Technical Questions.docx
DOCX document 17 KB Posted
- Solicitation number
- 36C25722Q0848
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25722Q0848 0002_1.docx | DOCX document | |
| 36C25722Q0848 0002.pdf | ||
| 36C25722Q0848 0001_1.docx | DOCX document | |
| Attachment A Layout 1.pdf | ||
| Attachment B Site Plan 2020.pdf | ||
| 36C25722Q0848 0001.pdf | ||
| Attachment A_Domiciliary Bedroom Furniture.xlsx | XLSX spreadsheet | |
| 36C25722Q0848_1.docx | DOCX document | |
| RFQ 36C25722Q0848.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Questions 36C25722Q0848-Domiciliary Bedroom Furniture
1. Is a liftgate required for unloading? Does the building accommodate Dock to Dock service?
A: Liftgate isn’t required but is preferred. The building does not have a dock but our main hospital on site does. Site plan attached.
2. Is your site accessible by a 53’ trailer (18-wheel semi-truck)?
A: Yes.
3. How many floors are there? How many rooms on each floor? Is there a floor plan available?
A: 1 Floor. Plan attached
4. Which items are going in each room?
A: Each suite will receive a new bed, mattress, nightstand, and wardrobe.
5. Is there removal of old furniture? What furniture is in each room?
A: Yes. Current suites have bed/mattress, nightstand, and wardrobe to remove and be disposed of.
6. If multiple floors, is an elevator accessible?
A: Single Level
7. Will residents be on site during installation?
A: Yes.