This is a Statement of Work (SOW) for emergency repair services for a GE LOGIQ E9 Ultrasound machine (Asset Number 1772184) at the Biloxi VA Medical Center. The document details a one-time service to replace the back-end processor (computer) of the ultrasound system, which is currently non-functional. The repair must be performed by manufacturer-trained GE technicians who are factory-certified on the specific device, with services to be completed within 5 days after contract award.

Key requirements include: technicians must have current factory training and certification, provide evidence of equipment standards and performance testing, comply with all federal, state, and manufacturer regulatory requirements, maintain continuous access to the most up-to-date manufacturer software, and guarantee a 95% equipment uptime rate. The work will be performed during normal business hours (8:00 a.m. through 4:30 p.m. Monday through Friday) at the Biloxi VA Medical Center, with services limited to the specified GE LOGIQ E9 ultrasound machine with serial number LE9203716US6. The contract includes stringent information security and privacy provisions typical of VA medical equipment service agreements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Service Plan/Agreement

Gulf Coast Veterans Health Care System Biomedical Engineering

1. OBJECTIVE: The Gulf Coast Veterans Health Care System requires the following services for the facility:

Emergency Repair Services for a GE Ultrasound with Asset Number 17721874. The original issue was that the Ultrasound will not boot up. The GCVHCS purchased diagnostic services that has been paid via a government purchase card. The issue of the back end processor (the ultrasound’s computer) needing replacement was found, and the services and parts to replace it are now needed.

2. GENERAL: This is a non-personnel services requirement. The contractor shall provide all management, supervision, labor, transportation, tools, materials, parts, and other items necessary to perform work, execute services, and to successfully complete all deliverables as contained within this Statement of Work. The Government shall not exercise any supervision and/or control over contractor personnel (which includes contractor service providers, contractor representatives, and subcontractors employed with and/or being utilized by the prime contractor) during all active performance periods of the contract. All contractor personnel shall be accountable solely to the Contractor, who in turn is responsible to the Government.

3. BACKGROUND: The GE Ultrasound is already utilized by the facility in support of facility operations for the delivery of veteran patient care. The services needed are a back end processor (the ultrasound’s computer) replacement and the labor associated with it. Scanning system use sound waves at frequencies well above the level of human hearing to generate an image of tissue in a transverse plane of the body. These systems convert an electrical signal into ultrasonic energy that is transmitted into tissues. The intensity, time, and direction of the echoes are measured and processed to generate an amplitude display (A-mode), a two-dimensional ""brightness modulated"" image display (B-mode), or a one-dimensional graphic display of a moving structure (M-mode). Ultrasonic scanning systems are used in many diagnostic procedures, including gynecologic, obstetric, cardiac, vascular, endoscopic, thyroid, and breast procedures.

4. SCOPE OF SERVICES: The services needed (to include required Deliverables) are described below. The manufacturer of the devices needed services is GE.

1. Services must ONLY be performed by manufacturer trained technicians, who have evidence of current factory training on the specific device being serviced. This must be available 24 hours a day from the vendors help desk line.

2. Must provide evidence of equipment standards and traceability and final device performance testing that follows and complies with all manufacturer’s procedural requirements.

3. Must guarantee that safety inspections performed will comply with all applicable federal, state, and regulatory requirements, manufacturer standards, and meet FDA alerts and recall requirements.

4. Each technician must be certified on the device prior to performing any service and/or maintenance on manufactured equipment.

5. Must provide evidence of recent attendance and successful completion of the Manufacturer Factory Training Seminars for each product serviced.

6. Must maintain continuous access to the most up to date manufacturer software revisions of the equipment listed.

7. Must guarantee execution of all Manufacturer Service Recommendations during each service incident, including the use of ONLY manufacturer planned maintenance and repair parts. (Note: Failure to utilize original manufacturer parts may result in the improper operation of the equipment.)

8. Must possess the legal rights to propriety software. Must provide updated versions of the software when released.

9. The service technician must have completed training for each specific device by a Manufacturer Authorized Trainer prior to performing service on said device.

