36C25718B0004-00004003.pdf
PDF 30 KB Posted
- Attached to
- Replace Roofs Building 1 and 28 (504-18-103) Federal contract opportunity
- Solicitation number
- 36C25718B0004
About this file
36C25718B0004 00004 SECTION B-SCHEDULE.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25718B0004-00004000.docx | DOCX document | |
| 36C25718B0004-00004002.pdf | ||
| 36C25718B0004-00004001.pdf | ||
| 36C25718B0004-00004004.pdf | ||
| 36C25718B0004-00003001.pdf | ||
| 36C25718B0004-00003000.docx | DOCX document | |
| 36C25718B0004-00002000.docx | DOCX document | |
| 36C25718B0004-004.pdf | ||
| 36C25718B0004-009.pdf | ||
| 36C25718B0004-002.pdf | ||
| 36C25718B0004-006.pdf | ||
| 36C25718B0004-008.pdf | ||
| 36C25718B0004-003.pdf | ||
| 36C25718B0004-007.pdf | ||
| 36C25718B0004-001.docx | DOCX document | |
| 36C25718B0004-005.pdf | ||
| 36C25718B0004-000.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION B – SCHEDULE OF PRICES/DESCRIPTION
DESCRIPTION: The Contractor shall provide all labor, materials, equipment, and supervision to replace roofs at the VA Amarillo facility as specified by the drawings and specifications and turn over the completed work to the VA within 60 calendar days after issuance of the Notice to Proceed (excluding VA Campus holidays).
ITEM UNIT TOTAL
NO. DESCRIPTION OF SERVICE QTY UNIT PRICE AMOUNT
BASE BID:
0001 PROVIDE ALL NECESSARY 1 JB $_____________ $______________
LABOR, TOOLS, MATERIALS, EQUIPMENT
AND SUPERVISION NECESSARY TO
REPLACE ROOFS PER THE PROVIDED
SPECIFICATIONS AND DRAWINGS.
0002 COST OF PERFORMANCE AND 1 EA $______________ $_______________
PAYMENT BONDS
0003 DEDUCTIVE ALTERNATE 1: 1 JB $_______________ $_____________
DEDUCT ALL WORK WHICH ENTAILS
TO THE PITCHED ROOF TO BUILDING 1 –
AREA B ON DRAWING A-101.
0003A DEDUCT COST OF PERFORMANCE AND 1 EA $______________ $___________
PAYMENT BONDS.
TOTAL PROJECT DURATION FOR BASE BID AND BID ALTERNATES: 60 Calendar Days from Issuance of the Notice to Proceed To Complete Project Work.
BASE BID TOTAL (Items 0001 – 0002): $ _______________________
BASE BID TOTAL MINUS DEDUCTIVE ALTERNATE 1 $ ___________________