Questions 11-18.pdf

PDF 61 KB Posted

Attached to
Mobile CT Scanner and technicians for Veterans Affairs Longview TX
Solicitation number
36C25627Q0112
Issued by

About this file

This is a Questions and Answers document for a Mobile CT Scanner contract requirement at the Longview Community Based Outpatient Clinic (CBOC) under the Overton Brooks VA Healthcare System.

The VA estimates 3,600 CT scans annually (approximately 164 scans per month or 7-8 scans per day), though this figure is not guaranteed and may fluctuate based on operational needs. The scanning schedule is Monday through Friday, 8:00 AM to 4:30 PM. The projected scan breakdown is 20% head, 35% chest, 35% abdomen, and 10% other procedures. The contract will utilize contrast and include lung screening but will not require cardiac scans. One CT-licensed technologist is required as the primary operator, with a trained CT assistant satisfying the VA regulatory requirement for two staff members present during scanning operations. The contract performance start date is targeted for January 1, 2027, with award expected by December 1, 2026, to allow time for staff hiring and mobile CT configuration. Performance will commence as soon as practicable following award and coordination with the awardee and VA facility. This is a new requirement with no prior CT capability at the Longview CBOC; correct power is established, and the lessor has agreed to installation. CT technologists will require access to VISTA, CARESTREAM/PACS, CPRS, and the S: Drive for protocolled exams. The VA will handle all patient scheduling and monthly audits. Mandatory training in BLS and CT Safety must be completed prior to onboarding; the VA will not compensate for training time. Personnel security clearance and credentialing verification must be completed within approximately one week to ten days of contract award.

View the file

Other files

File Type Posted
Performance Work Statement 11-18.pdf PDF
36C25627Q0112 0002.pdf PDF
QASP FOR CT SERVICES - 11-18.pdf PDF
36C25627Q0112 0001.pdf PDF
CSS RFQ 36C25627Q0112.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mobile CT Scanner – Longview – Questions and Answers

1. Have you Scanned at this location before? No, this is a new requirement

2. Is the correct power already installed and verified for mobile operation? It is not installed, but the correct power is established and the Lessor agrees to installation.

3. Are there any known power problems at the site? No

4. Can you guarantee 3600 patients per year? No. That is the best estimate we have at this time, but it cannot be guaranteed.

5. Can you guarantee any minimums scans per year? No. 3600 scans per year is the best estimate we have but it is not guaranteed. It could be more or less than that.

6. If another situation like covid hit would this site be shut down with 0 patients to scan?

or would we need to stay in the contract if scanning volumes are down and make payroll for the employees staffing this mobile This decision would be out of our local control

7. How many techs are needed to operate this unit? 1

8. Are the scanning day M-F 8-4? M-F: 5 days per week (M-F) 8:00 am – 4:30 pm

9. Will you be using contrast? Yes

10. Will you be doing lung screening? Yes

11. Can you break down the percentage of scans per 3600 per year (i.e., Head, Chest, abdomen)? 20% Head / 35% Chest / 35% Abdomen / 10% other

12. Will you require cardiac scans? No

1. What is the scheduled contract award date? Service starts Jan1, 2027, so award on or before Dec 1, 2026, will allow time to hire techs and finalize Mobile CT configuration. We will make award as soon as possible. The performance start date will be ASAP and will be coordinated with the awardee and the VA facility.

2. Number of scans per year 3600 = 164 scans per month and then 7-8 scans per day. What is the minimum number of scans per month that are guaranteed? There is no guaranteed minimum per month. 3600 is our best estimate, but more or fewer scans may be needed.

3. Staff: PWS 1. General “the Contractor shall provide a Technologist who possesses a CT license per VA regulation. VA regulations require 2 staff in a Mobile CT at all times during scanning. Does a Trained CT assistant meet that requirement? Yes

4. Training para 9. The training listed will take at least 1-2 weeks. Will the VA compensate us for those staff salaries during training. Suggest adding a contract line item for mandatory training. The VA does not intend to compensate for training time. BLS and any other required TMS training must be completed prior to onboarding at the VA facility. The contract employee will be granted access to TMS for this purpose.

Any additional BLS training can be conducted on site. The CT SME confirmed that the CT Safety training is available through TMS and can typically be completed within a few hours.

5. Scheduling: 10.2 “the contractor staff will aid in this process.” This task will detract from scanning and is an unpriced item. Suggest adding a line item for scheduling assistance. The VA will do all scheduling.

6. Para 23 Monthly Audits. These audits are to be performed by VA Staff, and should not involve our contracted staff. Correct

7. Para 24. Other Special Requirements: Employee verification of licenses, training, competency, credentials, must be completed by the COR and VA staff in less than 10 days of contract award so that staff can be hired to meet the contract start date. This process has been a huge VA staff bottleneck in previous contracts. Processing applicants through the Personnel Security Office has generally been quick; however, the timeline can vary and may become more time-consuming depending on individual circumstances. The overall speed of the process is largely dependent on the contract employee’s responsiveness and timely completion of required actions. Credentialing is a mandatory requirement, and there is no alternative pathway for onboarding a contract employee without completing the credentialing process. Based on recent experience, the Credentialing and Privileging Office has completed the credentialing of contract employees within approximately one week. As with the security process, timely completion is dependent on the applicant’s active participation and prompt response to requests.

8. Para 27. Contractor Personnel Security Requirements. “a background investigation and must receive a favorable adjudication from the VA Office of Security and Law Enforcement prior to contract performance. “This has typically been a long process and must be expedited by the VA in order that employees can be assigned to our contract. No one involved in the contract has any influence on this process.

9. Para 33. Access to VA information and VA Information Systems. What specific information systems will a CT technologist need access to? VISTA, CARESTREAM/PACS, CPRS / S: Drive for protocolled exams

10. Para 34. Delete if CT Technologist has no need to access VA Information systems N/A

11. Para 37. What does this mean? “ This entire section applies whenever sections 6 or 7 are included? Not applicable, as sections 6 and 7 do not apply.

12. Para 39. Viruses, Firmware, and Malware “This entire section applies when the acquisition involves any product (application, hardware, or software) or when section 6 or 7 is included. What are sections 6 or 7? Not applicable, as sections 6 and 7 do not apply.

13. Para 42. What are sections 6 or 7 and 8 through 12 are included? Not applicable, as sections 6 and 7 do not apply.

14. QASP para 5 a remove MRI and replace with CT. Ditto in the Performance Report ID 6 and 7. That looks like a typo based on using a previous PWS. It will be fixed.

I would appreciate knowing whether this mobile CT requirement is related to the replacement of an existing fixed CT system or whether it is intended to provide additional imaging capacity. There is no current CT capability at the Longview CBOC. This new contract does not augment or replace an existing capability.

If an existing system is being retired, MEC would welcome the opportunity to discuss professional removal services and potential equipment acquisition through authorized VA property procedures. N/A

I would also appreciate any assistance in identifying the Biomedical Engineering or Property Management representative responsible for future imaging equipment dispositions within the Overton Brooks VA Healthcare System. We cannot share that information.