10. The vendor must keep equipment functioning at a 95% uptime rate. The vendor must perform preventative maintenance that adheres to the original equipment manufacturer schedules.

11. The vendor must sign up for and utilize OR Trax to check in to the facility upon arrival.

12. The equipment to be covered under this contract is listed below:

Manufacturer: Model: Serial Number: MX Number:

GE LOGIQ E9 LE9203716US6 1772184

5. PLACE OF PERFORMANCE: Work will be performed, services will be executed, and deliverables will be completed at the following:

Biloxi VA Medical Center, 400 Veterans Ave, Biloxi, MS 39531.

6. PERIOD OF PERFORMANCE: The expected period of performance for services executed under the final contract for this acquisition is a one time service no later than 5 days after award.

Option years may or may not be exercised based on the needs of (and at the discretion of) the U.S.

Government.

7. WORK HOURS AND SCHEDULE: All work, execution of services, and completion of deliverables must be accomplished during normal business hours, 8:00 a.m. through 4:30 p.m. Monday through Friday, Federal Holidays excluded. Prior to work being performed proper coordination shall be initiated between the contractor and the government to ensure that services/work can be executed when scheduled. Any work, services, and/or other tasks performed during other than normal business hours must be approved in advance by the Contracting Officer Representative (COR), Contracting Officer, and/or other authorized facility designee/representative before such work begins. The Federal Holidays that are currently being observed by the facility are listed in the table below.

New Year’s Day January 1 Martin Luther King‘s Birthday Third Monday in January

President’s Day Third Monday in February Memorial Day Last Monday in May Juneteenth Independence Day June 19th

Independence Day July 4 Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11 Thanksgiving Day Fourth Thursday in November

Christmas Day December 25

Other Federal Holidays (that could occur) Any other day specifically declared to be a national holiday (per Federal Statute, Executive Order, or by the President’s Proclamation).

An alternative schedule (different from the schedule described above) may be utilized if there is mutual agreement between the government and the contractor regarding this alternative schedule if implemented.

8. PERSONNEL PERFORMING WORK/SERVICES - REQUIRED “CORE COMPETENCIES”:

Personnel performing work, executing services, and completing deliverables during the active performance periods of the contract shall possess the knowledge, skills, and abilities required to successfully execute the services described herein. No unqualified individual shall be allowed to perform work, execute services, and to complete deliverables at any time under the contract while active.

9. KEY PERSONNEL

During the active performance periods of the contract a Key Personnel Person shall be designated by the contractor (to be contacted by the government when needed) regarding performance of work, execution of services, and completion of Deliverables as contained within this Statement of Work and covered by the final contract. This Key Personnel person must have sufficient knowledge to be able to respond to technical questions by the government.

10. DELIVERABLES:

Required Deliverables

DELIVERABLE #1:

ROUTINE REPORTING, DOCUMENTATION, AND SERVICE LOG

Documentation shall be provided following execution of services, performance of work, and completion of deliverables during the active performance periods of the contract. A service log describing the efforts completed under the final contract shall be prepared, maintained, and provided to the government if/when requested.

DELIVERABLE #2:

CHECK IN AND CHECK OUT PROCEDURES

Before beginning any work at any time during the active performance periods of the contract personnel performing services must physically check in with the appropriate facility representative to obtain approval and confirmation of the expected work to be performed and services to be executed. Check out procedures will be the same once work has been completed and services have been executed. Check in and check out procedures shall include the following: 1). Written documentation of the contractor’s arrival and departure while on site and 2). Written documentation showing the expected work to be performed, approval of such work before such work begins, and confirmation/completion status of the planned work that was scheduled to be performed.

Facility personnel and the contractor may modify such procedures if there is mutual agreement among both parties regarding changes to these procedures if implemented.

11. RECORDS MANAGEMENT

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be management and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be management in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4. GVSM and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of GVSM VAMC or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to GVSM VAMC. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment.

Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the contract. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. Contractor personnel shall sign VA Form 10-0708 “Employee Clearance from Indebtedness” before resigning or termination from Contractor working for GVSM VAMC Facility Records Officer must sign form. A copy of completed signed VA Form 10- 0708 (Contractor personnel and Facility Records Officer signatures) shall be place in each competency folder.

When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to GVSM control, or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

6. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training. TMS(Talent Management System) course VA 4192704 : “Records Management for Everyone”.

7. Flow-down of requirements to subcontractors

a. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this contract and require written subcontractor acknowledgment of same.

b. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.

12. OTHER REQUIREMENTS:

12.1 Identification and Badges: Any individual performing work under this contract shall wear a badge or other identification while on site that is clearly displayed at all times. While on site, any person performing work directly or indirectly must be in a position to specify their authorized purpose for their presence at the facility in the event that such information is requested by VA facility personnel.

12.2 Parking: It is the responsibility of the contractor to park in the appropriate designated parking areas, to avoid ticketing or towing. Information on parking is available from the facility if requested by the contractor.

12.3 Contract Administration: The Contracting Officer is the only person authorized to approve changes or modify any of the requirements under this contract. The Contractor shall communicate with the Contracting Officer on all matters pertaining to contract administration. Only the Contracting Officer is authorized to make commitments or issue changes that will affect price, quantity, or quality of performance of this contract. In the event the Contractor makes any such change at the direction of any person other than the

Contracting Officer, this change shall be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof. All changes to the contract will be issued via an amendment and/or modifications in writing from the Contracting Officer to the Contractor.

12.4 Invoicing and Payment: Contractor is authorized prompt payment IAW applicable regulation following the successful performance of work, execution of services, and completion of required deliverables.

Contractor invoices shall be submitted IAW VAAR Clause 852.232-72 Electronic Submission of Payment Requests. Invoices submitted for payment must be detailed to the extent necessary to reflect the work done and the services performed during the time periods when completed so an accurate assessment can be made by the facility for certification of these invoices for payment. Advance payments are not authorized, and contractor is not authorized payment for future work not performed and/or for work that has not been successfully completed.

13. VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY LANGUAGE

1. GENERAL. This entire section applies to all acquisitions requiring any Information Security and Privacy language. Contractors, contractor personnel, subcontractors and subcontractor personnel will be subject to the same federal laws, regulations, standards, VA directives and handbooks, as VA personnel regarding information and information system security and privacy.

2. VA INFORMATION CUSTODIAL LANGUAGE. This entire section applies to all acquisitions requiring any Information Security and Privacy language.

a. The Government shall receive unlimited rights to data/intellectual property first produced and delivered in the performance of this contract or order (hereinafter “contract”) unless expressly stated otherwise in this contract. This includes all rights to source code and all documentation created in support thereof. The primary clause used to define Government and Contractor data rights is FAR 52.227-14 Rights in Data – General. The primary clause used to define computer software license (not data/intellectual property first produced under this contractor or order) is FAR 52.227-19, Commercial Computer Software License.

b. Information made available to the contractor by VA for the performance or administration of this contract will be used only for the purposes specified in the service agreement, SOW, PWS, PD, and/or contract. The contractor shall not use VA information in any other manner without prior written approval from a VA Contracting Officer (CO). The primary clause used to define Government and Contractor data rights is FAR 52.227-14 Rights in Data – General.

c. VA information will not be co-mingled with any other data on the contractor’s information systems or media storage systems. The contractor shall ensure compliance with Federal and VA requirements related to data protection, data encryption, physical data segregation, logical data segregation, classification requirements and media sanitization.

d. VA reserves the right to conduct scheduled or unscheduled audits, assessments, or investigations of contractor Information Technology (IT) resources to ensure information security is compliant with Federal and VA requirements. The contractor shall provide all necessary access to records (including electronic and documentary materials related to the contracts and subcontracts) and support (including access to contractor and subcontractor staff associated with the contract) to VA, VA's Office Inspector General (OIG), and/or Government Accountability Office (GAO) staff during periodic control assessments, audits, or investigations.

e. The contractor may only use VA information within the terms of the contract and applicable

