36C25819B0022-0002013.pdf
PDF 471 KB Posted
- Solicitation number
- 36C25819B0022
About this file
36C25819B0022 0002 36C25819B0022 Demolition Building 51 LLVAHCS 6-19-2019 RFIs and Responses.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25819B0022-0003000.docx | DOCX document | |
| 36C25819B0022-0002014.pdf | ||
| 36C25819B0022-0002016.pdf | ||
| 36C25819B0022-0002015.pdf | ||
| 36C25819B0022-0002012.docx | DOCX document | |
| 36C25819B0022-0002017.pdf | ||
| 36C25819B0022-0001000.docx | DOCX document | |
| 36C25819B0022-001.docx | DOCX document | |
| 36C25819B0022-003.pdf | ||
| 36C25819B0022-004.pdf | ||
| 36C25819B0022-002.docx | DOCX document | |
| 36C25819B0022-000.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25819B0022 Demolition Bldg 51 LLVAHCS RFI and Responses
RFI RESPONSES
Please verify access for equipment & debris hauling.
Will temporary removal of smoke pit canopy be the acceptable route?
Temporary removal of the canopy and smoking area would be the preferred removal route. Some grading and temporary drainage measures will be required to accommodate haul route. Reference attached diagram titled "Attachment 11: Haul Route - Demo Bldg 51".
Please verify demolition and replacement of sidewalk on Attachment 3:
To remove “duct bank” - utility junction boxes, is this desired?
Or will junction boxes be left for future building at site where building 51 currently sits? Yes.
Please verify if fiber optic cable removal only to the basement level is acceptable?
Or if cable needs to be removed to upper level floors? It is acceptable to remove cable back to panel from which it originates.
For Dust Control, is use of the red fire hydrant next to bridge (in parking lot) acceptable?
This hydrant or the hydrant located near building 52 may be used for dust control. Whichever allows the least amount of interference to patient access. Contractor will provide fire hose ramp anywhere hose crosses path of travel.
Where do the hearing booths need to be relocated? 2nd Floor of Main Hospital, in research corridor.
Is contractor responsible for anything beyond reassembly of hearing booths (ie electrical, partitions, walls)?
Yes, minor tenant improvement will be required, to include electrical and data. The reconfiguration and refinishing of floors and walls will be required to accommodate both booths. SOW states 800 sq. ft. but the total tenant improvement may be closer to 1,000 sq. ft.
Is a certified technician required to reassemble hearing booths? Yes.
Please verify storm drain installation and how it applies to this project (Ref: Notes 27 thru 48 attachment 1)?
Construction notes are provided for informational purposes. Notice these plans were the plans for original construction of building. Notes in RED are addressing specific demo concerns.
Please verify that the sewer is to be capped off 5’ from building. Remove sewer utility back to point of connection.
Please indicate laydown area for dumpsters and heavy equipment.
Laydown area will be located to the south of the building 51 footprint. Current area is a small hill and requires grading and temporary drainage measures. Laydown area is identified in attached diagram titled "Attachment 11: Haul Route - Demo Bldg 51".
During the site visit the VA suggested using the route through the smoking area for removal of the demolished building. Will the VA remove and store the canopy and equipment in the smoking area for the duration of the project? Demo contractor to disassemble and re-assemble smoking area canopy.
Will the sidewalk at the west end of building 51, that provides passage from the south parking to the front entry, be closed for this project? Sidewalk should be kept open as much as possible. When necessary, patients will be re-directed west through the parking lot to alternate sidewalks.
The fiber running to Bldg 51 and the Data Centers on 1st and 3rd floors are to be removed. Fiber is fed from Service Bay 7.
Please provide floor plans showing locations of data centers, path of travel and any obstructions for removal of fiber optics from Data Centers on 1st and 3rd floors. Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Will shoring be required between Bldg. 51 and Main Bldg.
where duct bank is being removed? Follow all OSHA requirements and recommendations for proper shoring methods.
Will shoring be required between Bldg. 51 and Nursing Home Building? There is only a 6’ sidewalk between the the two buildings. Follow all OSHA requirements and recommendations for proper shoring methods.
Can removal of duct bank and replacement of sidewalk between Bldg. 51 and Main Building be completed during normal work hours? Yes.
Is sidewalk branching off main sidewalk to northwest entrance of Bldg. 51 be included in demolition or repaired in place? Reference sheet A-0.3. The 27'7" branch of sidewalk is to be removed.
Demolition to include removal of footings, foundation, sand and vapor barrier. Please provide detail from building documents showing details. Reference sheet C-3 and S2.1. Wall sections sheets A-5.2 and A-5.3 are included in this amendment as attachment 13.
Attachment 1 states to Demo duct bank and repair wall. Is this a below grade concrete wall to basement of Main Bldg.? Reference sheet P-1.0 and H-1.0 for general location of sleeves through foundation wall to be repaired.
