This document is an amendment to a Request for Quote (RFQ) for furniture installation, storage, and moving services for the Department of Veterans Affairs (VA) in El Paso, Texas.

The key details are:

  • This is a new requirement with no incumbent contractor.
  • The RFQ covers storage, moving, and installation of furniture across multiple VA facilities in El Paso, with an estimated 38,400 square feet of furniture to be relocated.
  • The contract includes a base year and four option years.
  • Pricing is requested on a monthly basis for storage space, moving/installation, and inventory management.
  • A not-to-exceed line item is included for travel associated with work at the Las Cruces, NM location.
  • Responses to 12 clarifying questions are provided, addressing topics such as furniture inventory, phasing plans, certifications, network cabling, and site visits.

View the file

Other files

File Type Posted
36C25724Q0976 0002_1.docx DOCX document
S06 36C25724Q0976 0001.pdf PDF
36C25724Q0976 0001_1.docx DOCX document
36C25724Q0976_1.docx DOCX document
S02 36C25724Q0976.pdf PDF
P07 WD 2015-5229 rv 24 dated 7-22-2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 7

09-30-2024

756-25-1-6959-0001

36C257

Department Of Veterans Affairs Network Contracting Office 17

5441 Babcock Road Ste. 302 San Antonio TX 78240

36C257

Department Of Veterans Affairs Network Contracting Office 17

5441 Babcock Road Ste. 302 San Antonio TX 78240

To all Offerors/Bidders

36C25724Q0976

08-29-2024

X

X X

See CONTINUATION Page

X 1

The purpose of this amendment is to provide questions received and their answers and revised Price/Cost Schedule.

No other questions will be entertained. No other information is changed.

36C25724Q0976 Amend 0002

CONTINUATION PAGE

A.1 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

12.00 MO __________________ __________________

Storage Space: 2,500 square feet.

Contract Period: Base POP Begin: 12-31-2024 POP End: 12-30-2025

Moving and Installation on approximately 38,400 square feet.

Note to Exceed Line Item. Quantities are estimated and may decrease depending on actual amounts of furniture moved and installed. Contractor should invoice and will only be paid for amounts actually relocated and installed.

Contract Period: Base

Inventory for 2,500 square feet.

Contract Period: Base

1.00 YR

TBD by Government Travel associated with work at Las Cruces only.

This is a Not-to-Exceed LIN, amount not guaranteed and will fluctuate based on actual need.

Contract Period: Base

Contract Period: Option 1 POP Begin: 12-31-2025 POP End: 12-30-2026

Note to Exceed Line Item. Quantities are estimated and may decrease depending on actual amounts of furniture moved and installed. Contractor should invoice and will only be paid for amounts actually relocated and installed.

Contract Period: Option 1

Contract Period: Option 1

Contract Period: Option 1

Contract Period: Option 2 POP Begin: 12-31-2026 POP End: 12-30-2027

Note to Exceed Line Item. Quantities are estimated and may decrease depending on actual amounts of furniture moved and installed. Contractor should invoice and will only be paid for amounts actually relocated and installed.

Contract Period: Option 2

Contract Period: Option 2

Contract Period: Option 2

Contract Period: Option 3 POP Begin: 12-31-2027 POP End: 12-30-2028

Note to Exceed Line Item. Quantities are estimated and may decrease depending on actual amounts of furniture moved and installed. Contractor should invoice and will only be paid for amounts actually relocated and installed.

Contract Period: Option 3

Contract Period: Option 3

Contract Period: Option 3

Contract Period: Option 4 POP Begin: 12-31-2028 POP End: 12-30-2029

Note to Exceed Line Item. Quantities are estimated and may decrease depending on actual amounts of furniture moved and installed. Contractor should invoice and will only be paid for amounts actually relocated and installed.

Contract Period: Option 4

Contract Period: Option 4

Contract Period: Option 4

GRAND TOTAL __________________

RFQ 36C25724Q0976- ELP Furniture Install, Storage & Moving

Amendment #0002 Questions and Answers

Q1: Is there an Incumbent in place? If so, kindly provide the contract award number, awardee name, and award amount of the contract.

A1: This is a new requirement, so there is no incumbent.

Q2: Do we have a complete list of Furniture that needs to be removed from these facilities? Exact quantities and types of furniture broken down to identify which facility they are currently occupying would be very helpful in our Quotation Process.

A2: We do not have a list. Types and quantities of furniture will vary.

Q3: Do we have a Phasing plan?

A3: There is no phasing plan. Work will be coordinated and scheduled ahead of time as needed.

Q4: Do we have drawings outlining all facilities associated with this project that include current furniture layouts and ingress/egress points.

A4: We have floorplans for all of our facilities. We do not have furniture layouts for all our facilities.

These will be made available to the selected vendor as individual requirements arise.

Q5: it is exceedingly rare to find a contractor who holds certifications from four of the manufacturers listed in the solicitation. This is primarily due to the competition clauses that many manufacturers attach to their certification processes. With this in mind, I wanted to seek clarification: If a subcontractor possesses certification from one of the major manufacturers specified and has substantial industry experience in assembling and disassembling equipment from the other listed manufacturers, would that be deemed sufficient to fulfill the certification requirements for this solicitation?

A5: Certification from other vendors is acceptable. Certification from the four Manufactures listed is preferred. If subcontractors do not have certification from the four listed vendors a minimum of 5 years of experience is required. Subcontractors and subcontractor staff may be required to be replaced based on acceptable performance.

Q6: Other than the office furniture items listed in the Statement of Work, what are examples of other equipment that may be included in the VA El Paso’s work orders?

A6: This requirement will be used for all types of administrative type furniture and equipment. This requirement will not be used for medical equipment.

Q7: In the Statement of Work, Page 1 Section 2, “The Contractor shall furnish labor, tools, equipment and trucks to provide and execute the pickup of complex furniture systems, moving of complex furniture systems, freestanding furniture, and the computer data management of these complex systems and furniture.” Is “computer data management” referring to space plans, as-built and installation drawings?

A7: No. “computer data management” is referring to tracking and inventory.

Q8: Will the VA allow the vendor to include a drive time charge for the Las Cruces locations?

A8: Most work will be in El Paso; however, a Not-to-Exceed Line Item has been added for travel associated with Las Cruces only. This LIN’s amount is not guaranteed and will fluctuate based on actual need.

Q9: In the Statement of Work, Page 3 Section 4. A, “bond” is mentioned. Office furniture management services do not require bonding. Will you please clarify this?

A9: “Bond” removed from SOW and will be incorporated into the contract when awarded.

Q10: In the Statement of Work, Page 3 Section 4. B & Section 5. A. “receiving” is mentioned. There is no Item Information in the Price/Cost Schedule for “receiving new furniture.” How should this service be costed in the pricing schedule?

A10: This should be accounted for in LIN 3, Inventory.

Q11: How will the VA El Paso manage the network cabling required for systems furniture installations?

What will your process be? Is this done in-house at the VA El Paso or is it outsourced to a contractor? Is there one contractor or multiple contractors for this service?

A11: The El Paso VA holds a Data Cabling service contract that is used to address network cabling requirements.

Q12: Would there be an opportunity to conduct site visits?

A12: A site visit would not be beneficial at this time. The work will depend on the specific requirements as they arise, we do not know what those requirements are yet.