36C25724Q0467 0003.pdf
PDF 1 MB Posted
- Attached to
- N041--Amendment to attached Revised SOW and Technical Questions Answers and attach Floor Plans NEW: Directors Conference Room A/C replacement Federal contract opportunity
- Solicitation number
- 36C25724Q0467
About this file
This document is an amendment to a solicitation for the replacement of the HVAC system serving the Directors Conference Room at the Dallas VA facility. The amendment includes a revised Scope of Work and the answers to technical questions submitted by potential offerors, along with associated floor plans and equipment photos.
The key details are:
- Solicitation Number: 36C25724Q0467
- Seeking a new 10-ton HVAC system to replace the existing system, including new refrigerant lines, electrical work, and ceiling modifications
- Answers to 39 technical questions regarding equipment specifications, installation requirements, scheduling, and other logistics
- Photos of the existing indoor air handling unit and outdoor condensing units
- Floor plans showing the location of the HVAC equipment
- Work to be performed Monday-Friday, 7am-5pm
- No city permit required for federal property
- Contractor responsible for ceiling grid/tile removal and reinstallation
- VA will provide alternate cooling during installation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| P09 SOW Replace HVAC System.docx | DOCX document | |
| 36C25724Q0467 0003_2.docx | DOCX document | |
| bldg 2 1st floor executive area.pdf | ||
| 2-H5 First Floor Plan Unit A.pdf | ||
| 2-P6 First Floor Plan Unit B.pdf | ||
| 2-P5 First Floor Unit A.pdf | ||
| 36C25724Q0467 0003_1.docx | DOCX document | |
| 36C25724Q0467 0002_1.docx | DOCX document | |
| 36C25724Q0467 0001_1.docx | DOCX document | |
| 36C25724Q0467 Directors Conference Room AC replacement.docx | DOCX document | |
| 36C25724Q0467_1.docx | DOCX document | |
| SAM WD 2015-5227 Rv 21 122623.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
549-24-2-088-0108
36C257
Department Of Veterans Affairs Network Contracting Office 17
5441 Babcock Road Ste. 302 San Antonio TX 78240
36C257
Department Of Veterans Affairs Network Contracting Office 17
5441 Babcock Road Ste. 302 San Antonio TX 78240
To all Offerors/Bidders
36C25724Q0467
04-24-2024
X
The Purpose of this amendment is to post a revised Scope of Work and the answers to all submitted technical questions with pictures and attached floor plans.
a. Questions and Answers and Floor Plans are attached.
b. Revised Scope of Work attached (See highlighted addition).
c. All other terms and conditions remain the same.
This amendment is to post a revised Scope of Work and the answers to all submitted technical questions with pictures and attached floor plans.
CONTINUATION PAGE
See attached document: P09 SOW Replace HVAC System.
Technical Questions and Answers
1. Could a picture of the data plate of the air handler (Unit located indoor) be provided?
Photos of AHU and condenser attached.
2. We noticed that there isn't a CLIN number to price out the installation cost. I think line item #0005 was supposed to be for the installation cost, not the Administration Fee. Is this the case? In the RFQ under B.2 Scope of Work, it calls for a separate line item pricing the installation.
Contracting Officer Answer
3. What voltage the unit needs to be 208-230V or 460V single or 3 phase.
3 phase/460 volts
4. The location of the existing condenser system (for example northeast side of the building front back of the building or on the roof).
The condenser is located on the roof above the back dock of BLDG 2. It is currently in 2 pieces. One 10 ton and a separate 5 ton that was installed as a temporary repair within the last 2 last years. There is a wall mounted ladder and scuttle hole on the back dock to access the roof.
5. Is there a staging area for debris removal or an area for a small bin?
There is an open top dumpster below the worksite at the dock of BLDG 2. This may be utilized for debris. If the contractor wishes to leave the old units, the VA has a source that can scrap the old units out at no cost.
