S02-Updated SOW - Remodel Audiology_Amend_1 12-06-22.doc

DOC document 61 KB Posted

Attached to
Z2DA--623-23-107 Remodel Audiology (VA-23-00012198)
Solicitation number
36C25923Q0023
Issued by

View the file

Other files

File Type Posted
36C25923Q0023 0001.docx DOCX document
S02-NEW - Calculation Worksheet for Self-Performed and Subcontracted Work.docx DOCX document
S02-3-10-2021 Past Performance Questionnaire.docx DOCX document
36C25923Q0023.docx DOCX document
S02-Audiology Space Drawing.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work / Construction Project # 623-23-107 Renovate for Audiology Space Request contractor provide all required labor, material, equipment, and site investigations to complete renovation of the space as described below.

The objective of this project is to remodel audiology space on 5th floor B-wing of building 1 (refer to attached pdf drawing for reference). The entirety of space is approximately 922 sq. feet. Renovation area include room 5B35-1, 5B38-1, 5B39-1, 5B40-1, 5B41-1, 5B47-1, 5B49-1, 5B50-1, and 5B51-1. The remodeled space will require new luxury vinyl tile flooring, wall repair and paint, tile and wall demo and the addition of a new mop sink, and three wall hung sinks. During construction, remove all furniture and relocate to a secure storage area. All spaces shall be inspected for asbestos and lead paint prior to demolition work. If asbestos is found, a modification to the contract will be issued. The remodel should include the following:

Room
Addition
Demolish
5B35-1
New flooring/wall repair and paint. New wall mount sink.
Demo VCT flooring including mastic abatement
5B38-1
New flooring/wall repair and paint
Demo ceramic tile flooring and wall. Demo wall sink. Tiles will stay
5B50-1
New flooring/wall repair and paint
Demo VCT flooring including mastic abatement. Remove wall tiles
5B51-1
Add mop sink and repair and paint upper wall
5B39-1
New flooring/wall repair and paint. Combine space with 5B-40. New wall mount sink.
Demo tile showers and tile from walls and floor. Demo wall between 5B-39 and 5B-40.
5B40-1
New flooring/wall repair and paint. Replace door entry with wall. Repair Ceiling in area of wall removal to provide continuous ceiling through area.
Demo VCT flooring including mastic abatement. Demo and remove door and frame to 5B-40.
5B41-1
New flooring/wall repair and paint. New wall mount sink.
Demo VCT flooring including mastic abatement
5B47-1
New flooring/wall repair and paint
Demo VCT flooring including mastic abatement
5B49-1
New flooring/wall repair and paint
Demo VCT flooring including mastic

Renovation considerations shall include but are not limited to the following:

a) A phasing plan shall be developed to mitigate disturbance to the department. The space must remain fully functional during construction.

b) Existing wall art painted directly on the walls shall remain untouched. All removable wall art shall be removed during construction, stored in a safe location, and returned to the same location upon completion.

c) Flooring to be Milliken LVT Wood #EUC 122 Eucalyptus Salinga Planks 7”x48”. Wall paint to be Sherwin Williams #SW-7649 Silverplate Satin Enamel, cove base to be Roppe Pinnacle color: Charcoal 123 Standard Toe 4”.

d) Contractor to meet all VA Infection Control regulations while working in the area, including but not limited to ICRA barriers, negative air and walk off mats.

Prime contractor shall comply with NFPA, NEC and Life Safety Codes, ADA, VA Design Criteria / manuals, construction standards and other required standards for the development of construction documents. Prime contractor shall provide one year of maintenance and inspection service following beneficial use. The space conditions and the execution of this project shall proceed with minor interference to the operation of the medical center and shall comply with all requirements for infection control, utility interruptions, fire protection, and all other safety requirements of the contract. Contractor is required to attend a site visit after the project is awarded to familiarize themselves with existing conditions to be encountered during construction.

Construction is to be completed in 180 calendar days from notice to proceed.