This federal contract opportunity solicitation seeks bids to repair water infiltration at the Bonham Domiciliary in Veterans Integrated Service Network 17. The solicitation number is 36C25724B0003 and is being issued by the Department of Veterans Affairs Veterans Health Administration to address water infiltration issues impacting the facility. Bids are due by the date listed on the Federal Business Opportunities website and the contract award date will also be posted upon selection of a vendor. The opportunity is for remediation services to resolve water infiltration penetrating the building envelope that is causing damage.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 549A-21-921 Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building #171 Temple TX 76504 Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 To all Offerors/Bidders
36C25724B0003
X X
X The purpose of this amendment is to provide multiple documents and photos because of RFIs received.
The bidder shall acknowledge this Amendment 0001 to the solicitation as stated in 13.E. above.
The bid due date and time remains unchanged.
STATEMENT OF WORK
BUILDING 24 WATER INFILTRATION
PROJECT #: 549A4-21-921
October 20, 2023
1. SCOPE: This project provides primarily correct issues with improper drainage, rain runoff, and undermining that building 24 is currently experiencing. The location of Building 24 is at the Sam Rayburn Memorial Veterans Center, 1201 E. 9th St., Bonham, Texas, 75418.
2. CONTRACTOR RESPONSIBILITIES: The Contractor shall exercise extreme care to avoid damaging Government property such as buildings, equipment, trees, shrubs, or turf. Any damage to Government property by the Contractor shall be repaired by the Contractor to its original condition at no additional cost to the Government. The contractor shall restore ALL disturbed grounds to existing conditions. The Contractor shall ensure that all materials are new, free from defects, imperfections and asbestos free (NO ASBESTOS CONTAINING MATERIALS SHALL BE USED ON THIS PROJECT).
3. SCHEDULE OF WORK: The Contractor shall notify the Contracting Officer’s Representative (COR) Mr. Felix SanMiguel, Engineering Building 9, phone: 903 583 6494, prior to start of work. The Contractor shall schedule work through the COR. The Contractor shall coordinate work with COR NLT 7 days before starting work. Work shall be completed with-in 365 days of NTP. Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work.
4. HOURS OF WORK: The normal hours of work are 07:30 to 16:15 (4:15) Monday through Friday. Work shall be performed during normal work hours. Work to be performed in other than normal hours shall be approved by the Contracting Officer’s Representative.
5. WORKMANSHIP: All work under this contract shall conform to the standards of these specifications and in accordance with the TIL. The Contractor at no additional cost to the Government shall correct work not meeting these specifications. Work shall be accomplished by mechanics skilled in the trade.
6. DAILY PROGRESS REPORTS: The Contractor shall provide daily reports and no later than 9:00 AM, a progress report of work accomplished the previous day to COR Felix SanMiguel, located in Bldg. 9.
7. WORKING CONDITIONS: The buildings and the surrounding site areas will be occupied, and Government operations will continue a normal, temporary, or restricted basis for the duration of the contract. The Contractor shall take all precautions to ensure that his operations are conducted in a manner so as not to interfere with the normal operation of surrounding facilities. The Contractor shall execute work in a safe manner and shall not subject personnel to unsafe conditions. The Contractor shall provide safety barricades, devices, and equipment to protect personnel and property and repair damage caused by construction operations. Take all precautions to protect the building and its occupants during the construction period.
8. SITE VISIT: The Contractor shall visit the site to determine the full extent of the work. Failure to inspect the site will not constitute grounds for a claim after contract award. A site visit will be scheduled through the COR, Felix SanMiguel, Bldg. 9, telephone number 903 583 6494 or by email felix.sanmiguel@va.gov.
9. GEMS: Disposal of materials removed under this contract at an approved disposal site in accordance with all local, state, and federal laws, regulations, and guidelines are the Contractor’s sole responsibility. The contractor shall adhere to all EPA requirements concerning removal, transporting, and disposal of the materials according to the TIL.
