This statement of work outlines requirements for a federal contract to repair damaged flooring at the Veterans Health Care System of the Ozarks facility in Fayetteville, Arkansas. The contractor must demolish existing flooring, abate and dispose of asbestos mastic, and install new Armstrong LVT plank flooring and 6-inch cove base in seven rooms totaling approximately 30,000 square feet. The performance period is 60 calendar days. The statement of work provides detailed specifications for the scope of work, drawings, safety requirements, site access and storage, disposal procedures, and other contractual requirements. The related federal contract opportunity is solicitation number 36C25624R0034 issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 to obtain these flooring repair services.

View the file

Other files

File Type Posted
Combined Specs.pdf PDF
564-24-105 Drawing.pdf PDF
RFP 36C25624R0034.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Repair Damaged Flooring in HIMS (B-1) Veterans’ Health Care System of the Ozarks (VHSO) Fayetteville, Arkansas

The Contractor must furnish all management, supervision, labor, material, equipment, tools, supplies, consumables, parts, and related services, in accordance with the SOW, drawings, and specifications to demolish all existing flooring, abate and properly dispose of asbestos mastic in all rooms, and install Armstrong LVT Plank flooring or equal according to manufacturer’s’ instructions and 6” cove base according to manufacturer’s instructions in the HIMS department (Building 1, Basement, Rooms 29, 30, 31, 32 including 2 electrical closets (36 & 38), and 37). Electronic Portable Document Format (.pdf) copies of drawings and specifications to this work will be furnished by VA upon Contractor’s written request to the Contracting Officer (CO). Hard copies of SOW, drawings, and specifications must be the Contractor’s responsibility and expense. Contractor is responsible to verify existing and new dimensions, locations, and quantities to complete this project located on the VHSO Main Campus 1100 N. College Avenue, Fayetteville, AR 72703.

**The Certification and Accreditation (C&A) does not apply, a Security Accreditation Package is not required**

I. GENERAL:

A. Any provision or partial provision of the Contract, including but not limited to, drawings and specifications that is not consistent with this SOW will be null and void only to the extent of the inconsistency. All other provisions or partial provisions of the Contract, including but not limited to, drawings and specifications, must remain in full force and effect.

B. Safety must be the Contractor’s highest priority.

C. Period of Performance: Sixty (60) calendar days.

D. This project must be a turn-key operation in accordance with this SOW, drawings, and specifications to be complete and working system(s).

E. VHSO facility must continue to operate during the contract Period of Performance, including but not limited to, the mechanical and electrical systems.

F. Contractor’s work must be conducted with the least amount of disruption to the VHSO facility.

G. Contractor must submit to the CO and CO Representative (COR) a Schedule of Values (SOV) and a Project Schedule (including Phasing Control Plan if applicable) in accordance with this SOW, drawings, and specifications no later than ten (10) calendar days after Notice to Proceed (NTP) for COR written approval. The Project Schedule must contain provisions, including but not limited to, staging equipment and materials ahead of closing the affected patient care areas and working extended hours to meet the project requirement.

H. Contractor must submit to the CO and CO Representative (COR) all submittals no later than seven (10) calendar days after NTP for COR written approval.

I. Prior to the start of job site activities, together the Contractor and COR must conduct a site survey to identify and review specific work and differing site conditions.

J. VHSO utilities and work areas may not be immediately available to the Contractor and the Contractor must be flexible in the project schedule without additional cost to the Government.

K. Contractor materials, equipment, tools, supplies, consumables, and parts must not be left unattended within a common work area. When working in common areas, there must be a minimum of two (2) contractor employees present to ensure that Contractor building materials, including but not limited to, equipment, tools, and supplies are not accessible to others.

L. Warranty: Contractor must guarantee workmanship for a period of one (1) year after COR written acceptance of work. Contractor must furnish a minimum one (1) year parts and labor warranty on equipment, components, and materials furnished plus any manufacturer’s warranty greater than one (1) year.

