S04 - Site Visit Meeting Doc.docx

DOCX document 19 KB Posted

Attached to
Z2DA--442-22-014S CLC Bed Lights Revised (VA-23-00053169)
Solicitation number
36C25923Q0331
Issued by

View the file

Other files

File Type Posted
Pre-bid site visit attendance 2023.05.23.pdf PDF
36C25923Q0331 0002.docx DOCX document
S02 -Sol 36C25923Q0331.docx DOCX document
12-13-22 - Past Performance Questionnaire.docx DOCX document
Construction Safety memo.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid Meeting

FOR

442-22-014S CLC Bed Lights Revised

The contractor is to provide all labor, tools, materials, equipment, and supervision required to construction services to correct physical Security deficiencies at Cheyenne VA Medical Center located at 2360 East Pershing Blvd., Cheyenne WY, 82001 as outlined in the Statement of Work and associated documents.

All work must be done in compliance with applicable OSHA, EPA and federal/state environmental regulations and policies. Contractor is responsible for proper handling and disposal of debris, waste and excess fuel generated during completion of this work.

Location: Cheyenne, VA Medical Center

Introductions: Josiah Benton CO and Brian Kelly.

Site Visit:

· The pre-bid meeting/site walk is not mandatory.

· Questions during site visit must be written down and submitted to the Contracting Officer to provide answers in an amendment to all interested parties.

Pertinent Dates:

· Questions are due by May 26th, 2023, before 10:00 AM.MT. Any questions submitted after this time will not be reviewed or answered. Please submit to Elia-Laritza.Ruiz-Manzo@va.gov

· Bids are due on June 16th, 2023, no later than 10:00 AM MT. Submit via email to Elia-Laritza.Ruiz-Manzo@va.gov Site Visit Guidelines:

· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.

· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.

· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.

Solicitation Information:

· Confirmation of construction range: between $25,000 and $100,000.

· Bid Guarantee & Payment/Performance Bonds: are required as outlined in the solicitation.

· Special Standards of Responsibility: Please note solicitation requirements for submittal of OSHA and EMR ratings.

· VAAR clause 852.219-75 Limitation on Subcontracting: please ensure you provide a signed copy of this clause with your bid package.

· Contractor shall begin performance within 10 days after Notice to Proceed (NTP) and complete within 60 days.

Post Award Compliance:

· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor shall submit their weekly certified payrolls with their monthly invoice.