About this file

This document contains the A/E Submission Instructions for Minor and NRM Construction Program from the Department of Veterans Affairs. It outlines the minimum requirements for each submission in the production of VA Schematics, Design Development, and Construction Documents for Medical Center Projects.

The document details the specific content and format requirements for the 25% Schematic, 35%, 65%, 95% Design Development, and 100% Construction Document submissions. It covers requirements for site development, architectural, fire protection, interior design, structural, plumbing, sanitary, HVAC, electrical, equipment, steam generation, steam distribution, solid waste disposal, automatic transport, asbestos abatement, space planning, CPM, estimating, and specifications. The document also provides instructions for the distribution of A/E materials. This appears to be an internal VA document and does not address a specific federal contract opportunity.

View the file

Other files for this federal contract opportunity

Other files attached to C1DA--AE Project #667-24-133-Renovate 3N SICU & Replace AHU, newest first.
File Type Posted
36C25625R0017 0001.docx DOCX document
36C25625R0017- Renovate 3N SICU and Replace AHU SOW 111824.docx DOCX document
36C25625R0017.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Veterans Affairs Overton Brooks VA Medical Center

(OBVAMC)

PROJECT 667-088

Design to Renovate 3N SICU & Replace AHU

ATTACHMENT A

A/E Submission Instructions for Minor and NRM Construction Program:

· Schematics

· Design Development

· Construction Documents

Department of Veterans Affairs

Washington, DC 20420

FOREWORD

This document states the minimum requirements for each submission in the production of VA Schematics, Design Development, and Construction Documents for Minor and NRM Construction Program for Medical Center Projects. It will give VA reviewers and the A/E a clear understanding of what is required of the A/E at each stage of design.

This document does not relieve the A/E firms of their professional responsibility to produce a correct, complete, and fully coordinated set of construction documents.

Lloyd H. Siegel

William W. Graham

Director, Facilities Quality Office

(Acting) Director, Engineering Management and

Field Support Office

A/E SUBMISSION INSTRUCTIONS FOR

MINOR AND NRM CONSTRUCTION PROGRAM

MEDICAL CENTER PROJECTS

Table-of-Contents

I.

GENERAL

A. INTRODUCTION

B. A/E RESPONSIBILITIES

C. SUBMISSION POLICY

D. QUALITY ASSURANCE/QUALITY CONTROL

E. ADDITIONAL SERVICES

F. CRITICAL PATH METHOD

II.

SUBMISSIONS

A.

SITE DEVELOPMENT

B.

ARCHITECTURAL

C.

FIRE PROTECTION

D.

INTERIOR DESIGN

E.

STRUCTURAL

F.

PLUMBING

G.

SANITARY

H.

HVAC

I.

ELECTRICAL

J.

EQUIPMENT

K.

STEAM GENERATION

L.

STEAM DISTRIBUTION (OUTSIDE)

M.

SOLID WASTE DISPOSAL SYSTEM (INCLUDING INCINERATION)

N.

AUTOMATIC TRANSPORT

O.

ASBESTOS ABATEMENT

P.

SPACE PLANNING

Q.

CRITICAL PATH METHOD (CPM)

Table of Contents (Cont.)

R.

ESTIMATING

S.

SPECIFICATIONS

T.

FINAL BID DOCUMENTS

III.

DISTRIBUTION OF A/E MATERIAL

SYMBOL IDENTIFICATION OF CONTRACT DRAWINGS

GENERAL NOTES

A/E SUBMISSION INSTRUCTIONS FOR

MINOR AND NRM CONSTRUCTION PROGRAM

MEDICAL CENTER PROJECTS

I.

GENERAL

INTRODUCTION

1.

This document contains information and minimal submission requirements for contract documents specified in the A/E contract.

2.

The Department of Veterans Affairs (VA) may contract with an Architect/Engineer (A/E) for any portion of a design: Schematics, Design Development, Construction Documents, or a combination of these.

a.

For projects where the VA is contracting for Schematics Documents only, Schematics and Design Development Documents only, or Schematics, Design Development, and Construction Documents, the VA will provide the Design Program (if available), Facility Development Plans (if available), and VA design standards to accompany the Scope of Work for the project.

b.

For projects where the VA is contracting for Design Development and Construction Documents only, the VA will provide the Schematics Plans and VA design standards to accompany the Scope of Work for the project.

c.

For projects where the VA is contracting for Construction Documents only, the VA will provide the Design Development Plans and VA design standards to accompany the Scope of Work for the project.

3.

Coordinate all activities with the VA Medical Center (VAMC) COR. Hold informal meetings (upon mutual consent of the VA and the A/E) at the VAMC to discuss the design and related issues. Continue to expand contacts by telephone, rough sketch studies and other means of communication with the purpose of finalizing a general design approach to be followed.

4.

Final approved Schematic documents shall be the basis for the development of the Design Development phase. Likewise, final approved Design Development documents shall be the basis for the development of the Construction Documents phase. The VAMC must approve any changes from each set of documents before the A/E proceeds to the next phase.

5.

VA will review all submittals for functional and aesthetic relationships. However, no further functional decisions are anticipated after the Design Development phase.

6.

Provide a design narrative/analysis for each technical discipline (e.g., architectural, mechanical, fire protection, etc.) which describes the intent of each discipline with schematic and/or design development submission.

7.

Provide computations and sizing calculations for electrical, mechanical (HVAC, plumbing, and steam), sanitary, structural and fire protection designs. For computerized calculations, submit complete and clear documentation of computer programs, interpretation of input/output, and description of program procedures.

8.

