36C25725R0058 756-22-206 Repair Building Envelope.pdf
PDF 1 MB Posted
- Solicitation number
- 36C25725R0058
About this file
This is a Department of Veterans Affairs solicitation for a construction contract to repair the building envelope at the El Paso Veterans Affairs Health Care System. The project (Solicitation #36C25725R0058) is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with a project magnitude between $2,000,000 and $5,000,000, using NAICS code 236220. The scope involves comprehensive restoration and repair of the building envelope and moisture protection systems, including roof, skylights, windows, brick walls, pre-cast concrete panels, and building wall and roof penetrations.
Key contract details include a site visit scheduled for August 13th, 2025 at 9:30 AM MDT, with the location at 5001 N. Piedras Street, El Paso, Texas. Contractors must submit Request for Information (RFI) questions by August 18th, 2025 at 5:00 PM MDT via email. The contract performance period is 300 calendar days, with the contractor required to commence work within 14 calendar days after receiving the notice to proceed. The solicitation emphasizes strict compliance with service-disabled veteran-owned small business requirements, with specific limitations on subcontracting and mandatory certifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________
(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25725R0058
X
07/25/2025
756-22-206
36C257
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr.
Building #171, Room B32 Temple TX 76504
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr.
Building #171, Room B32 Temple TX 76504
Andres Garcia 254-899-6066 andres.garcia1@va.gov
PROJECT #756-22-206 REPAIR BUILDING ENVELOPE
The Contractor shall provide all labor, supervision, materials, equipment to restore and repair the building envelope and moisture protection systems at the El Paso Veteran Affairs Health Care System (EPVAHCS).
Restoration and repair of the building envelope and moisture protection systems to include but not limited to the roof, skylights, windows, brick walls, pre-cast concrete panels and any building wall and roof penetrations.
This is a competitive requirement Set Aside for 100% Service-Disabled Veteran Owned Small Business (SDVOSB).
The Magnitude of the construction project is between $2,000,000 and $5,000,000.
The applicable NAICS code for this project is 236220 Size Standard: $45M Site Visit shall be held on August 13th, 2025 @ 9:30 AM MDT. All interested Contactors shall meet at the El Paso Veteran Affairs Health Care System (EPVAHCS) Medical Center, located at 5001 N. Piedras Street, El Paso, Texas 79930. Meet at the main entrance on the 3rd Floor of the El Paso VA Medical Center to obtain visitor badges.
POC for the site visit shall be Steven Ambriz.
Cut off for submission of RFI(s)/Questions shall be August 18th, 2025 @ 5:00 PM MDT. All RFI(s)/Questions must be emailed to the following email: andres.garcia1@va.gov. Pleaseinclude the solicitation No. 36C25725R0058 on subject line of your email when submitting your RFI questions or proposal.
RFI answers shall be posted in SAM.gov on or around August 22th, 2025, no later than 5:00 PM MDT.
14 300
X X 52.211-10
X 10
0 10:00 AM MDT
08-25-2025
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C257
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr.
Building 171, Room B32
This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791 (512) 460-5540
Andres Garcia Contracting Officer
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
A.4 STATEMENT OF WORK
A.5 INSTRUCTION TO OFFERORs
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
2.4 52.228-1 BID GUARANTEE (SEP 1996)
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
(FEB 2021)
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
2.9 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)
(DEVIATION)
2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND
VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025)
(DEVIATION FEB 2025)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—
REPRESENTATION AND DISCLOSURES (DEC 2023)
3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (NOV 2021)
GENERAL CONDITIONS
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,
AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED
ENTITIES (DEC 2023)
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (OCT 2018)
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
4.5 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JAN 2025)
4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL
LABOR RELATIONS ACT (DEC 2010)
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
4.9 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.11 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN
2020)
4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)
(DEVIATION)
4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.15 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
4.17 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.18 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..65
4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
ATTACHMENTs
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1.00
JB
The contractor shall provide all necessary work in accordance with the statement of work for Project 756-22-206 Repair Building Envelope, specifications, and drawings.
