This is a Statement of Work (SOW) for a construction project involving the upgrade and replacement of water utility infrastructure at the Central Arkansas Veterans Healthcare System (CAVHS) facility in North Little Rock, Arkansas.

The project (598-22-115) encompasses a comprehensive water system modernization including: installation of a new elevated water storage tank to address the campus's reserve capacity shortage; complete demolition of the existing 250,000-gallon water tower; construction of a new pump house with pumps, controls, security features, and emergency generator; installation of a new automated control system integrated with existing south pump house operations; and replacement of all failing water piping (cast iron, ductile iron, galvanized, and asbestos cement) with new pipe in looped configuration to improve supply redundancy and pressure. The work includes installation of backflow preventers on fire protection supply lines, pressure testing, disinfecting, and hyper-chlorinating per Federal, State, and Local codes. All work must minimize impact to campus operations, patients, visitors, and staff with no prolonged service outages; the contractor must coordinate all activities affecting the campus in advance and maintain 24/7 medical center operations.

The contractor must comply with extensive VA security protocols including obtaining VA-issued identification badges for all personnel, attending VA-funded Safety and Infection Control training, maintaining OSHA 30-hour certification for superintendents and OSHA 10-hour certification for all workers, and providing unarmed security guards for unsecured areas after construction hours. Work will be executed in multiple phases with 6-foot chain-link safety fencing around each phase work area. The contractor must develop a detailed work plan addressing procedures, equipment, interim life safety measures, and schedules; provide as-built drawings in PDF and AutoCAD format within 15 calendar days of each completed phase; submit a testing and commissioning plan prior to work commencement; provide maintenance and operating manuals (four hard copies and one electronic copy) and factory-trained manufacturer representatives for equipment instruction; and hold weekly progress meetings with the Contracting Officer Representative. The performance period is 720 calendar days from Notice to Proceed, with contractor warranty for faulty workmanship of not less than one year from Government acceptance, requiring return to site within one working day of notification for repairs at no charge.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

CONSTRUCTION PACKAGE

FOR

Upgrade/Replace Site Utility Infrastructure-NLR

Water Package 598-22-115

Central Arkansas Veterans Healthcare System

VISN 16, Station 598

North Little Rock, Arkansas

Prepared By

CAVHS Planning and Design Office

1. DESCRIPTION OF WORK

A. Contractor shall completely prepare site for construction operations, including demolition, removal of existing structures, furnish labor and materials, and to perform the work in accordance with this description of work and the project plans and specifications.

B. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project, employer, and restricted from unauthorized access.

C. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

D. The scope of this project includes upgrading the water source, storage, and site distribution system at the North Little Rock (NLR) Veterans Affairs Medical Center (VAMC) campus:

a. All work shall be done is a manner and sequence to minimize impact to the campus, patients, visitors and staff. No prolonged outages are permitted and any activity affecting the campus shall be coordinated in advance. See additional sections for detailed information.

b. The NLR campus is short of reserve water capacity. This project includes a new elevated water storage tank. The new tank installation shall include all labor and materials required for a complete and operational system including, but not limited to, supporting structure, piping, appurtenances, and accessories as required.

c. The existing elevated 250,000-gallon water tower shall be demolished in its entirety including all below grade supporting structure, piping vaults, etc. The demolition shall be in strict accordance with the phasing schedule.

d. A new pump house with new pumps and new pump controls is included in this project. Physical and operational security, monitoring, controls, redundancy and emergency power are included. The new pump house installation shall include all labor and materials required for a complete and operational system including, but not limited to, structure, fence, paving, piping, cameras, access control, emergency generator, appurtenances, and accessories as required.

e. A new automated control system that interlocks to and also controls the existing south pump house as well as the new north pump house is included in this project. The new system shall be seamlessly integrated into the existing automation system currently operating the south pump house.

f. This project also replaces all existing, failing cast iron, ductile iron, galvanized, asbestos cement, and/or any other material water pipe with new pipe as shown on the project plans. The water supply lines are generally looped to improve supply redundancy and improve the water pressure. Additionally, new backflow preventers shall be installed on the Fire Protection supply lines to buildings which have fire protection systems. This installation will include pressure testing, disinfecting, and hyper-chlorinating as required for new piping installation per Federal, State, and Local codes. Multiple phases are required and part of the project.

g. The entire, completed campus wide water system shall conform to all current VA, Federal, State and/or Local codes and regulations.

h. The Contactor and subcontractors shall attend a VA funded Safety and Infection Control training provided by Central Arkansas Veterans Hospital before any work begins.

i. All Superintendents are required to have an OSHA 30-hour safety training certification. All employees working on site must have an OSHA 10-hour safety training. This training is not provided by the VA.

j. All contractor personnel are required to wear VA provided identification badges.

