36C25722Q0543 0001.docx
DOCX document 27 KB Posted
- Solicitation number
- 36C25722Q0543
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25722Q0543.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) none 36C257 Department of Veterans Affairs Network Contracting Office NCO 17 2002 Scott Blvd.
Temple TX 76504 36C257 Department of Veterans Affairs Network Contracting Office NCO 17 2002 Scott Blvd.
Temple TX 76504 To all Offerors/Bidders
36C25722Q0543 05-17-2022
X X x
X The purpose of this amendment will be as follows:
Post Questions and Answers.
Questions and Answers
1. Who will remove all utilities, security, sprinkler, standpipe, etc. from exterior walls prior to sheet metal demo?
Ans: The VA will remove the utilities, security, sprinkler and standpipe.
1. Is the height of the retaining wall to be 18” all the way to the end of the existing concrete wall as discussed in the site visit?
Ans: Yes, 18” height and 8” wide all down to the walkway entrance.
1. Please specify the portions of sheet metal that are to be replaced.
Sheet metal to be replace is from where the brick ends on the wall outside the doorway entrance to the turn where the garage starts.
1. Does the VA require the installation of an ADA ramp with a warning board at the end of the concrete run?
Ans: Yes, it does to the parking lot.
1. Is the contractor required to remove the wheel stop in front of the new ramp?
Ans: yes, the contractor will be required to remove the wheel stop in front of the new ramp.
1. Is the tree to near the end of the concrete run to be removed and include stump grinding?
Ans: Yes, the tree is to be removed and including stump grinding.
1. What is the concrete thickness requirement for the flume?
Ans: 4” thick for the flume.
1. What is the concrete thickness requirement for the retaining wall?
Ans: 8” thick for the retaining wall
1. Is rebar or fiber mesh required in the flume?
Ans: Rebar is required for the flume set at 24” OC.
File details come from the government source that posted it. Updated .