Attachments 9 and 10 states “Repair Fire Wall”. What is the extent of repairs needed? Drywall patch from removed lines?
Is wall painted?
Attachment 4 and 5 apply as well. Patch and paint drywall penetrations. Drywall is 2hr rated wall. Penetration repair rough measurements: 12"x36", 12"x24", 40"x36", and an 8" diameter pipe. Pictures attached, see attachment 14.
Attachments 9 and 10 states “Repair Foundation after Removing Lines” at the Main Building. Please provide either the construction drawings or as-builts showing foundation/footing for main building.
Attachment 4 and 5 apply as well. Plan for 20 penetrations, varying size. Wall is 12" thick. See attachment 15, main hospital as-builts 1-S12 Plan C and 1-S40 Section C.
Pictures attached see attachment 14.
What is the construction of the roof at Bldg. 51? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
IFB 36C25819B0022 LLVAHCS Care Center Demolition of Building 51
Disassemble & relocate two (2) audio booths. Please provide manufacturer and model of these booths to determine how to disassemble/reassemble?
Reference As-Built sheet E4.5 for power and signal plan. Reference Attachment 16, Spec 13035 Sound Conditioned Rooms, for manufacturer info. Reference Attachment 17, Supplement A1_2 for Vendor Information.
Where on second floor are audio booths to be relocated and what is current wall configuration? Floor plan, dimensions, photos needed to determine if pricing for wall reconfiguration is required in bid proposal.
2nd Floor of Main Hospital, in research corridor. Yes, minor tenant improvement will be required, to include electrical and data. The reconfiguration and refinishing of floors and walls will be required to accommodate both booths. SOW states 800 sq. ft. but the total tenant improvement may be closer to 1,000 sq. ft. The portion of the second floor is highlighted in Attachment 20.
What is the level of infection control need at 2nd Floor Main Building where audio booths are being relocated? ICRA protection of Class III will be required. ICRA containment, negative air, manomoter, etc.
What are the work hours at 2nd Floor Main Building where audio booths are being relocated? Monday to Friday, 6am to 4pm
Are there any know obstacles in path of travel to relocate the audio booths? Yes, moving from one building to another, transporting from ground to second floor, narrow hallway access, etc.
Please provide contractor work staging area for construction activities as well as demolition trucking ingress/egress travel routes. Addressed above.
What are the liquidated damages for this project? FAR 52.211-10 Liquidated damages is not listed in the solicitation.
Item B.2 Project Scope, section ii, i: “Prepare approximately 800 sf of research space to receive two audio booths.”
Correction: Prepare approx. 1000 sf Item B2 Continued - Please provide detailed description of subject area preparation including, but not limited to any possible electrical, comm, mechanical, architectural and structural work requirements. Addressed above.
Item B2 Continued - Will the floor area be required to be raised to allow for the height of the audio booths? Possibly, coordinate with audio booth vendor.
Item B2 Continued - Please provide audio booth drawing specification. Addressed above.
Item B2 Continued - Will the contractor be required to provide electrical and/or other utilities to the audio booths on the second floor of the main building? Yes
Item B2 Continued - Will the Contractor be required to provide any type of calibration of the audio booths being removed?
Sound booths will need to be installed to function in same capacity as they function in building 51. Audiology user, through coordination with COR, will perform calibration and have final approval on audio booth installation. VA recommends to coordinate with audio booth vendor to perform calibration/inspection upon completion of re-assembly.
Is the smoking area being demolished due to the fact that this is the only access to the project for our heavy equipment and trucks? No, this area is not being demolished. This area will be temporarily re-purposed. See above.
What is the building material and the roof material? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Are the sound rooms being demolished or relocated? See above.
During the site visit, there was a mention of a sound proof room that will need to be relocated. There is no mention of this in the plans and specifications, can you elaborate? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Audio Booth Questions -
What are the dimensions of 2 booths? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Double walled or single walled? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Audio Booth Questions Continued Do they have hookup to HVAC or fans? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Electrical connection included in relocation? If so what is required? See above.
What are existing electrical connections? Reference Attachment 18, 1-E149 for rough estimate of electrical in space to be renovated.
Requirements how many outlets inside or outside etc? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
What floors are they being installed? See above.
Are these replacements and thus we need to remove existing?
Or are these being installed in empty rooms? See above.
Is there any abatement anticipated for this project? If yes please see next four questions
Building 51 was built around 2006, so no abatement is expected. Abatement is expected in renovation area. Reference Attachment 19, Asbestos and Lead reports, for second floor area being renovated.
What is the notification period? Refer to specification 01 35 26.
Does an abatement plan have to be submitted; within what time frame?
Yes, reference specification 01 35 26 "Plans Required". This will be part of the Accident Prevention Plan. "Submit the APP to the COR for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP."
What is the certification/clearance process required (clean environment to work) who would be responsible for providing inspection?
