Contract Opportunity Presolicitation Notice

PRODUCT SERVICE CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

RESPONSE

DATE/TIME/ZONE

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

Required Field Contract Opportunity Presolicitation Notice J041 (CONS)Topeka AHU replacement, building 9, 2nd floor

(VA-21-00059538)

80111 36C25921R0074 06-23-2021 14:00

CENTRAL TIME, CHICAGO, USA

N 238220 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 aldo.girany@va.gov VHA –Member Services Call Center (VHA-MSCC)

3401 SW

21st street, Building 9 Topeka KS 66604

66604

The Veterans Health Administration – Member Services Call Center (VHA-MSCC) located at 3401 SW 21st street, Building 9, Topeka KS 66604

I. GENERAL: THIS IS A PRESOLICITATION NOTICE THE FULL SOLICITATION WILL BE POSTED ON or AFTER 5/24/2021 Air Handler Unit (AHU) replacement

NAICS CODE 238220

This solicitation will be a Service-Disabled Veteran Owned Small Business Set-Aside.

Magnitude; $250,000.00 - $500,000.00

Description of Work

Remove the current Air Handler Unit (AHU) in a confined space on the 2nd floor of building 9 and replace it with a new AHU that includes any duct work replacement needed to complete the installation.

The Contractor shall provide all labor, material to install new VA approve AHU units and exhaust fans for building 9.

The Contractor shall pump-down and recover the refrigerant from all units effected by this project.

Disconnect, de-pipe, detach, and remove the existing unit equipment at an offsite disposal site or recycling center in compliance with the regulatory requirements.

Provide and/or connect all required piping, electrical conduit and wiring, controls, ductwork, VAV boxes, condensate, insulations and necessary appurtenances.

Remove, cut, alter, replace, patch and repair existing work as necessary to install new equipment/component. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown

The Contractor is responsible for upgrading control for each unit to digital control system which includes but are not limited to upgrade actuators, VAV boxes, thermostats, wiring to such components, and integrate those to existing Johnson Control system.

The Contractor shall remove existing insulation and reinsulate the ducts. The contractor shall thoroughly clean all ductwork. The cleaning shall include all supply and return ductwork supply as well flex ducts from the mains to the diffusers. All diffusers shall be cleaned with appropriate method.

The Contractor shall provide and install concrete pad, vibration isolator, piping, condensate drain, floor drain for the new unit as required.

The Contractor is responsible for testing and balancing of all installed equipment and provide a detailed digital report to VHA MS COR and Eastern Kansas VA representative.

The Contractor shall provide 2D CAD (REVIT 2015 or later) as built drawing shall be provided to show all work, equipment, piping, penetrations, interior/exterior features, cables, panels, etc. that are to be installed in this project.

Contractor shall provide an adequate work force to complete all work associated with this project (i.e. plan, design, installation, and removal of project debris, and final cleanup.

File details come from the government source that posted it. Updated .