1.00
EA
Performance and
Payment Bonds
GRAND TOTAL
A.4 STATEMENT OF WORK
STATEMENT OF WORK
REPAIR BUILDING ENVELOPE
PROJECT #756-22-206
BACKGROUND: The purpose of this project is to restore and repair the building envelope and moisture protection systems infrastructure at the El Paso Veteran Affairs Health Care System (EPVAHCS) Medical Center, located at 5001 N. Piedras Street, El Paso, Texas 79930. The EPVAHCS Medical Center opened in 1995 and is a tenant organization located on the Fort Bliss Army Base in El Paso, Texas. The EPVAHCS Medical Center is a four-story building. This facility is 100% Asbestos Free Facility.
GENERAL SCOPE: The Contractor shall provide all labor, supervision, materials, equipment to restore and repair the building envelope and moisture protection systems at the EPVAHCS Medical Center. Restoration and repair of the building envelope and moisture protection systems to include but not limited to the roof, skylights, windows, brick walls, pre-cast concrete panels and any building wall and roof penetrations.
CONTRACTOR RESPONSIBILITIES: The Contractor shall exercise extreme care to avoid damaging Government property such as buildings, equipment, trees, shrubs, or turf. Any damage to Government property by the Contractor shall be repaired by the Contractor to its original condition at no additional cost to the Government. The contractor shall restore ALL disturbed grounds to existing conditions. The Contractor shall ensure that all materials are new, free from defects, imperfections and asbestos free (NO
ASBESTOS CONTAINING MATERIALS SHALL BE USED ON THIS PROJECT).
SCHEDULE OF WORK: The Contractor shall schedule work through the COR. The Contractor shall coordinate work with COR NLT 3 days before starting work. Work shall be completed with-in three hundred (300) calendar days after Notice to Proceed (NTP).
Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work.
HOURS OF WORK: The work will be performed during normal business hours in coordination with the Contracting Officer’s Representative (COR) and El Paso VA services. The El Paso VA Medical Center normal business hours are from 7:30 am to 4:30 pm Monday through Friday except Federal Holidays. If the work is potentially disruptive, work shall be performed during non-business hours which shall be from 4:30 pm to 11:30 pm Monday through Friday. If non-business hours will be required, the Contractor shall make any provisions necessary in their proposal to account for this work.
If the Contractor desires to work on weekends and/or Federal Holidays, the Contractor must submit a written request for approval to the COR at least five (5) working days prior to the proposed start of such work.
SECURITY: All employees of the General Contractor and the Subcontractors shall comply with VA security management requirements. All employees are to obtain visitor identification badges before starting work on daily basis from the VA Police Dispatch office. Contractor personnel shall always wear visitor badges in plain sight above the waist. Contractor personnel found without a badge will be immediately removed from VA property by VA Police. All Contractor personnel are restricted from unauthorized access.
WORKMANSHIP: All work under this contract shall conform to the standards of these specifications. The Contractor at no additional cost to the Government shall correct work not meeting these specifications. Work shall be accomplished by mechanics skilled in the trade.
DAILY PROGRESS REPORTS: The Contractor shall provide on a daily basis and no later than 5:00 PM, a progress report of work accomplished the previous day to COR.
Daily Progress Reports shall be typed and sent to the COR and designated Government Representatives in PDF format.
WORKING CONDITIONS: The buildings and the surrounding site areas will be occupied and Government operations will continue on a normal, temporary or restricted basis for the duration of the contract. The Contractor shall take all precautions to ensure that his operations are conducted in a manner so as not to interfere with the normal operation of surrounding facilities. The Contractor shall execute work in a safe manner and shall not subject personnel to unsafe conditions. The Contractor shall provide safety barricades, devices, and equipment to protect personnel and property and repair damage caused by construction operations. Take all precautions to protect the building and its occupants during the construction period.
SITE VISIT: Contractors are urged to attend the site visit to determine the full extent of the work. Failure to inspect the site will not constitute grounds for a claim after contract award.
DISPOSAL: Disposal of materials removed under this contract at an approved disposal site in accordance with all local, state, and federal laws, regulations, and guidelines are the Contractor’s sole responsibility. The contractor shall adhere to all OSHA requirements concerning removal, transporting, and disposal of the material. All waste and recycle receipts shall be turned into the COR, by e-mail weekly.
CLEAN-UP: The Contractor shall keep the area and surrounding areas clean and organized; as in neat, tidy, free of trash and debris daily.