Federal law, regulations, and VA policies. If new Federal information security laws, regulations or VA policies become applicable after execution of the contract, the parties agree to negotiate contract modification and adjustment necessary to implement the new laws, regulations, and/or policies.

f. The contractor shall not make copies of VA information except as specifically authorized and necessary to perform the terms of the contract. If copies are made for restoration purposes, after the restoration is complete, the copies shall be destroyed in accordance with VA Directive 6500, VA Cybersecurity Program and VA Information Security Knowledge Service.

g. If a Veterans Health Administration (VHA) contract is terminated for default or cause with a business associate, the related local Business Associate Agreement (BAA) shall also be terminated and actions taken in accordance with VHA Directive 1605.05, Business Associate Agreements. If there is an executed national BAA associated with the contract, VA will determine what actions are appropriate and notify the contactor.

h. The contractor shall store and transmit VA sensitive information in an encrypted form, using VA-approved encryption tools which are, at a minimum, Federal Information Processing Standards (FIPS) 140-2, Security Requirements for Cryptographic Modules (or its successor) validated and in conformance with VA Information Security Knowledge Service requirements. The contractor shall transmit VA sensitive information using VA approved Transport Layer Security (TLS) configured with FIPS based cipher suites in conformance with National Institute of Standards and Technology (NIST) 800-52, Guidelines for the Selection, Configuration and Use of Transport Layer Security (TLS) Implementations.

i. The contractor’s firewall and web services security controls, as applicable, shall meet or exceed

VA’s minimum requirements.

j. Except for uses and disclosures of VA information authorized by this contract for performance of the contract, the contractor may use and disclose VA information only in two situations: (i) in response to a qualifying order of a court of competent jurisdiction after notification to VA CO (ii) with written approval from the VA CO. The contractor shall refer all requests for, demands for production of or inquiries about, VA information and information systems to the VA CO for response.

k. Notwithstanding the provision above, the contractor shall not release VA records protected by Title

38 U.S.C. § 5705, Confidentiality of medical quality-assurance records and/or Title 38 U.S.C. § 7332, Confidentiality of certain medical records pertaining to drug addiction, sickle cell anemia, alcoholism or alcohol abuse or infection with Human Immunodeficiency Virus (HIV). If the contractor is in receipt of a court order or other requests for the above-mentioned information, the contractor shall immediately refer such court order or other requests to the VA CO for response.

l. Information made available to the contractor by VA for the performance or administration of this contract or information developed by the contractor in performance or administration of the contract will be protected and secured in accordance with VA Directive 6500 and Identity and Access Management (IAM) Security processes specified in the VA Information Security Knowledge Service.

m. Any data destruction done on behalf of VA by a contractor shall be done in accordance with

National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management, VA Handbook 6300.1, Records Management Procedures, and applicable VA Records Control Schedules.

n. The contractor shall provide its plan for destruction of all VA data in its possession according to

VA Directive 6500 and NIST 800-88, Guidelines for Media Sanitization prior to termination or completion of this contract. If directed by the COR/CO, the contractor shall return all Federal Records to VA for disposition.

o. Any media, such as paper, magnetic tape, magnetic disks, solid state devices or optical discs that is used to store, process, or access VA information that cannot be destroyed shall be returned to VA.The contractor shall hold the appropriate material until otherwise directed by the Contracting Officer’s Representative (COR) or CO. Items shall be returned securely via VA-approved methods.

VA sensitive information must be transmitted utilizing VA-approved encryption tools which are validated under FIPS 140-2 (or its successor) and NIST 800-52. If mailed, the contractor shall send via a trackable method (USPS, UPS, FedEx, etc.) and immediately provide the COR/CO with the tracking information. Self-certification by the contractor that the data destruction requirements above have been met shall be sent to the COR/CO within 30 business days of termination of the contract.

p. All electronic storage media (hard drives, optical disks, CDs, back-up tapes, etc.) used to store, process or access VA information will not be returned to the contractor at the end of lease, loan, or trade-in. Exceptions to this paragraph will only be granted with the written approval of the VA CO.

