36C25918R0261-00001000.docx

DOCX document 19 KB Posted

Attached to
554-18-1-540-0019 Legionella P and Scald Protection Plan (VA-18-927619)
Solicitation number
36C25918R0261
Issued by

About this file

36C25918R0261 00001 36C25918R0261 00001.docx

View the file

Other files

File Type Posted
36C25918C0170-000.docx DOCX document
36C25918R0261-00001001.jpg JPG image
36C25918R0261-006.zip ZIP file
36C25918R0261-004.zip ZIP file
36C25918R0261-005.zip ZIP file
36C25918R0261-009.zip ZIP file
36C25918R0261-001.docx DOCX document
36C25918R0261-011.zip ZIP file
36C25918R0261-013.pdf PDF
36C25918R0261-015.pdf PDF
36C25918R0261-014.pdf PDF
36C25918R0261-008.zip ZIP file
36C25918R0261-016.docx DOCX document
36C25918R0261-012.zip ZIP file
36C25918R0261-007.zip ZIP file
36C25918R0261-010.zip ZIP file
36C25918R0261-003.zip ZIP file
36C25918R0261-002.zip ZIP file
36C25918R0261-000.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 00001 none 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 To all Offerors/Bidders

36C25918R0261 04-03-2018

X x x The purpose of this amendment is to answer the questions received and include the site visit sign in sheet.

All other terms and conditions remain the same.

Questions

1. Will a temporary parking space/area be provided for contractor on site during the performance period?

Answer: Yes.

1. Drawings for physical plant and several of the buildings were not provided as part of the solicitation. Will a design analysis or some other descriptive document be provided that explains the water systems?

Answer: Yes.

1. Will contractor have full access to the entire site or will an escort be required?

Answer: Mostly. But, there are certain restricted areas due to either safety or security reasons which would require coordination for access with the Contracting Officer several weeks ahead of time.

1. What is the VA’s intent for identifying dead legs? The timeframe and cost are not in line with walking through the facility and inspecting the plumbing system. Are there known dead legs that the contractor will be told about and then investigate or will it be a paper/CAD review?

Answer: As per the statement of work, the intent is to determine areas of risk for the growth and potential presence of the Legionella P. pathogen, and how to eliminate this risk. A thorough physical survey and evaluation of as-built conditions are required.

1. A flushing plan for the existing domestic water system was emphasized during the site visit. The best method to develop this is through modeling the water system, which will add significant cost. How does the VA propose the contractor to develop and provide the flushing plan?

Answer: Excellent question. Extensive building plumbing information and design model data shall also be available as noted in previous government responses to questions in #1 and #2.

1. Can you please verify that the 90-day performance period is anticipated to be sufficient to complete the requested scope?

Answer: Currently, this is not anticipated to be an issue for the successful bidder; however, reasonable requests along with relevant justifications for additional time may be made through the Contracting Officer should the need arise.

See attached document: S04 Site visit Sign in sheet.