6. 10 Ton Air Handler with a 24.92KW Heater: Air handlers in commercial settings often operate on 208/230V or 460V, three-phase power, especially when paired with large electric heaters like the 24.92KW unit mentioned. The voltage requirement can depend on the specific model and manufacturer. It is not disclosed in the equipment specs which Voltage the requested system runs on, could you please advise?
The air handling unit and condenser are 3 phase/ 460 volts. The current air handler has a hot water heating coil. We would like to go back with that and stay away from electric heat. I’m not sure the available power would support electric heat.
7. What prompts the VA to replace the copper line outside the building?
The lines are original to the equipment(20 years) Multiple leaks have been repaired as well as different refrigerants used in these units. A new line set will help ensure the longevity of this new equipment. A separate 5-ton condenser was set within the last 2 years when we lost a compressor due to possible burnout. Lines were flushed, but contamination could still be present.
8. Why does the VA wish to remove all electrical conduits beneath the existing equipment?
Technical Questions/Answers 36C25724Q0467 Dallas VA Directors Conference Room A/C
It is not required, but we believe it will be necessary to remove the old unit and set the new. The VA electricians will need to identify those circuits that are needing to be shut down and help mitigate and disruptions during the swap out.
9. What is the reason for the VA's decision to remove the ceiling grid?
The air handling unit is located above the drop ceiling and removal is necessary to facilitate removal of the old unit and installation of the new unit.
10. The old system is not a Heat Pump System, you are requesting the new system to be a heat pump, correct?
The old system is a 10-ton DX cooling unit with two stages of cooling(5 each). The heating on the old unit is hot water. The heating water is provided through building heat exchangers and is piped to the unit above the ceiling. The heating valve on the circuit is controlled by building automation and does not need to be replaced.
11. Access point to the interior unit is very limited. In the event that the unit doesn't fit through the only access, would it be ok if we can remove the door along with any additional demo and rebuild?
Contracting Officer Question I can confirm that there is 35” of clearance at the door and the current air handler installed is 28” at its widest point.
12. Do you want us to include the removal of the ceiling grids, lights fixtures and assemble them back in our bid ?
Yes
13. On the rooftop there were 2 condenser units instead of one that was mentioned. Do you want us to replace both ?
Only one- 10 ton condenser to be installed.
14. Will we keep the same duct components and just attach them to the new units?
Yes. The contractor will only be responsible for adapting the new unit to the existing room duct system.
15. 5. Is there any brand preference to be used ?
As long as the unit meets the same requirements as the unit being replaced, the brand is up to the contractor.
16. What are the ICRA requirements? ICRA LEVEL 1 AND 2
1. Perform work activity in a manner that does not create dust.
2. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
3. Any materials and equipment being brought into the facility must be free of contaminants and loose material.
4. Provide active means to control airborne dust from dispersing into occupied areas and/or water mist surface to control dust (e.g., Mobile Dust Containment Cart or some other system).
5. Ensure worker clothing is clean and free of visible dust before leaving the work area.
6. Remove or isolate air diffusers (supply and return) to protect the HVAC system from dust and reduce air turbulence. Rebalance system to address diffuser isolation.
7. When the work involves or impacts potable water systems including stagnation due to reduced usage, the piping shall be flushed twice a week or isolated from the main system.
8. Seal doors to prevent dust migration.
9. Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.
10. Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and debris prior to removal from the area.
11. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
12. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
13. Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces at least daily.
17. Will contents in the room be removed by the VA prior to the contractor beginning work?
The room is small, but not completely full of things. The VA will relocate anything inside the room that is movable and the contractor deem in the way.
18. Will the VA remove and replace the ceiling grid and tile or will this be the contractor's responsibility?
The Contractor will remove and reinstall the ceiling grid and tiles for installation.
19. There is some electrical obstructing the installation. Will the VA or contractor be responsible for moving the obstruction?