Provide individually packaged drawings for each submission to each unit specified in the "Distribution of A/E Materials" section.

9.

Submit a complete set of final approved drawings incorporating all revisions, in accordance with the Contracting Officer’s approved Design Schedule.

10.

At each review stage, the VA’s technical reviewer, a value-engineering consultant, or a construction manager will perform a value engineering review.

11.

Submit final drawings (Bid Documents) as per the 100% Construction Documents Instructions, para C.1.e.

B.

A/E RESPONSIBILITIES:

1.

Contract documents shall meet or exceed the requirements of this document.

2.

The A/E is responsible for producing a complete set of drawings, design narrative/analysis, calculations, sample boards, and specifications in accordance with professional standard practices and VA criteria. Each A/E discipline shall receive a copy of their respective VA design manuals, standard details, construction standards, and VA National CAD Standard Application Guide. The AE is responsible for obtaining the NCS.

3.

A/E shall conduct coordination meetings between A/E technical disciplines before submitting material for each VA review and provide minutes of the meetings to VAMC.

4.

A/E shall adhere to the approved Memorandum of Agreement (MOA).

5.

A/E shall provide a checklist of all submittals, certifications, tests, and inspections required per drawing and specification section.

6.

In addition, the A/E shall conduct interim fire protection installation inspections and witness final fire protection equipment testing.

C.

SUBMISSION POLICY:

1. There is a 25% Schematic* submission, a 35%; 65% and 95% Design Development (DD**) submissions, and a 100% complete Construction Document (CD***) submission as indicated below.

a. 25% Schematic Design: Investigate and survey project site. Verify any VA provided data. AE is responsible for collecting any and all data required for the design. The A/E is responsible for measuring and collecting actual field data that may be required. The A/E shall collaborate with VA COR and end user(s) to develop conceptual and viable design options to meet the intended scope of work. The A/E shall develop schematic drawings and design options, along with Pro’s and Con’s with associated cost for review. This schematic design phase is an iterative process and requires close coordination back and forth with the VA COR/Project manager. The preliminary schematic design/layout will most likely require tweaking until a final plan/layout is officially approved by the hospital and COR. Dimensions, areas, spaces, etc. will need to be indicated clearly on the drawings. With respect to space, the A/E needs to identify the size of the existing space, the space VA standard and proposed space for review and consideration (Space Program – Current, VA Standard & Proposed). The AE shall work with the VA COR until an acceptable plan is developed and approved in writing by the VA COR. The A/E final deliverables for this phase are (hard and electronic copies):

1) OBVAMC Approved Plan (Siting Plan & Floor Plan)

2) Preliminary Cost Estimate (RS Means, Cost Works)

3) List of probable Specification Sections for this project

4) Initial Design Analysis and Approach

b. 35% Design Development: These drawings shall be at the largest scale possible and shall show the utilities, infrastructure, architectural layout of each floor, room dimensioning/square footage, room identification, fire exists (Life Safety), chases, columns and other pertinent information necessary to provide information that will carry the design to the next review.

1) Drawings & Specifications: Provide one 22”x34” size D set, four 17”x22” size C sets and one unbound 11”x17” size B set of preliminary construction drawings. Provide one set of preliminary specifications indicating all of the AE proposed edits in a 3-hole punch binder. Drawings and specifications to indicate potential deductive bid alternates and any phasing requirements. Also, provide electronic copies on a CD (Drawings PDF format, Specifications in Word format).

2) Cost Estimate: Provide a detailed cost estimate indicating labor, material and equipment cost in RS Means CostWorks format. Estimate shall include Prime Contractors Overhead, Profit, Bond and Labor Burden (typically 32%). Estimate shall indicate feasible deductive bid alternates to bring the construction cost within the allotted construction budget. This cost estimate shall be submitted in hard copy with the Design Analysis and an electronic copy on a CD.

3) Design Analysis: Provide a design analysis for each discipline indicating the design rational, thought process and design calculations (including actual field test and test date). Provide a summary of deductive bid alternates. Provide a draft preliminary detailed submittal register. Provide a list, by discipline, on what outstanding data or feedback is required from OBVAMC. Provide one hard copy of the Design Analysis and one electronic copy on a CD.

4) FPE Review/Certification: Provide review comments made by the Fire Protection Engineer for this submission.

NOTE: The AE shall not proceed with the 65% design without written concurrence from the VA COR.

c. 65% Design Development: This submission of drawings, specifications and cost estimate shall be very close to complete. This review by the VA shall be to validate that 35% comments were incorporated into the project. The construction documents should be sufficiently developed to cover all work items to be addressed by the project, including clearing defined phasing requirements and deduct bid alternates. No major items missing from this submission. The VAMC review of these documents should result in very minor comments to allow for the next 95% submission. A/E shall provide a list of questions by discipline on anything that’s needed from the VA to continue and fully develop the next 95% design submission. Additionally, the A/E shall provide minutes from the last design review meeting and shall provide responses to all VA comments noted or identified during the last review submission.

1) Drawings & Specifications: Submit in the same manner as the 35% DD submittal. Specifications shall incorporate AE’s edits.

2) Cost Estimate: Submit in the same manner as the 35% DD submittal.

3) Design Analysis: Submit in the same manner as the 35% DD submittal. Include A/E responses to all 35% design review comments.

4) FPE Certification: Submit in the same manner as the 35% DD submittal. Specifications shall incorporate AE’s edits.

d. 95% Design Development: This submission of drawings, specifications and cost estimate shall be complete. This review by the VA shall be to validate that 65% comments were incorporated into the project. There shall be nothing missing from the construction documents. The VAMC review of these documents should result in very minor comments to allow for the next submission to be final. If the comments of this set of documents results in numerous comments, then a 99% review or a check set of certain elements of the design may be required before the AE shall proceed to the 100% Final Construction Documents.

