
9. Once approval to proceed with work is given the contractor will work to completion without delay until all tasks are complete.
10. The contractor will verify all materials and equipment operate correctly. The contractor will verify all batteries are in new fully charged and good condition.
11. The contractor will provide a written warranty for all batteries.
12. The contractor will clean all affected work areas before leaving campus.
| *=Required Field |
| Presolicitation Notice |
Presolicitation Notice
File details come from the government source that posted it. Updated .