TEMPORARY FACILITIES: Contractors are responsible for their own temporary facilities and utilities.
SAFETY AND FIRE: The Contractor shall comply with the most recent fire and safety rules and regulations; NFPA and OSHA Standards, for minimum safety requirements.
PERMITS: The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required Federally and by the State of Texas.
WARRANTEE: The contractor shall warrantee work to be free of defects and workmanship for a period of 1 year from date of acceptance.
STATEMENT OF WORK: The Contractor shall provide all labor, supervision, materials, equipment to restore and repair the building envelope and moisture protection systems.
Work shall be inclusive of the requirements in the specifications, drawings, statement of work, to include but not limited to:
I. Contractor shall repair and restore roof system
a. The entire roof system is approximately 144,786 square feet (SF).
b. Replace approximately 15,159 SF of non-coated roof with Garland Coated Roof system.
c. Power wash the entire roof system to identify existing conditions such as ponding, poor or no drainage, delamination, roof leaks, etc.
d. Remove and replace all sealant with new sealant.
e. Remove and install new pitch pockets / flashing at all roof penetrations.
f. Replace insulation that has lost stability and has reduced thickness.
g. Replace areas of the roof that have delaminated.
h. Eliminate all ponding.
i. Repair poor slope to drains due to overbuilt crickets.
j. Repair roof drains adjacent to columns to maintain a consistent slope / height under seasonal loads.
k. Clean roof drains and overflow drains to daylight.
l. There is approximately 53,244 SF of photovoltaic solar array panels located on three different roofs of the facility. Solar array panels will have to be removed, securely stored, cleaned, reinstalled, and commissioned to reinstate a working system, allowing the Contractor access to areas of the roof that are damaged.
m. Contractor shall provide a work plan so the work is done in phases. This work plan to be approved by and coordinated with the VA's COR.
II. Contractor shall decommission and demolish a rooftop antenna.
a. Demolition includes removal of supporting guy wires and anchor weights.
b. Repair or patch roof membrane as required after removal.
III. Contractor shall remove Annex building skylight system and install a new skylight.
IV. Contractor shall reseal perimeter of windows, doors and louver frames.
a. Replace current perimeter sealant with new sealant and backer rods.
b. All weeps shall be purged and cleaned out.
c. Contractor shall not obstruct weeps at windows sills or sill flashing.
V. Contractor shall reseal pre-cast concrete wall and brick veneer wall systems.
a. Replace current sealant with new sealant and backer rods.
b. All weeps shall be purged and cleaned out.
c. Contractor shall not obstruct weeps.
VI. Contractor shall repair leaks on foundation wall in Canteen storage room on the first floor.
a. To include replacement of waterproofing and sill flashing
VII. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
Reference Division 01 00 00 General Requirements, Section 1.14 of Specifications document for additional information.
QUALITY ASSURANCE: The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of theses specifications.
SUBMITTALS: Contractor shall provide with their quote manufacturer’s descriptive literature for items mentioned in STATEMENT OF WORK with Data Sheets and/or Shop Drawings.
1. RECORDS MANAGEMENT:
I. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C.
chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy
Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
II. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
III. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
IV. El Paso Veteran Affairs Health Care System (EPVAHCS) and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of EPVAHCS or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701.
In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to EPVAHCS. The agency must report promptly to NARA in accordance with 36 CFR 1230.
V. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to EPVAHCS control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
VI. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and EPVAHCS guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
VII. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with EPVAHCS policy.
VIII. The Contractor shall not create or maintain any records containing any non-public EPVAHCS information that are not specifically tied to or authorized by the contract.
IX. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
X. The EPVAHCS owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S.
Government for which EPVAHCS shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
XI. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #10176, Privacy and Information Security, Rules of Behavior. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
END OF STATEMENT OF WORK
A.5 INSTRUCTION TO OFFERORs
INSTRUCTIONS
Offerors shall follow the instructions contained herein. These instructions prescribe the proposal format and describe the approach for development and presentation of the proposal. These instructions are designed to ensure the submission of necessary information. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications. The Contracting Officer has determined there is a high probability of adequate competition in this acquisition.
Interested offerors shall be solely responsible for all costs associated with this solicitation including but not limited to the preparation of proposals.