1) Drawings & Specifications: Submit in the same manner as the 65% DD submittal.

2) Cost Estimate: Submit in the same manner as the 65% DD submittal.

3) Design Analysis: Submit in the same manner as the 65% DD submittal. Include A/E responses to all 65% design review comments.

4) FPE Certification: Submit in the same manner as the 65% DD submittal

e. 100% Construction Documents: This submission shall incorporate all project requirements and previous comments. These documents shall be ready for bidding/construction.

1) Drawings & Specifications: ALL ENGINEERS AND ARCHITECTS PROFESSIONAL “STAMPS” SHALL BE ON THIS SET OF DOUMENTS. Provide one 22”x34” size D set, four 17”x22” size C sets and two 11”x17” size B sets of FINAL construction drawings (one set of the 11”x17” size drawings to be unbound). Provide two set of FINAL fully edited specifications (specs in a 3-hole punch notebook, printed on both sides of the paper). Drawings and specifications to indicate potential deductive bid alternates and any phasing requirements. Provide two CD electronic copies of the entire package (Construction Drawings, Specifications, Design Analysis and Cost Estimate). The drawings shall be as both AutoCAD (2017)/BIM, and PDF format both in individual files per drawing and a combined drawing PDF file. The specifications shall be in separate WORD documents and separate PDF files for each specification section. Also, provide a combined PDF file for each complete volume of the specifications. Coordinate the naming & numbering of the files with the COR.

2) Cost Estimate: Submit FINAL CostWorks cost estimate in the same manner as previous submittal.

3) Design Analysis: Submit FINAL and complete Design Analysis documents including all calculations for each discipline. Submit in the same manner as the previous submittals. Include A/E responses to all design review comments.

4) FPE Certification: Provide a FINAL certification letter from a registered Fire Protection Engineer stating that the FINAL plans and specifications are in compliance with the current Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) code

2. At each submission, the A/E shall date all material and present the designs on VA standard size drawings that are appropriately labeled, "SCHEMATIC SUBMISSION", “DESIGN DEVELOPMENT SUBMISSION”, OR “CONSTRUCTION DOCUMENT SUBMISSION”, in large block letters above or beside the VA standard drawing title block. In each submission, the A/E shall incorporate the corrections, adjustments, and changes made by VA at the previous review.

3. The VA Staff shall have a minimum of 16 business days to review and coordinate each A/E design submission. If the VA work load does not allow for a thorough review within the 16-day time frame, the A/E shall not proceed to the next design phase until comments have been received from the VA. The A/E will be entitled to a time only contract extension for the number of VA review days beyond 16 days.

D.

QUALITY ASSURANCE/QUALITY CONTROL (QA/QC):

In an effort to reduce construction change orders due to design errors and omissions, the Office of Facilities Management has initiated a Quality Assurance/Quality Control program. The A/E shall develop, execute, and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort. The requirements are as follows:

Fee Proposal: Provide an outline of the actions that your firm will take during the design process along with an associated fee.

2.

Two Weeks after Receipt of the Notice To Proceed: Submit a detailed QA/QC Plan describing each step that will be taken during the development of the various phases of design. Each step should have an appropriate space where a senior member of the firm can initial and date when the action has been completed.

3.

100% Submittal: Submit the completed QA/QC Plan along with the latest marked-up documents (plans, specifications, etc.) necessary to ensure that a thorough review and coordination have been completed.

E.

ADDITIONAL SERVICES:

If additional services (i.e. surveys, soil borings, asbestos surveys, water flow testing, or lead surveys), are necessary to be performed by consultants, submit criteria for the work to be performed to the VAMC Contracting Officer as soon as possible. Upon approval of the criteria, submit proposals and qualifications of at least three firms being considered for the work in accordance with the contract procedures (CP1) of the contract, together with a proposal from the recommended firm and a brief justification for its selection, for VA approval. A/E should submit survey information for the Schematic Review.

Critical Path Method PHASING MEETINGS

A.

If required and prior to submission of Schematic material, the A/E shall meet with the VAMC’s Project Manager to discuss and outline phasing requirements for the project. These phasing requirements shall describe the general sequence of the project work, estimated project duration, and what Government constraints will exist that will influence the Contractor's approach to the construction project. The A/E shall be responsible for recording the phasing requirements.

B.

Submit a phasing narrative and phasing plans (on reduced size plans) within two weeks after each phasing meeting to the VAMC Project Manager. VA will review these submission(s) and return comments to the A/E within two weeks of receipt. The A/E will then use this information in preparing their schematic, design development, and construction document submissions.

A.

SITE DEVELOPMENT: Submit the following:

Site Development:
Schematics*
DD**
CD***
Narrative
(
Analysis of site
(
Circulation study
(
Phasing analysis
(
Parking analysis
(

Development concept showing proposed buildings and structures

Landscape drawings with plant groupings

Topographic, utility, and landscape survey

(
(
Demolition plan
(
(
(

Layout plan showing location of:

* Building and structures
(
(
(
* Roads
(
(
(

* Fire Access

(
(
* Parking
(
(
(

* Accessible spaces

(
(

* Van spaces

(
(
* Mechanical and electrical equipment on grade
(
(
(
* Future expansion
(
* Off-site roads
(
(
(
* Off-site utilities
(
(
(

* Service area(s)

(
(

* Entrances and exits

(
(

* Walks

(
(

* Inlets

(
(

* Contractor's staging area

(
(

* Vertical and horizontal road alignment

(
(

* Paving joint patterns

(
(

Grading plan showing:

* Existing contours

(
(

* Proposed contours

(
(

* Spot elevations at structure corners, entrances, equipment pads, etc.