See question 8. The contractor will be responsible for removing and reinstalling these circuits for installation of the unit. The VA electrical Shop will identify the circuits and assist with mitigating power outages during the installation.
20. Are any of the wires to the server rack running in any of the conduit under the unit?
No. There are 5 electrical conduits that run under the current unit. One feeds power to the air handler. Two 1-1/4” conduits provide power from a lighting controller to the Conference Room. Two ½” conduits provides control from the room to the lighting controller.
There is also a live sprinkler line under the unit with a sprinkler head terminating in the ceiling under the air handling unit. (Fire Control or Plumbers would have to address this.)
21. The SOW states work can be conducted Monday through Friday, 7:00 am to 5:00 pm.
Can you confirm these hours are still acceptable?
Yes.
22. Would you be extending this solicitation for a couple more days up?
No.
23. Will there be changes to the SOW to combine the other other HVAC?
NO
24. Work hours and accessibility.
Please see question 21
25. Will we be responsible for alternate A/C for the staff while we will be installing the new replacement The VA will be responsible for providing alternate cooling during the installation.
26. Will vendor we allow to pull city permit?
Contracting Officer Question I do not believe a city building permit is required on federal property, but this should be verified.
27. Can we get a copy of the layout of the ceiling plans?
added
28. Please Provide make and model numbers of the existing equipment to be replaced.
American Standard Inc. Trane Co. model No. TTA120B400EA (pictures of the AHU and Condenser data plates are attached)
29. What are the anticipated hours of the day work can be performed?
See Question 21
30. Will the contractor be responsible for removing all electrical conduit serving other areas or devises interfering with the removal and installation of the HVAC equipment being replaced in this SOW?
contractor will be responsible for all electrical to the AC unit. VA electricians will reroute power not related to the current unit.
31. What does the existing conduit routed under the AHU serve?
Other systems in the area. I believe the conduits are for lighting and associated controls for the conference room.
32. Will the existing conduit under the AHU need to be rerouted to another permanent location.
Please provide desired routing.
VA personnel will identify and reroute unrelated power
33. Will the contractor be responsible for the removal and reinstallation of the existing ceiling system?
yes
34. If a new ceiling is to be provided, will it need to be painted same as the existing?
Replacement ceiling should match existing
35. Will new ceiling need to be provided or will the existing be reinstalled?
Contractor may use existing materials if possible.
36. Will the entire supply and return air ducting be replaced?
The Contractor will be responsible for adapting the new unit to the existing supply and return ducts. The existing ductwork does not need to be replaced.
37. Please provide contact information for the Siemens controls representative.
Our current contract representative is
Jason Griffin
Siemens Industry, Inc jason.griffin@siemens.com
Service Line 972-751-5225
The VA A/C Shop does employ a Controls Mechanic that can assist with the control wiring of the new unit to the existing Building Automation System.
38. Is the existing refrigerant piping to be replaced with new piping?
A new 2 circuit line set should be included in the replacement.
39. How many condensing units make up this system?
There is one 10-ton condensing unit to this air handler. A separate condenser was installed about 2 years ago when the original unit lost a compressor. The Contractor will be responsible for removing both units associated with this install, but only replace the 10- ton condenser.
Pictures - included
Dir Conf Condenser #1 Dir Conf Condenser #2
Dir Conf Indoor #1 Dir Conf Indoor #2 mailto:jason.griffin@siemens.com
Dir Conf Condenser #1
Dir Conf Condenser #2
Dir Conf Indoor #1
Dir Conf Indoor #2
Floor Plans – are found in attachments.
See attached document: 2-P5 First Floor Unit A.
See attached document: 2-P6 First Floor Plan Unit B.
See attached document: 2-H5 First Floor Plan Unit A.
See attached document: bldg 2 1st floor executive area.
This amendment is to post a revised Scope of Work and the answers to all submitted technical questions with pictures and attached floor plans.