36C25919R0098-0002000.docx
DOCX document 129 KB Posted
- Solicitation number
- 36C25919R0098
About this file
36C25919R0098 0002 36C25919R0098 0002.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25919R0098-0001000.docx | DOCX document | |
| 36C25919R0098-0001001.pdf | ||
| 36C25919R0098-005.pdf | ||
| 36C25919R0098-008.pdf | ||
| 36C25919R0098-003.pdf | ||
| 36C25919R0098-004.pdf | ||
| 36C25919R0098-010.pdf | ||
| 36C25919R0098-002.pdf | ||
| 36C25919R0098-006.pdf | ||
| 36C25919R0098-007.pdf | ||
| 36C25919R0098-001.docx | DOCX document | |
| 36C25919R0098-009.pdf | ||
| 36C25919R0098-000.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 660-19-110 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 To all Offerors/Bidders
36C25919R0098 04-25-2019
X X X
The Purpose of Amendment A00002 is to:
a. Add updated answers.
b. e.
All other terms and conditions remain unchanged.
Terminal HEPA 660-19-110 Solicitation Questions
UPDATED ANSWERS TO SELECT QUESTIONS
1. Q: Will owner be furnishing the shop drawings with the units or prior to shipment of units?
A: The manufacturer should provide manufacturer installation instructions and drawings with the shipment of hoods and HEPA units. The HEPA fan filter unit drawing is provided with the documents.
1. Q: Comments were made at the pre-bid about requiring compliance to USP 800. It is noted in the spec. This is a code on handling of drugs inside a pharmacy and does not provide design guidance. Are we to hire a USP 800 expert consultant, and who does the pharmacy use currently?
A: Pharmacy does not use a USP 800 consultant currently, but below are CETA Certifiers the SLC VA has used in the past:
Andy Testing and Consulting Inc.
Yancy Rod- Intelligent Enclosures
This is not a design, a CETA assessment has been done in the past and the gap noted is the installation of the terminal HEPAs. In order for USP 800 compliance, the contractor is responsible for installing HEPA units, testing and balancing, and certifying with a CETA certifier.
1. Q: Will the addition of HEPA filters impact the control system for the rooms?
A: The addition of HEPA filters should not impact the control system for the rooms. The low-profile filters with a fan were chosen to compensate for any static pressure loss across the HEPA filter. During testing and balancing of the system, the fans should be set to maintain a certain pressure in the rooms according to USP 800 standards and will not need to be integrated into the control system.
1. Q: What are the changes to the control system and who to do that work?
A: The addition of HEPA filters should not impact the control system for the rooms. The fans in the low-profile fan filters should compensate for any static pressure loss across the HEPA filter. The system will need to be tested and balanced after installation to ensure proper air flow. It is the responsibility of the contractor to test and balance the system, and set the fans to regulate the pressure of the rooms per USP 800 standards. After testing and balancing is complete, it is the contractor’s responsibility to ensure the room is certified with a CETA certifier.
1. Q: Has the pressure gradient noted on the drawings changed and if so, to what?
A: The 2017 USP General Chapter <800> Hazardous Drugs – Handling in Healthcare Settings elaborates on room pressure requirements for sterile and non-sterile compounding. The updated drawing of the space below shows the pressure relationships are and what they will need to be maintained at. It is reflected correctly on the drawing below.
image1.png
File details come from the government source that posted it.