About this file

36C25819Q0309 S02_Attachment 02_Schedule LLVA SOW Duration.pdf

View the file

Other files

File Type Posted
36C25819Q0309-0001001.pdf PDF
36C25819Q0309-0001000.docx DOCX document
36C25819Q0309-0002000.docx DOCX document
36C25819Q0309-004.pdf PDF
36C25819Q0309-001.docx DOCX document
36C25819Q0309-002.pdf PDF
36C25819Q0309-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 02

ATTACHMENT 02

SCHEDULE

LLVA Pipe Replacement SOW Durations

Project # 605-19-420

1 pages

26 June 2019

Loma Linda, California VA Health Care System (605)

Urgent Repair Water Main

CONSTRUCTION

LLVA City Water Pipe Replacement Proposal

Scope of Work Durations

STEPS PROCEDURE DURATION

PHASE I - CITY WATER MAIN 6" DIA

1 Confirm positive shutoff of valves prior to air separator tank. 2 HRS

2 Build pipe assemblies onsite. 5 DAYS

3 Perform city water shutdown, drain, demo existing piping and install new assemblies, test and re-establish service.

8 HRS

4 Connect soft water supply to new city water main 6" pipe.

No City Water shutdown is required for this operation.

Only the soft water system will be affected and will require to be shutdown.

8 HRS

PHASE II - CITY WATER LOOP

1 Build pipe assemblies onsite. 5 DAYS

2 Perform city water shutdown, drain, demo existing piping and install new assemblies, test and re-establish service.

8 HRS

S02_Attachment 02_Scheduled LLVA Pipe Replacement SOW Durations
S02_Attachment 02 Scheduled LLVA Pipe Replacement SOW Durations