Tech Questions for RFQ 36C25724Q0707 CTX Cooling Tower Crane.docx
DOCX document 20 KB Posted
- Attached to
- N041--Amendment to extend Offer Due Date | Post Technical Question Answers | Post Site Visit Sign In Sheet
- Solicitation number
- 36C25724Q0707
About this file
This document contains technical questions and answers related to RFQ 36C25724Q0707 for the CTX Cooling Tower Crane project. The key details are:
The RFQ is for the replacement of a cooling tower gearbox at a facility. The incumbent gearbox model is Amarillo M22 with a serial number of M1647. The new gearbox weighs 426 pounds and has dimensions of 24" x 30" x 31", with an additional 100-pound fan that is 10' wide and 1' high. The building height, including the brick parapet wall, is 99' 8.25".
The MEP contractor estimates 4 hours to hook up and disconnect the gearbox. The delivery date for the new gearbox is currently unknown. The only known underground utility is a 4" sanitary line. Site visits are not mandatory for bidding but are recommended to verify measurements and site conditions. The solicitation allows electronic submissions, and the VA is responsible for disconnecting the existing equipment. The new gearbox is to be installed immediately after the existing unit is removed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tech Questions for RFQ 36C25724Q0707 CTX Cooling Tower Crane.docx | DOCX document | |
| S04 Site Visit Sign In Cooling Tower Crane.pdf | ||
| 36C25724Q0707 0001_1.docx | DOCX document | |
| 36C25724Q0707 0001.docx | DOCX document | |
| 36C25724Q0707_1.docx | DOCX document | |
| P07 SAM WD 2015-5237 Rev. 24 04.19.2024.pdf | ||
| 36C25724Q0707 - Cooling Tower Crane.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Questions/Answers 36C25724Q0707 CTX Cooling Tower Crane
1. Please confirm in Writing the height of the building including the Brick Parapet wall that we must lift the gear box up and over too.
The prints indicate 99 feet 8 1/4 inches.
2. Please confirm in Writing the exact weight and dimensions of the gear box we are going to be lifting.
Gearbox: Packing Slip states that it weighs 426 pounds. Width 24inches, length 30 inches, height 31 inches.
Installed with fan attached. Fan: Weight approximately 100 pounds. Width 10 feet, height 1 foot.
3. How long does the MEP contractor anticipate that it will take to hook up the gear box, and be able to disconnect from the crane? If their estimate of time takes longer, will the Prime contractor be able to submit an equitable adjustment?
The estimated time is four hours.
4. Please confirm in writing the delivery date for the gear box. If a precise date is currently unknown, please confirm the MEP contractors estimated delivery date.
Currently unknown.
5. Please confirm in writing the exact locations of any known underground utilities.
The only known utility is a 4 inch sanitary line that runs across the area where the crane will sit.
6. In the scope of work, you mentioned that "A pre site visit will be coordinated for contractors bidding and all must be present to verify measurements and investigate site conditions prior to submitting proposal.", is that means that the site visit is mandatory? if so, are we still have the ability to bid without attending the site visit?
They can still bid if they did not attend.
7. Provide us with more information about the cooling tower gearbox brand name, model and serial number.
Amarillo Model: M22 Serial number: M1647
8. Will electronic submissions be allowed? if not, what physical address will the submission be sent too.
9. Provide specifications of existing and new equipment to be removed and installed?
Amarillo Model: M22 Serial number: M1647 is the new unit and is an exact replacement. The existing unit has fan blade removed. New unit will be lifted with fan blade installed.
10. Who is responsible for disconnecting existing equipment?
The VA has responsibility for disconnecting existing equipment.
11. What is the time frame between demo of existing and installation of new equipment ?
Once existing is removed the new unit is to be immediately installed.
12. Where is the location of demoed equipment once removed?
Demoed equipment to be place on a pallet at ground level.
13. Is this work to be completed during normal business hours ? Weekends?
Saturdays and normal business hours.