The Government plans to make an award without discussions. Therefore, each initial offer shall contain the offeror’s best terms from a price standpoint. The Government reserves the right to conduct discussions if it is determined to be necessary.
Proposal shall be (1) submitted on the forms furnished by the Government or on copies of those forms; and (2) Signed. The person signing the proposal shall initial each erasure or change appearing on any proposal form. Alternate proposals will NOT be considered. Faxed submissions will not be accepted.
PROPOSAL SUBMISSION REQUIREMENTS
1. The Offeror’s proposal shall be submitted electronically via email to andres.garcia1@va.gov by the date and time indicated in the solicitation/solicitation amendments. It is the sole responsibility of the offerors to ensure the Government receives the proposals before or on the exact date and time set forth in this solicitation.
2. PROPOSAL FILES. Offeror’s responses shall be submitted in accordance with the following:
a. Format. The submission shall be clearly indexed and logically assembled. Each volume’s cover page shall include company name, date, and solicitation number only. Any other information included on the cover page will not be evaluated. All pages of Volume I/II shall be appropriately numbered and identified by the complete company name, unique entity identifier (UEI), date and solicitation number in the header and/or footer. The Table below indicates the maximum page count for each volume of the Offeror’s proposal. All proprietary information shall be clearly and properly marked. If the Offeror submits annexes, documentation, attachments or the like, not specifically required by this solicitation, such will count against the
Offeror’s page limitations unless otherwise indicated in the specific Volume instructions below. Pages in violation of these instructions, by exceeding the total page limit for a particular volume, will not be evaluated. The page count will be determined by counting the pages in the order they are assembled by the offeror, minus the cover page.
b. Offeror may only submit one (1) email for their proposal submission.
Email size limitation is 15MB. Volumes I thru III shall be included in the one single email permitted. Each Volume shall be a single attachment. Your firm’s email shall only include two attachments and titled as such:
I. Technical Acceptability-Vol. I
II. Past Performance-Vol. II
III. Price-Vol. III
IV. Solicitation, Offer, & Award Documents-Vol. IV
c. Content Requirements. All information shall be confined to the appropriate file. The Offeror shall confine submissions to essential matters, sufficient to define the proposal and provide an adequate basis for evaluation.
Offerors are responsible for including sufficient details, in a concise manner, to permit a complete and accurate evaluation of each proposal. The page limits for each volume are shown in the table below:
Volume Number
Factor File Name Page Limitations
Volume I Technical Acceptability Tech.pdf N/A
Volume II Past Performance Past Perf.pdf 20 pages
Volume III Price Evaluation Price.pdf N/A
Volume IV Solicitation, Amendments, Offer, Award Documents, Certifications and Representations
Solicitation #.pdf N/A
BASIS FOR CONTRACT AWARD:
3. Evaluation: The Source Selection process will be completed as a past performance, price tradeoff (PPTO), where there is a tradeoff between past performance and price factors and will allow the Government to accept other than the lowest priced proposal. Past performance is significantly more important than price. The highest past performance lowest price rated offerors will determine the best value basis for contract awards.
The past performance price trade-off approach will best achieve the objective of awarding contracts to Offeror for Project 756-22-206 Repair Building Envelope, with expertise and qualities that are most important to VISN 17. The Government will make an award to the contractor that obtains a substantial confidence rating for the past performance factor. The Government reserves the right to award to contractor who is rated substantial confidence, followed by a satisfactory confidence if deemed necessary.
The Government will strictly enforce all the proposal submission requirements outlined in the solicitation. Failure to comply with these requirements will result in an Offeror's proposal being rejected as being incomplete or non-conforming to solicitation requirements.
3.1 Factors and Sub-Factors Order of Importance: The Source Selection process will be completed as a PPTO, where there is a tradeoff between past performance and price factors and will allow the Government to accept other than the lowest priced proposal. Past performance is significantly more important than price. The highest past performance lowest price rated offeror will determine the best value basis for contract awards.
A. Factor 1: TECHNICAL ACCEPTABILITY (Acceptable/Unacceptable).
Sub Factor 1- (Acceptable/Unacceptable) – Verification at https://dsbs.sba.gov/ as a SDVOSB under NAICS Code: 236220 - Commercial and Institutional Building Construction which has a $45 Million small business size standard.