From the specs, "A Certified Safety Professional (CSP) with specialized knowledge in construction safety or a certified Construction Safety and Health Technician (CSHT) shall randomly conduct a monthly site safety inspection. The CSP or CSHT can be a corporate safety professional or independently contracted. The CSP or CSHT will provide their certificate number on the required report for verification as necessary.
1. Results of the inspection will be documented with tracking of the identified hazards to abatement.
2. The COR will be notified immediately prior to start of the inspection and invited to accompany the inspection.
3. Identified hazard and controls will be discussed to come to a mutual understanding to ensure abatement and prevent future reoccurrence.
4. A report of the inspection findings with status of abatement will be provided to the COR within one week of the onsite inspection."
Would abatement period count towards 60 day schedule? Yes, abatement can happen in conjunction with demo work of building 51.
During the jobwalk, it was mentioned that we would be tearing down the smoker patio in order to gain access to the site with equipment, wanted to clarify if that is the case See above.
Yes
Is there an asbestos and lead paint survey performed on the building? See above.
Will contractor have to maintain the silt fence and straw waddles placed around the building perimeter, once the project is complete? Once project is complete there is no expectation for contractor to maintain site.
SOW says to “relocate” audio booths. Does this include final electrical connections? If so, is there enough power at the new location or does additional power need to be run to the location? Sufficient power exists at new location. See sheet E4.5 deductive alternate #7 narrative for specific power requirement.
If audio booths require additional power run, where and how far is the nearest source? Service bay 6 is in very close proximity.
To what extent will the VA empty Building 51 prior to contractor’s start of work? Will all items not attached to the building be removed prior to start? If not, what will remain for contractor to include? Expect to remove and dispose of equipment, desks, chairs, and furniture not attached to walls in addition to items attached to wall.
Room IG-210 is a “Laser” room. Will the laser equipment be removed by VA prior to construction start? If not provide product data for this equipment. Yes, this will be removed.
Are there any items in building requiring special consideration prior to or during demo? Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
There appears to be a large awning or canopy over the fountain and hardscape. What is this made of?
The awning remains and is not going to be demo'd. Part of the awning may need to be disconnected and temporarily pulled back, but this will need to be put back to original state prior to completion of contract.
Can contractor fence off fountain area at northeast corner of building from patients/staff/visitors? Fountain does not exist. A portion of the northeast area may be fenced off.
The southwest corner of the building goes right up to sidewalk.
How much of the surrounding sidewalks can be closed to foot traffic around the building? Sidewalk should be kept open as much as possible. When necessary, patients will be re-directed west through the parking lot to alternate sidewalks.
Is the red line around the building shown on Attachment 3 (Site Plan) the location of temp fencing? If so, recommend extending fencing to include closing off the sidewalk between Bldg. 51 and Nursing Home Building to the east and between Bldg. 51 and Main Bldg.
The north side will require the extension of the fence when the duct bank and sidewalk is removed and the sidewalk repaired. Fence line location will be close to the red line, yes. Final location will be approved by COR prior to start of demo. Access to Nursing home building should be maintained as much as possible.
Can VA provide plan showing location for temporary fencing?
This will provide contractor with limits of work area, possible sidewalk repair quantities and foot traffic control needs. See above.
Please provide a conference call number for contractors to call in and listen to the public bid opening. This is important feedback and required by our bonding agent. When only an award is posted we are unable to provide the number of bidders, range in pricing and how we placed.
This is not an option. Bids will be opened in a public location. Bidders have the option to attend in person or submit their bids in accordance with the solicitation. An abstract of received bids will be posted after the bid opening.
Refer to Attachment 12 Bldg 51 As-Built drawings for Bldg 51.
Provide structural framing and roof plans.
Drawing C-1 has a note at Building Section C on the south side of the building states “Cut and cap northern SD line at this point.” This conflicts with Section C-C on C-3 which states “Protect in place.” Should the storm drain be cut and capped or protected?
The note on C-1 should be moved to the west, to the westerly side of the most western SD lateral coming from the building's roof drain. The "protect in place" note on C-3 is refering to the southern most SD line coming from the drain inlet.
The audio booths are provided with floors depending on the existing building and what is part of the build out (if any): Information on the flooring for the audio booths can be found in the as-built drawings for building 51, see attachment 12.
If the build-out includes a depression or pit in the building, to install the booths then we provide a floor as part of the booth and it can come with or without carpet. The floor is generally a 4” steel floor on isolation rails to reduce vibration noise into the chamber/booth (double wall note 1 or 2)). This is not a question. See response above.
If no depression but the build-out allows for a raised floor around the booth (audiology area) then the above occurs. This is not a question. See response above.
If not depression or raised floor we will provide a special low profile floor to comply with ADA entry by laying down a noise reducing pad (3/8”) with a 1/8” steel plate on with we mount the booth. This reduces any noise due to not having the standard isolated floor (see low profile drawing This is not a question. See response above.