36C25722Q0399 0001_1.docx

DOCX document 18 KB Posted

Attached to
J045--NTX Replace Domestic Hot Water Recirculation At Main
Solicitation number
36C25722Q0399
Issued by

View the file

Other files

File Type Posted
Map to Site Visit Location.docx DOCX document
36C25722Q0399_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25722Q0399 - Replace Domestic Hot Water Recirculation

SUBJECT*
NTX Replace Domestic Hot Water Recirculation At Main

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
78240
SOLICITATION NUMBER*
36C25722Q0399
RESPONSE DATE/TIME/ZONE
04-29-2022 09:00 CENTRAL TIME, CHICAGO, USA
ARCHIVE
15 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N
SET-ASIDE
SDVOSBC
PRODUCT SERVICE CODE*
J045
NAICS CODE*
238220
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs-VISN 17

Network Contracting Office (NCO)17 5441 Babcock RD Suite 302.

San Antonio, TX 78240

POINT OF CONTACT*

Contract Specialist Jennifer Stringer jennifer.stringer@va.gov 254-899-6054

PLACE OF PERFORMANCE

ADDRESS
Department of Veterans Affairs

Garland VA Medical Center

Engineering Services

2300 Marie Curie BLVD

Garland TX

POSTAL CODE
75042
COUNTRY
USA

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS
jennifer.stringer@va.gov

EMAIL DESCRIPTION

DESCRIPTION

Amendment to a Previous Combined Solicitation

Amendment to a Previous Combined Solicitation The purpose of this amendment is to post questions with corresponding answers in order to facilitate more accurate quoting.

*= Required Field
Amendment to a Previous Combined Solicitation

Page 1 of

Amendment to a Previous Combined Solicitation

Questions and Answers:

1. Will the successful bidder be required to abate asbestos, lead, or any other hazardous material? If so, please provide the required survey report.

Asbestos abatement will not be required

1. Can this work be performed during normal working hours?

Yes

1. Is any of the work required to be after hours or on weekends?

No

1. How long can the domestic hot water be shut down if required?

Can be shut for extended hours since none of floors serviced by line are occupied

1. During the site visit a change to the scope of work was discussed. Will a new scope of work be issued for this project?

No change in scope of work

1. Are plumbing as-builts available for the basement up to the fourth floor? If yes, please provide to bidders.

No new lines or designs required, replace the existing piping per SOW. As-builts are not available at the moment, if they are located will be provided.