3. ACCESS TO VA INFORMATION AND VA INFORMATION SYSTEMS. This section applies when any person requires access to information made available to the contractor by VA for the performance or administration of this contract or information developed by the contractor in performance or administration of the contract.

a. A contractor/subcontractor shall request logical (technical) or physical access to VA information and VA information systems for their employees and subcontractors only to the extent necessary to perform the services specified in the solicitation or contract. This includes indirect entities, both affiliate of contractor/subcontractor and agent of contractor/subcontractor.

b. Contractors and subcontractors shall sign the VA Information Security Rule of Behavior (ROB) before access is provided to VA information and information systems (see Section 4, Training, below). The ROB contains the minimum user compliance requirements and does not supersede any policies of VA facilities or other agency components which provide higher levels of protection to VA’s information or information systems. Users who require privileged access shall complete the VA elevated privilege access request processes before privileged access is granted.

c. All contractors and subcontractors working with VA information are subject to the same security investigative and clearance requirements as those of VA appointees or employees who have access to the same types of information. The level and process of background security investigations for contractors shall be in accordance with VA Directive and Handbook 0710, Personnel Suitability and Security Program. The Office of Human Resources and Administration/Operations, Security and Preparedness (HRA/OSP) is responsible for these policies and procedures. Contract personnel who require access to classified information or information systems shall have an appropriate security clearance. Verification of a Security Clearance shall be processed through the Special Security Officer located in HRA/OSP. Contractors shall conform to all requirements stated in the National Industrial Security Program Operating Manual (NISPOM).

d. All contractors and subcontractors shall comply with conditions specified in VAAR 852.204-71(d);

Contractor operations required to be in United States. All contractors and subcontractors working with VA information must be permanently located within a jurisdiction subject to the law of the United States or its Territories to the maximum extent feasible. If services are proposed to be performed abroad the contractor must state where all non-U.S. services are provided. The contractor shall deliver to VA a detailed plan specifically addressing communications, personnel control, data protection and potential legal issues. The plan shall be approved by the COR/CO in writing prior to access being granted.

e. The contractor shall notify the COR/CO in writing immediately (no later than 24 hours) after personnel separation or occurrence of other causes. Causes may include the following:

i. Contractor/subcontractor personnel no longer has a need for access to VA information or VA information systems.

ii. Contractor/subcontractor personnel are terminated, suspended, or otherwise has their work on a VA project discontinued for any reason.

iii. Contractor believes their own personnel or subcontractor personnel may pose a threat to their company’s working environment or to any company-owned property. This includes contractor-owned assets, buildings, confidential data, customers, employees, networks, systems, trade secrets and/or VA data.

iv. Any previously undisclosed changes to contractor/subcontractor background history are brought to light, including but not limited to changes to background investigation or employee record

v. Contractor/subcontractor personnel have their authorization to work in the United States revoked.

vi. Agreement by which contractor provides products and services to VA has either been fulfilled or terminated, such that VA can cut off electronic and/or physical access for contractor personnel.

f. In such cases of contract fulfillment, termination, or other causes; the contractor shall take the necessary measures to immediately revoke access to VA network, property, information, and information systems (logical and physical) by contractor/subcontractor personnel. These measures include (but are not limited to): removing and then securing Personal Identity Verification (PIV) badges and PIV – Interoperable (PIV-I) access badges, VA-issued photo badges, credentials for VA facilities and devices, VA-issued laptops, and authentication tokens. Contractors shall notify the appropriate VA COR/CO immediately to initiate access removal.

g. Contractors/subcontractors who no longer require VA accesses will return VA-issued property to VA. This property includes (but is not limited to): documents, electronic equipment, keys, and parking passes. PIV and PIV-I access badges shall be returned to the nearest VA PIV Badge Issuance Office. Once they have had access to VA information, information systems, networks and VA property in their possessions removed, contractors shall notify the appropriate VA COR/CO.