(
(

* First floor elevations

(
(

* Rim and invert elevations on storm drainage fixtures

(
(

* Erosion and sediment control

(
(

Rock excavation (quantity)

(
(

Planting plan showing:

* List of plant material
(
(
(
* Limits of irrigation
(
(
(

Site details

(
(

Landscape details

(
(

Signage plan and schedule

(
(

Specifications

(
(

Submit site and landscape plans at an appropriate scale to show all work involved.

Submit site and landscape plans at same scale as topographic/utility survey incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated site and landscape plans incorporating all revisions required by comments from the design development phase.

B.

ARCHITECTURAL: Submit or show the following:

Architectural:
Schematics*
DD**
CD***

Location of:

* Rooms1
(
(
(
* Doors2
(
(
(
* Corridor(s)3
(
(
(
* Basic column grid/sizes
(
(
(
* Expansion and seismic joints
(
(
(
* Electrical closets
(
(
(
* Equipment rooms
(
(
(
* Signal and telephone closets
(
(
(
* Mechanical shafts and space
(
(
(

* Stair(s)

(
(

* Ramp(s)

(
(
* Elevator(s)
(
(
(
* Automatic Conveyances
(
(
(

Floor Plans/Drawings:

* All floors (new and renovated)
(
(
(
* Penthouse
(
(
(
* Roof plan
(
(
(
* Pipe basement
(
(
(

* Pipe tunnel

(
(

* Reflected ceiling4

(
(

* Equipment floor plans 1:50 (1/4 inch) scale5

(
(

* Demolition plans6

Room names and numbers7

(
(
Program net/designed net
(
(
(

Exterior dimensions/total building gross area

(
(
(

Size and shape of all departmental functions and services9

(
(
(
Exterior building elevations10
(
(
(
Finish floor elevations11
(
(
(

Door locations, sizes, and swings

(
(

Wall thickness and chase walls

(
(

Handrail location/dimensions

(
(

Fixed equipment

(
(

Equipment elevations and details

Plumbing fixtures

(
(

Wheelchair accessible facilities

(
(

Wall sections12

(
(

Building sections13

(
(

Finish grades at corners, entrances, exits, platforms and ramps

(
(
Fire and smoke rated partitions14
(
(
(

Lead-lined and radio-frequency-shielded partitions14

(
(

Fire extinguisher cabinets14

(
(

Spray-on fire proofing (see fire protection)

Construction details15

(
(

Drafting symbols, abbreviations, and general notes

(
(

Door, window, and louver schedules

Interior details, elevations, sections

Finish schedule16

(
(

Graphics and signage17

Color rendering

Specifications

(
(

Lead abatement18

Lead abatement specification19

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). A scale of 1:200 (1/16 inch) is acceptable for architectural floor layout if an entire floor cannot be shown on one sheet. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

B.

NOTES:

1.

Use lines between spaces to indicate the centerline of the partition (for schematics only).

2.

Indicate doors with a slash mark.

3.

Along the corridor, the line shall represent the corridor side of the partition.

4.

Indicate ceiling mounted equipment, lighting fixtures, air diffusers, registers, tracks, and other significant elements.

5.

Identify all equipment for each room. Indicate and coordinate all equipment with the Equipment Guide List (Program Guide 7610) and Activated Equipment List. Use VA standard symbols and notation to distinguish between contractor-furnished and installed (CC), VA-furnished contractor-installed (VC), VA-furnished and installed (VV), VA-furnished with construction funds [VC(CF) and VV(CF)], and relocated (R) equipment. Equipment floor plans are not required for the offices, consultation rooms, classrooms, conference rooms, and waiting rooms within the above departments. Draw equipment details which are necessary for major decisions, though complete detailing is not required for this submittal.

6.

Indicate existing finish schedule and notes on plan.

7.

Label as required for schematic drawings. Coordinate new room numbering with medical center.

8.

Use the same names on drawings as those used in the space program. Provide area figures in fractional form, e.g., 400/390. Indicate space provided, but not called for in the space program, as: -/390.

9.

Label each service or activity listed in the Project Scope Data of the Design Program and indicate boundaries with a distinctive line. Include the activity code number (see Handbook 7610).

10.

If the project requires exterior work, show all facades indicating massing, proposed fenestration and the building relationship to adjacent structures and the finish grade. Show all significant building materials, including their colors, any proposed roof top mechanical equipment, architectural screens, skylights, and stacks on the elevation drawings. If building is designed for future expansion (vertical and/or horizontal), delineate elevations with and without the future expansion. If project is an addition, show elevations of the existing building in sufficient detail to illustrate the relationship between the new and existing in terms of scale, material, and detail.

11.

Define the relationship of the finish ground floor to finish grade at major entrances and docks.

12.

Indicate construction including fire resistance rating, building materials and systems, and proposed sill and head heights of openings. Indicate both new and renovated areas on form provided by VA.

13.

Define building configuration. Draw sections at the same scale as floor plans, normally 1:100 (1/8 inch). If the building abuts an existing structure, indicate in the section how the new floor elevations align with existing.

14.

Identify psychiatric areas where special considerations are required to ensure the safety of patients (e.g. hard ceilings, safety glazing, etc.).

15.

Indicate new building components and systems, such as window design, roofing system, special entryways, building "skin", and any special architectural elements for the project. Complete detailing of miscellaneous items is not required for this submission.

