S04 - Questions and Answers No 1 - 10-25-2021.docx

DOCX document 17 KB Posted

Attached to
Z1DA--554-22-135 Install Critical Electrical Circuit for Lab Analyzer
Solicitation number
36C25922Q0011
Issued by

View the file

Other files

File Type Posted
S04 - Site Visit Attendance.pdf PDF
36C25922Q0011 0004.docx DOCX document
S04 - Questions and Answers No 2 - 10-29-2021.docx DOCX document
S04 - Pre-Bid Meeting Attendance 10-27-2021.pdf PDF
36C25922Q0011 0003.docx DOCX document
Drawing page 14-1 updated proj 554-22-135.pdf PDF
36C25922Q0011 0002.docx DOCX document
36C25922Q0011 0001.docx DOCX document
36C25922Q0011.docx DOCX document
S02 - Site Map RMR VAMC.pdf PDF
General Decision Number - CO20210020.pdf PDF
S02 - Specifications.pdf PDF
S02 - Drawings.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions—36C25922Q0011 Install Critical Electrical Circuit for Lab Analyzer Q1: If necessary is core drilling required to be at night?

A1: No, but coordination/scheduling is required to be sure that we are not making noise/vibration while a medical procedure is being performed nearby.

Q2: If necessary are floor x-rays required for core drilling?

A2: No, optional. The narrower part of the slab (web) avoids rebar. We do not have pretensioned cables.

Q3: Per drawing 11, its calling for a 350amp 120/208V panel fed from the transformer. Our engineer seems to think this only needs to be a 250amp rated panel. Please confirm A3: New panel 03-CL24 S-3 on page 11 of the drawings can be downsized to a 250 A 120/208 V panel if engineering calculations are provided to show that it is code compliant.

Q4: Are completion dates flexible due to availability of materials?

A4: The contract period of performance (PoP) is 150 calendar days. The PoP is based on operational requirements. The government is aware of national supply chain issues, and if sourcing materials precludes meeting this deadline, a no-cost time extension may be considered.

Q5: Do we get 150 working days to complete the project?

A5: The contract PoP is 150 calendar days. The 150 calendar days includes submittals/procurement, planning, site prep, mobilization, and execution. See question #4 for potential procurement issues.

Q6: How long does it take to get a badge when you bring someone new to the job?

A6: Allow two weeks minimum. The badging process depends on the contractor’s availability to go to the badging office on our campus.

Q7: Do we have to provide fire extinguishers?

A7: Yes.

Q8: Will we be able to use the elevator and do we have to install pad's to protect the walls of the elevator?

A8: Elevators are available for your use. Install pads to protect the walls of the elevators only if there is a chance of scratching or damaging the walls.