36C26023Q0422 0001.docx

DOCX document 29 KB Posted

Attached to
J045--Boiler Calibration and Tuning Federal contract opportunity
Solicitation number
36C26023Q0422
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 20

View the file

Other files for this federal contract opportunity

Other files attached to J045--Boiler Calibration and Tuning, newest first.
File Type Posted
36C26023Q0422 0002.docx DOCX document
S02 36C26023Q0422.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 05-17-2023 668-23-3-5058-0060 36C260 NCO 20 Network Contracting Office

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661 36C260 NCO 20 Network Contracting Office

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661 To all Offerors/Bidders

36C26023Q0422 05-17-2023

X X X

05/23/2023 5PM

See CONTINUATION Page 668-3630162-5058-851100-2548 0100501X3 The purpose of this amendment is to answer question received and to add CLIN 0003, 1003, 2003, 3003, and 4003 for emergency call and repairs.

Offers are due on 23 May 23 at 5PM Pacific.

PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 350 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every October on the 350 hp boilers. Auxiliary devices, and mainstream flow transmitters shell be calibrated annually.

Subtitle .............. 2X 350 HP Boiler Manufacturer........... Burnham Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit Rated Capacity………. 12,000 pounds per hour Fuel… Natural gas and or #2 fuel oil fired boilers Contract Period: Base POP Begin: 06-01-2023 POP End: 05-31-2024

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 200 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every March on the 200 hp boilers. Auxiliary devices, and mainstream Subtitle .............. 2X 200 HP Boiler Manufacturer........... Burnham Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit Rated Capacity………. 6900 pounds per hour Fuel… Natural gas and or #2 fuel oil fired boilers

20.00
HR
__________________
__________________

2 Hour Emergency Response and Repair Contract Period: Base POP Begin: 06-01-2023 POP End: 05-31-2024

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 350 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every October on the 350 hp boilers. Auxiliary devices, and mainstream flow transmitters shell be calibrated annually.

Manufacturer........... Burnham Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit Rated Capacity………. 12,000 pounds per hour Fuel… Natural gas and or #2 fuel oil fired boilers Contract Period: Option 1 POP Begin: 06-01-2024 POP End: 05-31-2025

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 200 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every March on the 200 hp boilers. Auxiliary devices, and mainstream Subtitle .............. 2X 200 HP Boiler

Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit

20.00
HR
__________________
__________________

2 Hour Emergency Response and Repair

Contract Period: Option 1 POP Begin: 06-01-2024 POP End: 05-31-2025

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 350 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every October on the 350 hp boilers. Auxiliary devices, and mainstream flow transmitters shell be calibrated annually.

Manufacturer........... Burnham Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit Rated Capacity………. 12,000 pounds per hour Fuel… Natural gas and or #2 fuel oil fired boilers Contract Period: Option 2 POP Begin: 06-01-2025 POP End: 05-31-2026

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 200 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every March on the 200 hp boilers. Auxiliary devices, and mainstream Subtitle .............. 2X 200 HP Boiler

Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit

20.00
HR
__________________
__________________

2 Hour Emergency Response and Repair Contract Period: Option 2 POP Begin: 06-01-2025 POP End: 05-31-2026

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 350 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every October on the 350 hp boilers. Auxiliary devices, and mainstream flow transmitters shell be calibrated annually.

Manufacturer........... Burnham Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit Rated Capacity………. 12,000 pounds per hour Fuel… Natural gas and or #2 fuel oil fired boilers Contract Period: Option 3 POP Begin: 06-01-2026 POP End: 05-31-2027

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 200 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every March on the 200 hp boilers. Auxiliary devices, and mainstream Subtitle .............. 2X 200 HP Boiler

Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit

20.00
HR
__________________
__________________

2 Hour Emergency Response and Repair Contract Period: Option 3 POP Begin: 06-01-2026 POP End: 05-31-2027

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 350 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every October on the 350 hp boilers. Auxiliary devices, and mainstream flow transmitters shell be calibrated annually.