16.

Indicate all building systems, materials, and future expansion, if applicable.

17.

Submit a drawing for all which is part of the construction contract.

C.

FIRE PROTECTION: Submit the following:

Fire Protection:
Schematics*
DD**
CD***

Fire protection narrative:1

* Fire and smoke separation
(
* Fire sprinkler/standpipe system
(
* Size of fire pumps
(
* Water supply available/max. demand
(
* Water flow testing results
(
* Fire alarm systems2
(

Existing to be modernized

Base loop system for interface of new construction
(

* Kitchen extinguishing systems

* Size of air handling unit
(
* Exit paths from each zone
(
* Distances to stairs
(
* Occupancy of each area
(
* Exit calculations for each floor
(
* Smoke control features
(

Floor Plans/Drawings:3 & 4

* Sprinkler zones
(
* Fire alarm zones
(
* Smoke zones
(
* Building water supply
(
* Interior sprinkler supply lines
(
* Standpipes
(
* Fire extinguisher cabinets
(
(
(
* Fireproofing of structural members
(

* Sprinkler/standpipe riser supply piping

(
(

* Termination of sprinkler main and inspector test drains

(
(

* Sprinkler alarm valves

(
(

* Waterflow and tamper switches

(
(

* Sprinkler system fire department connections

(
(

* Sprinkler design hazards per

NFPA 13

(
(

* Exit signs and emergency lighting

(
(

* Occupied areas not protected by automatic sprinklers

(
(
Calculations
(
(
(

Estimated capacities for proposed air handling units in cubic meters (cubic feet) per minute

(
(

Location of:

* Fire alarm system

(
(

* Annunciator panels

(
(

* Pull stations

(
(

* Flow switches

(
(

* Audio-visual devices

(
(

* Smoke detectors

(
(

* Duct smoke detectors

(
(

* Smoke dampers

(
(

* Fire dampers

(
(

* Fire alarm risers5

(
(

* Exit signs

(
(

* Emergency lighting

(
(

* Fire sprinklers

(
(

* Standpipes

(
(

* Fire hydrants

(
(

* Fire pumps

(
(

* Post indicator valves

(
(

* Sectional valves

(
(

* Fire extinguisher cabinets

(
(

* Electromagnetic door hold open devices

(
(

Wall sections indicating fire resistive ratings

(
(

Staff sleeping rooms

(
(

Excavation plan signage

(
(

Door and window schedule with fire rating or fire rated glazing

Zoning of each fire alarm initiating device

Details:

* Fire pump system (capacity and pressure)

* Elevation and isometric view of fire pump

* Stairwell sign

* Annunciator panel

Interconnection of fire alarm system with:

* Smoke dampers

* Air handlers

* Elevator controls

* Kitchen fire extinguishing and fire pump system

* HVAC system with smoke duct detectors

Single line riser diagram for fire alarm system

Height/configuration of storage racks and shelving

Specifications

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

C.

NOTES:

1.

Indicate NFPA 220 and UBC fire resistive rating of the building, NFPA 101 occupancy type, and fire protection code analysis to access compliance with NFPA 101.

2.

Determine type, features, age, reliability, compliance with present day codes, capacity, zoning, supervision, control panel and power supplies, initiating devices and circuits, and auxiliary functions for existing fire alarm system. Indicate manufacturer, model number, voltage, and wiring style of existing alarm systems and devices. Provide recommendations for the proposed fire alarm work.

3.

Provide information to meet JCAHO requirements; e.g. location of all fire rated barriers, smoke barriers, exit signs, fire extinguishers, manual pull stations, smoke detectors, and sprinkler flow switches. Show all interim life safety measures such as temporary systems Fire Alarm, Sprinkler, and Smoke.

4.

At DD Submission, add room names, room numbers, door locations and swings, smoke and fire rated partitions, sprinkler/standpipe risers to floor plans. Identify psychiatric areas on drawings so areas for institutional type heads are identified. Add location of all valves (post indicator, sectional) and backflow preventer if provided.

5.

Show new equipment and/or the necessary changes involved if modification to the existing system is required. Include any recommendations where certain requirements of VA criteria might be waived, in order to allow the existing equipment to be reused.

D.

INTERIOR DESIGN: Submit the following:

Interior Design:
Schematics*
DD**
CD***
Written interior design concept1
(
Illustrate overall design solution2
(
Material and finish samples
(
Sketches
(

Design solution for interior spaces:

* Perspectives

(
(

* Plans

(
(

* Details

(
(

* Elevations

(
(

* Sections

(
(

* Wayfinding

(
(

* Floor patterns

(
(

* Wall patterns

(
(

* Lighting

(
(

* Signage

(
(

* Handrails

(
(

* Bumper guards

(
(

Specification section 09050

(
(

Finish schedule

(
(

Exterior colors and materials

(
(

Sample boards for interior and exterior materials, products, and finishes

(
(

Edited carpet and wallcovering specifications

(
(

Specifications

Keyed Finnish plans

Interior design details, elevations, and sections

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

D.

NOTES:

1.

Provide a document of data collected in interior design programming. Include collection and analysis of data from the VAMC project coordinator and interior designer. Data includes, but is not limited to the following: existing interior and exterior design and materials, light, safety, patient profile, customer’s “vision” or desired image, public vs. private spaces, complete signage package, goals of customer, relationship to existing facilities, future expansion/renovation plans, regional influences, etc.

2.

