S04 - Site Visit Meeting Doc.docx

DOCX document 19 KB Posted

Attached to
Z2DA-- Shower pan and wall tile demo and replacement (660-23-4-5056-0516) (VA-23-00094732)
Solicitation number
36C25923Q0798
Issued by

About this file

This document outlines requirements for a federal contract solicitation to replace shower pans and wall tiles at the Salt Lake City VA Medical Center. The solicitation seeks bids to provide all labor, materials, equipment, and supervision necessary to complete tile demolition and installation work in two areas of the facility. Questions are due by September 15th and bids are due by September 29th, with confirmation that the construction costs will be between $25,000 and $100,000. The selected contractor must begin performance within 10 days of notice to proceed and finish within 42 weeks, complying with all applicable regulations including Davis-Bacon wage rates. Submitted payrolls and invoices are required on a monthly basis.

View the file

Other files

File Type Posted
Introductory Information and Instructions.docx DOCX document
Answer to Questions.docx DOCX document
36C25923Q0798 0001.docx DOCX document
Introductory Information and Instruction1.docx DOCX document
S04 - Site Visit Meeting Doc.pdf PDF
36C25923Q0798.docx DOCX document
S22- 852.219-75 LOS Certificaiton.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid Meeting

FOR

660-23-4-5056-0516 Shower Pan and Wall Tile Demo and replacement.

The contractor is to provide all labor, tools, materials, equipment, and supervision required to replace the Shower Pan, do tile demolition, install new tiles and seal Concrete at the Telemetry and ICU areas located at the Salt Lake City VA Medical Center as outlined in the Statement of Work and associated documents.

All work must be done in compliance with applicable OSHA, EPA and federal/state environmental regulations and policies. Contractor is responsible for proper handling and disposal of debris, waste and excess fuel generated during completion of this work.

Location: Salt Lake City VA Medical Center

Introductions: Donna Gillette CO and Jeremiah Percy COR Site Visit:

· The pre-bid meeting/site walk is not mandatory.

· Questions during site visit must be written down and submitted to the Contracting Officer to provide answers in an amendment to all interested parties.

Pertinent Dates:

· Questions are due by September 15, 2023, before 10:00 AM MDT. Any questions submitted after this time will not be reviewed or answered. Please submit to Elia-Laritza.Ruiz-Manzo@va.gov

· Bids are due on September 22nd, 2023, that has been extended in this amendment to new due date September 29. 2023 no later than 10:00 AM MDT. Submit via email to Elia-Laritza.Ruiz-Manzo @va.gov.

Site Visit Guidelines:

· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.

· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.

· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.

Solicitation Information:

· Confirmation of construction range: between $25,000 and $100,000.

· An irrevocable letter of Credit ILC or payment bond: are required as outlined in the solicitation.

· Special Standards of Responsibility: Please note solicitation requirements for submittal of OSHA and EMR ratings.

· VAAR clause 852.219-75 Limitation on Subcontracting: please ensure you provide a signed copy of this clause with your bid package.

· Contractor shall begin performance within 10 days after Notice to Proceed (NTP) and complete within 42 days.

Post Award Compliance:

· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor shall submit their weekly certified payrolls with their monthly invoice.

File details come from the government source that posted it. Updated .