10. CLEAN-UP: The Contractor shall keep the area neat and tidy and free of debris at the end of each workday.
11. TEMPORARY FACILITIES: Temporary electrical power and water may be provided by the Government at no cost to the Contractor from existing lines and sources located at the building site. The characteristics and source locations may be verified by a visit to the site. The Contractor shall provide ample temporary storage shed space for materials requiring shelter from the weather, and security and safety protection. Storage facilities shall be in the areas of the facility designated by the Contracting Officer’s Representative.
12. SAFETY AND FIRE: All fire and safety rules and regulations are applicable; NFPA and SBCCI dated 1999. The Contractor shall comply with EM385-1-1 dated 1987 for minimum safety requirements and in accordance with the TIL.
13. PERMITS: The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required Federally and by the State of Texas.
14. WARRANTEE: The contractor shall warrantee work to be free of defects and workmanship for a period of 1 year from the close out of the entirety of the project.
15. STATEMENT OF WORK: The Contractor shall perform installation for all materials and components in accordance with TIL.
Work shall include installation, but is not limited to the following:
This project provides primarily correct issues with improper drainage, rain runoff, and undermining that building 24 is currently experiencing. The location of Building 24 is at the Sam Rayburn Memorial Veterans Center, 1201 E. 9th St., Bonham, Texas, 75418 A. Correct gutter downspout leaks according to designs provided.
B. Correct the storm drain inlets around the permitter of building 24.
C. Grading according to plan to redirect the water runoff around the perimeter of building 24 to correct any undermining of the building’s foundation.
D. Landscape according to design for the perimeter of the building to help with soil stabilization. Landscaping to be native to the reginal area, low maintenance, and draught resistance.
E. Correct existing gravity drain to be used by new downspouts F. They are total of 7 roof drain entrances that need replace.
G. St. Augustine grass must be utilized and minimum orbit brass type temp sprinkler system until grass adheres/takes growth.
15. QUALITY ASSURANCE: The Contracting Officer (CO)/ Contracting Office Representatives (COR) reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of theses specifications.
16. SUBMITTALS:
The contractor shall provide with their quote the following information:
ITEM DESCRIPTION
Doors Submit manufacturer's descriptive literature for screens and any accessories required to complete the work. Include data and details on screen construction and motorized components.
END OF SECTION
QUESTIONS & ANSWERS
1. Are we to dispose/abate of any asbestos, lead, mold, or other hazardous material as part of this project? If so, provide appropriate hazardous material site survey report.
· None.
2. What will the ICRA level be for this project?
· VA will submit ICRA once we receive means and method. This will determine level of precautions.
3. Are there any required/proprietary subcontractors the general contractor is to hire associated with this project?
· All subcontractor specialties must be well qualified and meet all local and government requirements.
4. Will all work associated with this project able to be performed during regular working hours?
· Yes, however contractor may request to work evenings and weekends.
5. When removing designated trees, is the contractor responsible for removing the stump and root system too?
· Yes, removing the stump and root system is required.
6. Is the contractor responsible for replacing landscaped areas with sod or gravel?
· The requirements are called out in the landscaping plans.
7. There are four (4) leaking roof drain above the loading dock. Is the contractor responsible for removing and replacing these roof drains?
· Plans show new surface mounted down spouts.
8. Plan Page A101, Demolition General Note 4 states that “Contractor shall determine the location of mildew on the interior of the building and coordinate with the VA for removal.” Is the contractor responsible for locating mildew and mold on the interior of the building? If yes, are there know quantities and locations of existing mildew and mold in the building?
· No existence currently under consideration or current condition.
9. Is the contractor responsible for replacing landscaped areas with sod or grass seed?
· The requirements are called out in the landscaping plans. Plans call for Sod. St. Augustine grass and a temp sprinkler system until grass adheres / takes growth to be priced.
10. Please provide a standard detail for the 6” curbs.
· Contractor to follow VA Standard for concrete curb shown below.