Discuss and illustrate the overall design solution for the primary areas of the project using marked-up floor plans, loose sketches, and material and finish samples. Use broad categories of materials, finishes, color palettes, patterns, textures, and scales. Separately group all major neutral background materials and finishes that will be used and discuss how they will be integrated with all other materials and finishes on the project. Include all primary and secondary corridors, typical patient and toilet rooms, lobbies, atriums, eating spaces, chapels, waiting rooms, and exam rooms. Show the relationship among departments and functions, and between public and private spaces.

E.

STRUCTURAL: Submit the following:

Structural:
Schematics*
DD**
CD***

Three alternative structural systems for typical bays1

Supporting calculations2
(
(
(
Cost estimates for each system3
(
Recommend preferred system
(
Column locations
(
Shear load resisting elements4
(
Boring location plan5
(

Structural plans6

(
(

Sections

(
(

Details

(
(

Size/location of:

* Columns

(
(

* Beams

(
(

Lateral load resisting elements

(
(

Load bearing walls

(
(

Slabs

(
(

Foundations

(
(

Elevations

Schedules

General notes

Boring logs

Subsurface investigation report

Estimated quantity of rock

Specifications

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

E.

NOTES:

1.

When only one structural system is possible due to other project requirements, include an explanatory statement and submit only that structural system.

2.

Include vertical and lateral load design for CD submission.

3.

Include foundation and fireproofing.

4.

Indicate existing utilities and structures within, adjacent, or contiguous to the new construction.

5.

Upon approval of the subsurface investigation criteria, submit qualifications of at least three consultants being considered for the work together with the proposal of the consultant recommended as most qualified.

6.

If there is only a CD submission, provide a Structural Engineering Analysis Submission within six weeks from the notice to proceed including sketches, calculations, and cost estimates of three alternative structural systems for typical bays, boring location plan for subsurface investigation, and consultant qualifications. For vertical expansion projects, analyze existing structure for structural feasibility.

F.

PLUMBING: Submit the following:

Plumbing:
Schematics*
DD**
CD***

Narrative:

* Existing plumbing systems to be used and necessary modifications

(
(
(
* New plumbing systems
(
(
(
* New or modified water treatment
(
(
(

Floor Plans/Drawings:

* Room names
(
(
(

* Identify

Existing plumbing fixtures w/VA numbering system

(
(
(

New plumbing fixtures w/VA numbering system

(
(
(
Existing equipment
(
(
(
New equipment
(
(
(

New medical gas outlets

(
(

New laboratory gas outlets

(
(
Plumbing piping
(
(
(

* Size of pipe

(
(

* Equipment schedule

(
(
* Fire & smoke partitions
(
(
(

* Demolition plans

(
(

* Riser diagrams

* Legend, notes, and details

Location and size of sprinkler riser, standpipes, and fire pumps (see fire protection)

(
(

Location of emergency eyewash and shower equipment

(
(

Calculations (equipment & piping)

(
(

List of Required Contract Specifications

Contract Specifications

PLUMBING (cont.):

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch).

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics phase.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch).

G.

SANITARY: Submit the following:

Sanitary:
Schematics*
DD**
CD***

Narrative:

* Existing sanitary systems:

underground water, sanitary sewers, storm sewers, & fuel gas with sources, disposal methods, storage pressures, condition, etc.

(
(
* New sanitary systems
(
(
(

* Provide water analysis & expected yield if well required

(
(
(

* Circulation study to assess emergency vehicle access

(
(
(
Install test well, if well is required.
(

Utility Plans/Drawings showing existing and new sanitary systems:

* Size of pipes
(
(
(
* Invert elevations of sewers
(
(
(

* Locate/size

Pumps
(
(
(
Storage facilities
(
(
(
Treatment equipment
(
(
(

Fire hydrants

(
(

Sectional and post indicator valves

(
(

Backflow preventer

(
(
* Areas of new irrigation system
(

* New irrigation system

* Profiles of sanitary & storm sewers

* Demolition Plans

(
(

* Legend, notes, and details

Point of connection to sprinkler system
(
(
(

Calculations

(
(

List of specifications

Contract Specifications

G.

SANITARY (cont.):

Submit utility drawings at same scale as provided for Site Development drawings.

Submit utility drawings at same scale as provided for Site Development drawings, incorporating all of the revisions required by comments from the schematics phase.

Submit utility drawings at same scale as provided for Site Development drawings, incorporating all of the revisions required by comments from the design development phase. Submit legend, notes, and details at a scale not less than 1:100 (1/8 inch).

H.

HVAC: Submit the following:

HVAC:
Schematics*
DD**
CD***
Description of HVAC systems
(
Equipment for each functional space
(
Life cycle cost analysis1
(

Tentative location/sizes:

* Mechanical equipment room
(
* Principal vertical shafts
(
Block layout of equipment
(

Louvers:2

* Outside air
(
(
(
* Exhaust air
(
(
(
* Relief air
(
(
(
Engineering calculations3
(
(
(

Selection of HVAC equipment

(
(

Catalog cuts of equipment

(
(

Room by room heating and cooling loads

(
(

Zone by zone heating & cooling loads

(
(

Building block heating & cooling loads

(
(

Tabulation of steam consumption

(
(

Psychometric chart for air handling unit

(
(

Coil entering and leaving conditions

(
(

Fan motor heat gains

(
(

Consumption of humidification loads

(
(

Sound/acoustic analysis

(
(

Room-by-room air balance charts4

(
(

Chilled water plant:5

* Quantity and type of chillers

(
(

* Capacity in tons of refrigeration

(
(

* Electrical equipment

(
(

Heating system:

* Total heating load

(
(

* Domestic hot water load

(
(

* Humidification load

(
(

* Equipment steam demand

(
(

* Zoning of heating system

(
(

HVAC floor plan:6

* Main supply, return and exhaust ductwork

(
(

* Volume dampers

(
(

* Fire and smoke partitions

(
(

* Fire and smoke dampers

(
(

* Smoke detectors

(
(

* Automatic control dampers

(
(

* Air quantities for each room

(
(

* Air inlets/outlets

(
(

* Rises and drops in ductwork

(
(

* Expansion loops

(
(

* Anchors

(
(

* Vales

(
(

* Drip assemblies

(
(

* Balancing fittings

(
(

Interconnection of HVAC equipment with fire protection equipment (see fire protection)

(
(

Plan/section of mechanical equipment rooms

(
(

Schematic flow and riser diagrams7

(
(

Schematic control diagrams8

(
(

HVAC demolition drawings

(
(

Phasing plan

(
(

Equipment schedule

(
(

Seismic bracing

(
(

VA symbols and abbreviation

(
(

Selection of

* Pumps

x
(

* Fans

x
(

Sizing and selection of

* Expansion tanks

x
(

* Steam to hot water convertor

x
(

* Heat exchangers x

Sound analysis

x
(

Complete selection data

x
(

Outside chilled water and condenser water distribution9

x
(

Standard detail drawings

x
(

Automatic temperature control drawings10

x
(

HVAC specifications

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

H.

NOTES:

1.

Provide specific design recommendations and full back-up data. Include the heating and cooling capacities of each functional area and the block cooling and heating loads for each new and/or existing building.

2.

The locations of these louvers must not allow short circuiting of air from emergency generator exhaust or truck waiting and loading dock areas into air intake etc. Consider factors affecting louver location such as visibility, historical considerations, wind direction, nuisance and health hazard odors (from emergency generator or truck exhausts).

3.

Include room-by-room, peak zone-by-zone, and building block heating and cooling loads. Provide a tabulation of steam consumption based on data from all sources. Show correlation between each HVAC zone boundary and architectural floor area correlation between the architectural room numbers and abbreviated/coded room numbers used with computer input data sheets.

4.

Show supply, return, exhaust, make-up, and transfer quantities with intended pressure relationships, i.e. positive, negative, or zero with respect to adjoining spaces.

5.

Provide pertinent data on accessories such as pumps and cooling tower etc. Show the extent of the outside chilled water and condenser water piping. Clearly show how the piping will be laid in tunnels, trenches, or by direct burial.

6.

Show ceiling clearances, at locations where ducts cross each other, by providing 1:50 (1/4 inch) scale local sections. Show all ductwork, and piping 150 mm (6 inch) and larger in double line. Show separate floor plans for air distribution and piping unless waived by VA. Show clearances required for access and maintenance with coil and tube pull.

7.

Show typical air handling systems and all hydronic systems with existing capacities and new estimated loads. Verify actual operating conditions and capacities of HVAC systems prior to design.

8.

Show control devices, such as, thermostats, humidistats, flow control valves, dampers, freezestats, operating and high limit sensors for all air systems and fluids, smoke dampers, duct detectors etc. Provide a written description of the sequence of operation on the floor plans. Detail the scope of work involved with the Central Engineering Center (ECC) and address if enough spare capacity is available or a new ECC is required. Show a point schedule for analog/digital input/output to be included in ECC.

9.

Show pipe sizes and insulation with plans, profile, sections, details, and all accessories, such as, anchors, expansion loops/joints, valves, manholes, capped and flanged connections, interface between the new and existing work (if any). Clearly indicate interferences (if any) with the existing utilities and/or landscape elements on outside piping layout drawings. Show rerouting any utilities, cuttings of roads, pavements, trees, etc., and the extent of new and demolition work. Outside utility drawings shall be based on the study of the latest site drawings, discussions with engineering personnel, and actual site inspection of the existing utility.

10.

Show all duct detectors, control valves/dampers static pressure sensors, differential pressure control assemblies, etc., whose actual physical location is critical for the intended sequence of operation on floor plans.

I.

ELECTRICAL: Submit the following:

Electrical:
Schematics*
DD**
CD***

Narratives:

* Design1
(

* Life cycle analysis for electrical systems

Location and size of:

* Electrical equipment2
(
* Electric closets3
(
* Telephone closets3
(
* Signal closets3
(

* Electrical distribution equipment

Drawings showing:

* Electrical plot plan of existing and proposed underground power (including manholes)

(
(
(
* Telephone systems
(
(
(
* Signal inter-building systems
(
(
(
* Proposed electrical system4
(
(
(
* Electric symbols
(
(
(
* Lighting fixture schedule
(
(
(

* Emergency Life Safety Equipment (see fire protection)

* Symbols, note, abbreviations

(
(
List of specialty areas
(
Method of short-circuit calculations
(

Method of voltage drop and demand calculations

Utility company correspondence
(

Utility company requirements

(
(

Load calculations for normal & emergency use

(
(
(

Drawings:

* Lighting layouts

(
(

* Power layouts

(
(

* Signal layouts

(
(

* Specialty area layouts

(
(

* Demolition plans

(
(

Riser diagrams

(
(

Branch circuit wiring (typ.)

(
(

Location and size of:

* Primary distribution switchgear/switchboard

(
(

* Engine-generator sets

(
(

* Substation/padmounted transformer

(
(

* Manholes

(
(

Location of smoke dampers and duct smoke detectors

Interconnection of electrical control equipment with HVAC equipment (see fire protection)

Smoke partitions and fire alarm zones
(
(
(

Fire alarm and signal riser diagrams (see fire protection)

(
(

Calculations for emergency generator(s)

(
(

Phasing scheme

(
(

Electrical details

Specifications

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

I.