4. TRAINING. This entire section applies to all acquisitions which include section 3.

a. All contractors and subcontractors requiring access to VA information and VA information systems shall successfully complete the following before being granted access to VA information and its systems:

i. VA Privacy and Information Security Awareness and Rules of Behavior course (Talent Management System (TMS) #10176) initially and annually thereafter.

ii. Sign and acknowledge (electronically through TMS #10176) understanding of and responsibilities for compliance with the Organizational Rules of Behavior, relating to access to VA information and information systems initially and annually thereafter; and

iii. Successfully complete any additional cyber security or privacy training, as required for VA personnel with equivalent information system or information access [to be defined by the VA program official and provided to the VA CO for inclusion in the solicitation document

– i.e., any role-based information security training].

b. The contractor shall provide to the COR/CO a copy of the training certificates and certification of signing the Organizational Rules of Behavior for each applicable employee within five days of the initiation of the contract and annually thereafter, as required.

c. Failure to complete the mandatory annual training is grounds for suspension or termination of all physical or electronic access privileges and removal from work on the contract until such time as the required training is complete.

5. SECURITY INCIDENT INVESTIGATION. This entire section applies to all acquisitions requiring any Information Security and Privacy language.

a. The contractor, subcontractor, their employees, or business associates shall immediately (within one hour) report suspected security / privacy incidents to the VA OIT’s Enterprise Service Desk (ESD) by calling (855) 673-4357 (TTY: 711). The ESD is OIT’s 24/7/365 single point of contact for IT-related issues. After reporting to the ESD, the contractor, subcontractor, their employees, or business associates shall, within one hour, provide the COR/CO the incident number received from the ESD.

b. To the extent known by the contractor/subcontractor, the contractor/ subcontractor's notice to VA shall identify the information involved and the circumstances surrounding the incident, including the following

i. The date and time (or approximation of) the Security Incident occurred.

ii. The names of individuals involved (when applicable).

iii. The physical and logical (if applicable) location of the incident.

iv. Why the Security Incident took place (i.e., catalyst for the failure).

v. The amount of data belonging to VA believed to have been compromised.

vi. The remediation measures the contractor is taking to ensure no future incidents of a similar nature.

c. After the contractor has provided the initial detailed incident summary to VA, they will continue to provide written updates on any new and relevant circumstances or facts they discover. The contractor, subcontractor, and their employes shall fully cooperate with VA or third-party entity performing an independent risk analysis on behalf of VA. Failure to cooperate may be deemed a material breach and grounds for contract termination.

d. VA IT contractors shall follow VA Handbook 6500, Risk Management Framework for VA Information Systems VA Information Security Program, and VA Information Security Knowledge Service guidance for implementing an Incident Response Plan or integrating with an existing VA implementation.

e. In instances of theft or break-in or other criminal activity, the contractor/subcontractor must concurrently report the incident to the appropriate law enforcement entity (or entities) of jurisdiction, including the VA OIG, and the VA Office of Security and Law Enforcement. The contractor, its employees, and its subcontractors and their employees shall cooperate with VA and any law enforcement authority responsible for the investigation and prosecution of any possible criminal law violation(s) associated with any incident. The contractor/subcontractor shall cooperate with VA in any civil litigation to recover VA information, obtain monetary or other compensation from a third party for damages arising from any incident, or obtain injunctive relief against any third party arising from, or related to, the incident.

f. The contractor shall comply with VA Handbook 6500.2, Management of Breaches Involving Sensitive Personal Information, which establishes the breach management policies and assigns responsibilities for the oversight, management and reporting procedures associated with managing of breaches.

g. With respect to unsecured Protected Health Information (PHI), the contractor is deemed to have discovered a data breach when the contractor knew or should have known of breach of such information. When a business associate is part of VHA contract, notification to the covered entity (VHA) shall be made in accordance with the executed BAA.

h. If the contractor or any of its agents fails to protect VA sensitive personal information or otherwise engages in conduct which results in a data breach involving any VA sensitive personal information the contractor/subcontractor processes or maintains under the contract; the contractor shall pay liquidated damages to the VA as set forth in clause 852.211-76, Liquidated Damages— Reimbursement for Data Breach Costs.