Sub Factor 2 - (Acceptable/Unacceptable) – Bonding Capacity – Minimum $2M.
The offeror shall ensure all bonding comes from the Bureau of the Fiscal Service (BFS), Surety Bonds, List of Certified Companies found at https://www.fiscal.treasury.gov/surety-bonds/list-certified-companies.html.
In addition, at time of award offeror shall provide performance and payment bonds IAW FAR 28.102-1(a) for the proposed amount of the project.
B. Factor 2: PAST PERFORMANCE.
Past Performance Evaluation. The Past Performance evaluation will assess the relative risks associated with an Offeror's likelihood of success in fulfilling the solicitation's requirements as indicated by that Offeror's record of past performance. In this context, "Offeror" refers to the proposed prime contractor. A joint venture will be assessed on the combined performance of each or as a team of the joint venture offerors.
1. Recent Successful Past Performance: Offerors are required to demonstrate recent successful performance under contracts that demonstrate that they have successfully performed to Repair Building Envelope as a prime contractor within the last three (3) years (calculated from the solicitation issue date).
a. Provide a detailed summary of the most recent three (3) projects valued between $2 Million to $5 Million.:
b. Owner Government Agency/Company which awarded contract.
c. Location (physical address)
d. Project Name
e. Project Description (Details of equipment site preparation requirements, challenges, and solutions)
f. Project Cost and Cost Control Measures (original and final contract costs, contract mods, cost containment measures, value engineering, etc.)
g. Project Performance Period (Initial/Actual, schedule impacts and efficiencies)
h. Owner POC (Name, Title, Telephone Number, Email)
i. Subcontractors (Rolls, Responsibilities, Percent of work)
In addition, for each project submitted, Offeror’s shall provide a narrative that describes recent successful performance and demonstrates experience working in remodeling/renovating and construction of space. Information should include details on complexity, magnitude, challenges, and degree of success. Offerors are encouraged to include supporting documents such as photographs that support the narrative.
The first aspect is to evaluate the offeror’s past performance to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. The criteria to establish what is recent and relevant must be unique to each source selection and must be stated in the solicitation. In establishing what is relevant for the acquisition, consideration should be given to those aspects of an offeror’s contract history that would give the greatest ability to measure whether the offeror will satisfy the current procurement. Common aspects of relevancy include similarity of service/support, complexity, dollar value, contract type, hospital environment and degree of subcontract/teaming.
There are four levels of relevancy as shown in the following table. When source selections require a greater level of discrimination within the past performance evaluation, the Source Selection Evaluation Board (SSEB) Members must use all four of the relevancy ratings identified below. However, for those source selections requiring less discrimination in the past performance evaluation, the board members may use, as a minimum, “Relevant” and “Not Relevant” past performance ratings. The Source Selection Plan (SSP) must clearly identify the treatment of relevancy within the past performance evaluation. With respect to relevancy, more relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
Past Performance Relevancy Ratings Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
An example would be a project involving repair of the Building Envelope valued at $2M or greater, at a VA healthcare system.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
An example would be a project involving repair of the building envelope valued at $2M or greater, at any health care system.
Somewhat Relevant
Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires
An example would be a renovation construction project valued at $2M or greater in a healthcare system (internal/external)
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
An example would be a renovation construction project less than $2M in a non-healthcare system.
The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts.
Sources of Past Performance Information for Evaluation are as follows:
1. Past performance information can be obtained from any source available to the Government, to include, but not limited to, the Contractor Performance Assessment
Reporting System (CPARS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases, interviews with Program Managers, and Contracting Officers,
2. Past performance information may be provided by the offeror, as solicited.
3. Past performance information may be obtained from questionnaires tailored to the circumstances of the acquisition.
The Past Performance Evaluation Team will review this past performance information and determine the quality and usefulness as it applies to performance confidence assessment.
Performance Confidence Assessments
Rating Description
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
C. Factor 3: PRICE EVALUATION APPROACH
Fixed Price: The Government will evaluate offers by adding the total of all line-item prices. The Total Evaluated Price will be that sum. The Government will evaluate price to determine fair and reasonableness.