NOTES:

1.

Include basic assumptions, points of interconnection, impact of new construction to existing electrical distribution system, current demand loading (high voltage switchgear and primary feeder), and projected load of new construction. Propose various feasible electrical systems for project and provide advantages/disadvantages.

2.

Include means and clearances for installation, maintenance, and removal/replacement of equipment.

3.

Electrical, signal and telephone closets must stack vertically.

4.

Include high voltage and low voltage switchgear, transformers and low voltage main and/or distribution panels, branch panels and methods of feeding 277/480 volt and 120/208 volt normal and emergency panels.

J.

EQUIPMENT: Submit the following:

Equipment:
Schematics*
DD**
CD***
Equipment (on architectural drawing)
(
(
(

Activation Equipment List (Excel format)

(
(

Specifications

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

K.

STEAM GENERATION: Submit the following:

Steam Generation:
Schematics*
DD**
CD***

Report on new and existing steam loads1

Life-cycle cost analysis of steam supply alternatives

Analysis of alternate plant locations

Life-cycle cost analysis for alternative types of equipment

Life-cycle cost analysis for heat recovery alternatives

Data on emissions regulations
(
Data on methods of compliance
(
Selection of major equipment
(

Plot plan with new and existing plant locations

Fuel related storage and handling facilities

Alternate plan view layouts of new and existing plant

Plot plan of steam generating facility2

(
(

Catalog cuts on equipment from two manufacturers

(
(

Plans/sections/locations of:

* Equipment

(
(

* Major piping

(
(

* Pipe supports

(
(

Demolition

(
(

Schematic flow diagrams of all piping systems

(
(

Calculations:

* Equipment sizing
(
(
(

* Major piping systems

(
(

* Steam load

(
(

* Control and regulating valve

(
(

* Flowmeter systems

(
(

* Steam trap

(
(

* Heating and ventilating system

(
(

* Steam piping

(
(

Schedules

(
(

Equipment lists

(
(

Verification of emission regulations

(
(

List of standards and details

Specifications

(
(

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

K.

NOTES:

1.

Include maximum and minimum summer and winter demands and total annual production. Provide break-down of new steam loads into categories of end use such as building heating, humidification, reheat, domestic hot water, sterilization, line losses, kitchen, and laundry.

2.

Show boilers, pumps, heat recovery devices, tanks, and emission control devices.

L.

STEAM DISTRIBUTION (OUTSIDE): Submit the following:

Steam Distribution (Outside):
Schematics*
DD**
CD***
Estimate steam and condensate loads
(
(
(

Life-cycle cost analysis of steam distribution system

Calculations of pipe sizing
(
(
(
Steam distribution plot plan
(
(
(

Existing underground utilities

Soil conditions report
(
(
(

Performance requirements for steam traps

(
(

Calculate pipe stress

(
(

Select expansion facilities for piping

(
(

Location of:

* Manholes

(
(

* Pipe expansion devices

(
(

Profile drawings including existing utilities

(
(

Plan views/sections/dimensions for major piping, pipe layout and pipe supports of:

* Manholes

(
(

* Trenches

(
(

* Tunnels

(
(

Demolition Plans

(
(

Submit outside steam generation plans at an appropriate scale to show all work involved.

Submit outside steam generation plans at same scale as topographic/utility survey incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated outside steam generation plans incorporating all revisions required by comments from the design development phase.

M.

OMIT SOLID WASTE DISPOSAL SYSTEM INCLUDING INCINERATION: Submit the following:

Solid Waste Disposal System Including Incineration:
Schematics*
DD**
CD***

Incineration report including:

1. amount and type of waste (new & existing)

2. emissions regulations and types of emissions controls required

3. life-cycle cost analysis on alternatives for waste disposal

4. calculations of equipment sizing and description of types of equipment

5. viable alternatives for waste disposal

Evaluation of capability of existing incinerator

Complete description of existing processing system

Tests to determine remaining service life and capacity of system

Plot plan with new plant location and location of existing plant

Plan view layout of new system or existing system showing new equipment location

Load calculations on amount and types of waste

(
(

Plot plan with location of new processing system

(
(

Plans/sections showing locations of:

* Equipment

* Major piping

(
(

Demolition

(
(

Catalog cuts (2 min.) of equipment selections

(
(

Emissions control devices

(
(

Schedules

(
(

Equipment lists

(
(

List of standards to be furnished later

(
(

List of special details to be furnished later

(
(

Verification of applicable emissions regulations affecting design or operation

Specifications

Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.

Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.

Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.

N.

AUTOMATIC TRANSPORT: Submit the following:

Automatic Transport:
Schematics*
DD*
CD*

Automatic transport systems (ATS):

* Narrative w/ recommended improvements for exiting system

* Traffic study including existing and proposed ATS w/ alternate methods of distribution

Changes to existing systems (arch. dwgs.)

Hoistway (arch. dwg.)

(
(

Machine room vents (arch. dwg.)

(
(

Type of ventilation (mech. dwg.)

(
(

Electrical requirements (elect. dwg.)

(
(

Drawings:1, 2, & 3

* Automatic Transport Systems

* Elevators

(
(

* Dumbwaiters

* Other ATS systems

Sizes/dimensions/details:

* Hoistway enclosures

(
(

* Pits

(
(

* Pit ladders

(
(

* Machine area ladder and railings

(
(

* Entrances

(
(

* Machine rooms

(
(

Locations/dime…