Manufacturer........... Burnham Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit Rated Capacity………. 12,000 pounds per hour Fuel… Natural gas and or #2 fuel oil fired boilers Contract Period: Option 4 POP Begin: 06-01-2027 POP End: 05-31-2028

2.00
EA
__________________
__________________

Boiler calibration and tuning- Burnham 200 HP Fire Tube Boilers Boiler tuning and calibration shall be completed every March on the 200 hp boilers. Auxiliary devices, and mainstream Subtitle .............. 2X 200 HP Boiler

Boiler Type............ Fire tube Boiler Year Built Design Pressure........ 200.00 PSI Operating Pressure..... 120.00 PSI [relief valve set pressure] Design Temperature..... 650.00 degrees Fahrenheit

20.00
HR
__________________
__________________

2 Hour Emergency Response and Repair Contract Period: Option 4 POP Begin: 06-01-2027 POP End: 05-31-2028

GRAND TOTAL
__________________
Option Year 1 Total
$
Option Year 2 Total
$
Option Year 3 Total
$
Option Year 4 Total
$
Base+4 Grand Total:
$

Questions:

Q1: Pages 8 and 41 mention that "technicians shall be certified through an ISO 17025 business and provide proof of at least one-year of relevant trade schooling." We perform VA boiler inspections all the time and ISO 17025 has never been a requirement for similar VA boiler inspection contracts we have completed previously. I do not see how it is relevant to the scope of work. Can you please confirm that both the ISO 17025 certification and trade school experience are necessary to perform this contract?

Answer: The calibration devices used have to be iso 17025 certified in order to field calibrate which means they have to meet the specific requirements in order to use for calibrating. If One has the ISO 17025 certification then they are held to that standard.

Q2: - Introduction Section D of the Statement of Work on page 8 states that the contractor "must be able to respond to and to send a certified technician to any emergency service calls within 2 hours of notification and routine calls within 24 hours", however, there is no other.

Answer: This requirement is to insure that if there is a tuning issue that occurs we will have a technician on site within 2 hours for an emergency or within 24 hours for a non-emergency which is up to the VA to determine or we can call in another company to fix the issue.

Q3: Since ISO 17025 is not a standard VHA requirement outlines in VHA 1810 or BEI Boiler Plant Safety Device Testing Manual (7th Edition), can the requirement be removed or better defined? Since the site’s gauges and transmitters can be field calibrated can you please specify which devices may require laboratory calibration as indicated by ISO 17025? Additionally, if ISO 17025 requirement is not removed, will past performance on VA gauge calibration be acceptable?

Answer: The calibration devices used have to be iso 17025 certified in order to field calibrate which means they have to meet the specific requirements in order to use for calibrating. If One has the ISO 17025 certification then they are held to that standard.

Q4: Section 1D states that 2-hour response time is required for emergency and 24 hours for routine calls. However, no emergency support is indicated in the Price Schedule which would indicate there are no emergency support requirements. Could you please either add a CLIN for emergency support or remove any specific response time as the service visits will otherwise be scheduled with the site weeks ahead of time.

Answer: This requirement is to ensure that if there is a tuning issue that occurs we will have a technician on site within 2 hours for an emergency or within 24 hours for a non-emergency which is up to the VA to determine or we can call in another company to fix the issue.

Q5: • Section 6 states that all equipment must be fully functional and 100% of all instruments returned to acceptable working condition.

Answer: This is referring to if they are doing a safety test or calibration or tunning the must have the equipment they are working on able to go back online and cannot leave a job half done or not completed.

Q6: As this is a testing and calibration contract rather than a maintenance contract, could you please specify the contractor’s role in ensuring the site makes all necessary repairs?

Answer: Repairs would be anything that fails or needs replaced as part of the tune, safety devices, calibration.

Q7: Schedule specifies that only calibration and tuning is covered could you please remove the expectation that contractor is responsible for repairs or define how repairs will be billable by adding CLIN?

Answer: If repairs are needed that are outside the scope then there will be a mod request completed for the additional cost and up to the contractor to order and replace the part.

Q8: Are National Board Boiler (internal) Inspections included in this contract?

Answer: No Q9: Are all 4 boilers currently able to run up to 100% on both fuel sources?

Answer: Yes they can run to 100% but 1 is having issues right now with either the fuel or tuning ( which will be resolved before hand)

File details come from the government source that posted it. Updated .