Solicitation, Amendments, Offer, Award Documents, Certifications and Representations:
1. Standard Form (SF) 1442 Solicitation, Offer, and Award:
All blocks under section "OFFER" on page 2 of SF1442 (Item 14 thru 20C) shall be completed. Offerors shall be solely responsible for monitoring the Government’s website SAM.gov for amendments to this solicitation, if any, and acknowledge them in accordance with the requirements stipulated in this solicitation and amendments.
2. Duly executed Bid Bond/Guarantee:
Offerors shall use form SF24 Bid Bond. Bid bonds that are found noncompliant with bid guarantee requirements may result in the rejection of the offer. See clause 52.228-1 Bid Guarantee for additional information on the compliance with bid guarantee requirements.
3. SDVOSB Certification:
To be eligible for award, Offerors are required to be SDVOSB certified. Offerors must register their businesses at https://search.certifications.sba.gov/advanced?page=0 and https://www.sam.gov and complete the Reps and Certs.
4. Acknowledgement of All Amendments:
The Offeror must acknowledge and agree to all amendments by either 1.)
completing block 19 of the SF 1442, or 2.) returning the signed amendment form(s) with the submission.
5. Representations & Certifications:
Clause 52.219-28 must be completed, dated, and signed. As the provision at FAR 52.204-7 is included in the solicitation, FAR 52.204-8(d) applies and the fill-in for FAR 52.204-8(b)(2) does not need to be completed. The Offeror is required to complete the annual representations and certifications electronically at https://sam.gov/. SAM registration must be active from the time the proposal is submitted through the time of award.
6. Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment:
The Offeror must provide their response to FAR 52.204-24(d) Representation, unless the requirements in the first paragraph of this provision have been met.
7. Information Regarding Responsibility Matters:
The Offeror must provide their response to FAR 52.209-7(b).
8. Violation of Arms Control Treaties or Agreements:
The Offeror must provide their response to FAR 52.209-13(b) Certification.
9. Tax on Certain Foreign Procurements—Notice and Representation: The Offeror must provide their response to FAR 52.229-11(d).
10. Limitations on Subcontracting:
The Offeror must complete and sign the VAAR 852.219-75 VA NOTICE OF
LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR
SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) included in this solicitation and return it with their submission. Offerors must also complete the attached Self-Performed Work Calculations and submit this form with its proposal.
The completed and signed forms will become part of the official award documentation.
11. Notice to SB Joint Venture/Mentor Protegee:
Any Offeror submitting a proposal as a joint venture must provide a certification from each SDVOSB joint partner, signed by an authorized official of each partner to the joint venture, stating that the parties to the joint venture (1) have entered into a joint venture agreement that fully complies with paragraph (c) of 13 CFR §
128.402 and (2) will perform the contract in compliance with the joint venture agreement. Failure to submit the certification with the Offeror’s proposal will render the Offeror ineligible for award.
It is solely the responsibility of the Offerors to ensure the Government receives the proposal before or on the exact due date and time set forth in this solicitation.
Offerors shall provide the Contracting Officer confirmation of the bid bond delivery via email to andres.garcia1@va.gov prior to the closing date/time.
12. VETS-4212:
Title 38, USC Section 4212(d) and Public Law 105-339, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. This VETS-4212 report can be submitted per the instructions at https://www.dol.gov/agencies/vets/programs/vets4212. For assistance contact VETS-4212 customer support at 1-866-237-0275 or VETS-4212 customersupport@dolncc.dol.gov. For procurement awards in excess of $150,000, this report must be completed and accepted prior to any Federal contract award.
Therefore, all potential contractors are encouraged to file every year. All inquiries about this solicitation shall be directly submitted in writing via email. No phone or faxed inquiry will be accepted. Deadline for all inquiries for this solicitation is listed on the SF1442. Government’s responses to inquiries will be issued in the form of Amendment(s) to be posted on the same website where this solicitation is posted:
www.SAM.gov. All interested offerors including those submitting inquiries are required to monitor the above website for any posted amendments and acknowledge them in accordance with the instructions provided in the amendments as well as in this solicitation.
All inquiries about this solicitation shall be directly submitted in writing via email to the andres.garcia1@va.gov. No phone or faxed inquiries will be accepted.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY
SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225- 9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID
GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an…
This is the start of the file's text. The full file is on GovTribe.