11. Do we need to use flowable fill?
· Flowable fill is required. We want to make sure that the surface backfill does not seep/go into holes under the building and we want to flush what animals are currently living under the building, so we can see and further prevent said animals from returning.
12. Does the new gutter system need to be painted and does the roof need to match? What color would be required?
· Roof match, but if cannot match exactly, then gutters are a color that complements the roof color. COR/Interior Designer to approve color.
13. Extent of removal of existing roof drains?
· 4 locations needing roof drain replacement near the dock area. Currently leaking. There are also a few drains near front, left (as you are looking at the front of the building) that requires adding.
14. Does the roof slope need to be reworked in areas the roof drains are being removed?
· No roof drains are being removed; they are being replaced. No roof slope rework needed.
15. During our site walk the interior spaces where damage was caused by the existing roof drains and has since been repainted by the maintenance crew so we were unable to verify the interior damage. Can the VA provide the extent of water damage to the interior and exterior of the building? This unclear at this time and plans put it off the on contractor to determine. We could not determine this on the site walk and information provided.
· No interior repairs included. That said, GC shall document/bring to COR’s attention any/all interior damage that is found in course of performing their work.
16. Can we get field condition photos on the existing roof hatches to have seals replaced? There was no access during our site visit. We need to verify if they're warped and the actual sizes. We'd like to get a photo of the tag model number if it's still on the equipment.
· Refer to attachments.
17. The plans call for us to follow as-builts, the plans provided are not a complete construction set. Can the VA provide the complete fully engineered set of plans that includes details, sections, depths, etc. along with any as-built information that applies?
· See as-builts. Note, this does not negate the GC’s responsibility to provide a complete product, nor does it give the GC the ability to request unforeseen conditions for everything they find, since they are contracted to do site visits that confirm any ambiguities with the current as-builts/drawings are absent of/ missing.
18. Has the VA performed a geotechnical report for this area?
· No
19. Does the VA have any existing SUE investigations of this area?
· NO
20. Does the VA have any existing a place to store gutters, area drains, and any other items the drawings call for us to store and protect?
· Yes, the COR to provide a small laydown yard/area, but GC shall be responsible for the security for yard/area to include secure with fencing a lockable gate.
21. In order for us to perform a SUE investigation properly on this site we need all lines shown to be accurate due to the material so they can properly verify them. The engineers have a caution note on several plans that state they're not responsible for the accuracy of the existing underground utilities. If the engineers can't confirm what needs to be verified would the VA consider this an unforeseen circumstance if an existing line was struck that is not shown?
· The VA expects the GC to add scanning of ground/areas, if required, into their costs/plan so that no unforeseen conditions requests are required.
22. Note #2 on sheet C-100 puts it off on the contractor to protect utility lines whether they're shown on the plans not, how should we verify lines no one is aware of their existence?
· VA expects the GC to add scanning of ground/areas, if required, into their costs/plan so that no unforeseen conditions requests are required.
23. Keynotes on sheets A-101 and A-201 are conflicting about which drains need to be removed and which are completely new based on the existing field conditions. One plan says to remain the other says provide new, please clarify.
· The existing down spouts are between the walls and remain in place. The existing down spouts are between the walls and remain in place, but the downspouts that are remaining in place have to be covered/sealed off so not to let water/ice to enter and expand/crack and cause more damage in the future. The new down spouts will be out, on the exterior of the wall and tied into the current gutter system at top and the storm drain at bottom.
See attached document: 40-01-A6 Access Doors Gutters Scuppers 6 Misc Details.
See attached document: Bonham Site-Model.
See attached document: Domicilary Building Plan Stairs Basement _ Misc.
See attached document: Electrical Oneline.
See attached document: Natural Gas.
See attached document: REDLINE DRAWINGS ELECT FEEDERS AND STREET LIGHTING.
See attached document: Sanitary.
See attached document: Steam.
See attached document: Storm Sewer.
See attached document: Street Lights.
See attached document: Transformers.