The badges are to be worn in accordance with VA standards.

k. Work will be performed in phases. The contractor will only be allowed to work on one phase at a time, and each phase must have a safety fence surrounding the work area. This fence shall be chain link and 6’ in height.

l. All porta johns shall be contained inside the safety fence and are the contractor’s responsibility.

m. The contractor shall provide unarmed guards at the project site after construction hours for any unsecured areas. Guards are not necessary for areas with construction fencing.

n. The Contracting Officer’s Representative (COR) monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel.

The COR is not authorized to change any of the terms and conditions of the Contract.

2. PROJECT AREA

A. All work shall be performed North Little Rock (NLR) Veterans Affairs Medical Center (VAMC) campus

3. CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

i. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

ii. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

i. General Contractor’s employees shall not enter the project site without appropriate contractor developed and contractor provided badge. Contractor provided badges shall include company name, project number, and project name. They may also be subject to inspection of their personal effects when entering or leaving the project site.

ii. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort arrangements can be provided for the employees if required. This notice is separate from any notices required for utility shutdown described later in this section.

iii. No photography of VA premises is allowed without written permission of the Contracting Officer.

iv. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

4. PRIVACY AND INFORMATION SECURITY

A. Information Systems Officer, Information Protection:

i. The contractor will not have access to VA Desktop computers, nor will they have access to online resources belonging to the government while conducting services. If removal of equipment from the VA is required, any memory storage devices, such as hard drives, solid state drives and non-volatile memory units will remain in VA control and will not be removed from VA custody.

B. Privacy Officer:

i. The contractor will not have access to protected Patient Health Information (PHI) and nor will they have the capability of accessing patient information during the services provided to the VA and if removal of equipment from the VA is required, any memory storage devices, such as hard drives, solid state drives and non-volatile memory units will remain in VA control and will not be removed from VA custody. All research data available for Contractor analyses is de-identified.

C. Records Manager:

i. Citations to pertinent laws, codes, and regulations such as 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a);

36 CFR Part 1222 and Part 1228.

ii. Contractor shall treat all deliverables under the contract as the property of the U.S.

Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.

iii. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.

iv. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.

v. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.

vi. The Government Agency owns the rights to all data/records produced as part of this contract.

vii. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.

5. OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. Due to limited space on the North Little Rock (NLR) Veterans Affairs Medical Center (VAMC) campus, the contractor will use parking lot 10.

B. Workmen are subject to rules of Medical Center as applicable to their conduct.

C. Plan and execute the work with minimal impact to the normal functioning of Medical

Center as a whole, including patient care, operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

i. Do not store materials and equipment in other than assigned areas.

ii. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.

D. Phasing:

i. The Medical Center must maintain its operation 24 hours a day 7 days a week.

Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

a. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof.

6. AS-BUILT DRAWINGS

A. The contractor shall maintain one full-size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings.

To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two (2) approved, completed sets of as-built drawings in the electronic version (scanned PDF and AutoCAD Record Drawings) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the

COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

7. AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

8. UTILITY SHUTDOWNS

A. No utility services such as water, gas, steam, HVAC, sewers, electricity, or fire protection systems and communications systems may be interrupted without prior approval of the CAVHS Chief Engineer. If services must be interrupted to other services outside of the immediate work area of this scope, a minimum of 14 days’ written notice must be submitted for approval. This outage request must identify the affected buildings, areas, rooms, date, duration, outage description, and the procedure of the intended work.

9. TESTS

A. The contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

10. INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub assembly components. Manuals shall include an index covering all component parts clearly cross referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to ensure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage.

The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

11. PROJECT MEETINGS

A. Each week the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government. Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.

B. Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer Representative (COR). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and email addresses; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision.

Copies of updated minutes shall be distributed to all attendees within 48 hours after change notice.

12. HOLIDAYS: The following legal holidays are observed by this Government Agency to include any day declared by the federal government as holiday.

New Year's Day January 1st Martin Luther King's Birthday Third Monday in January Presidents Day Third Monday in February Memorial Day Last Monday in May Juneteenth June 19th Independence Day July 4th Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th

13. FINAL CLEANUP

A. Final clean up and finishes. At the completion of the work, all fixtures, equipment, and materials shall be cleaned. The Contractor shall do a final cleaning to include disposal of debris resulting from construction as well as dispose of containers for the materials used during the performance of the work.

14. PERIOD OF PERFORMANCE

A. The Performance Period for this project is seven hundred twenty (720) calendar days after issuance of the Notice to Proceed.

15. WARRANTY

A. Contractor will warrant its work against faulty workmanship for a period of not less than one year from the date of Government acceptance of the work provided under this contract. Under this warranty, contractor shall be prepared to return to the work site within one working day after notification without charge to make any necessary repairs.