M. Emergency Service: Contractor emergency service must be available 24 hours per day. Contractor must respond on-site to emergency service calls within two (2) hours of notification. Contractor must have the issue(s) corrected or a plan in place (awaiting parts) within four (4) hours of arrival at job site. Any temporary repairs must have prior written approval by the Chief, Engineering Service or their designated representative.

II. SCOPE OF WORK:

A. Contractor except as noted otherwise must demolish all existing flooring:

1. Demolish all carpet tile and vinyl tile.

B. Contractor must abate and properly dispose of asbestos mastic under all floor tiles.

1. Contractor must remove and store all existing furniture and equipment during abatement and return once complete.

C. Contractor except as noted otherwise must furnish and install:

1. Armstrong LVT Plank flooring or equal per manufacturer’s instructions in color chosen by COR.

2. 6” cove base per manufacturer’s instructions in color chosen by COR.

III. SPECIFICATIONS INDEX:

SECTIONS NO. DIVISION AND SECTION TITLES DATE

01 00 00Division 01 - General Requirements11/01/2021
01 33 23Division 01 – General Requirements - Shop Drawings02/01/2023
01 35 26Division 01 – General Requirements – Safety 10/01/2022

02 41 00 Division 02 – Demolition 08/01/2017 02 82 13.19 Division 02-- Asbestos Floor Tile and Mastic Abatement 01/01/2021 09 65 19 Division 09—Resilient Tile Flooring 05/01/2018

IV. DRAWINGS INDEX:

DWG#

A101

DWG NAME

564-24-105 Drawing

V. CONTRACTOR ACCESS AND ACTIVITIES:

A. Safety: Contractor’s highest priority must be safety. Contractor work must be in accordance with Federal, State, Local OSHA codes, regulations, latest edition of NEC, latest edition of NFPA 70E, and 01 35 26 Safety Requirements specification. Contractor must furnish required safety items, including but not limited to, safety signage, cones, barricades, open trench coverings, steel grates/plates, and must furnish and wear required Personal Protective Equipment (PPE). Contractor must be prohibited to work without proper safety items and PPE and will be asked to leave job site in absence or use of same.

B. Site Supervision: Contractor must submit written qualifications of proposed site superintendent(s) to the CO and COR for consideration. Contractor must furnish superintendent(s) with written COR approval to continuously supervise on site contract activities. Contractor superintendent(s) must not engage in any direct trades’ labor.

C. Security: Contractor must coordinate with VA Police and COR to comply with the VHSO security management program, including but not limited to, obtain onsite access permission by the VA Police, be identified by Contractor and project, and restricted from unauthorized access.

D. Badging: While on campus, Contractor must wear a visible VHSO issued identity Badge. Contractor can be subject to inspection of personal effects when entering or leaving the project site and VHSO property. Contractor site superintendent must escort Contractor employees to Engineering (Building 5) to obtain badge(s). Contractor must maintain a Badge Log with Employee Names, Badge ID Numbers, Start Date(s), Departure Date(s), ID Lost Date(s), and ID Return Date(s). Contractor must update Badge Log and furnish to the COR weekly or as directed in writing by COR. Contractor must report lost Badge(s) immediately to the COR and document on Badge Log. Contractor must return Badge(s) immediately on day of departure of employee from project to COR and document on Badge Log. Contractor must return remaining Badge(s) at project closeout to COR. Contractor must reimburse the Government a $100.00 fee for each lost or unreturned Badge.

E. Property Access Work Hours:

1. Regular Business Hours: Work must be scheduled during regular business hours, 0600 to 1800 hours, Monday through Friday (excluding the following Federal holidays - New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day).

2. Designated Hours: Contractor must plan contract work activity that interferes with Medical Center (MC) operations and must not commence without prior COR written approval at no additional expense to the Government.

F. Utilities: Contractor must not leave unattended out-of-service any utility, fire protection, life safety system, or security system without written permission of the COR. If a utility, fire protection, life safety system or security system is not functional at the end of a work period without written permission of the COR, then the Contractor must restore the system(s) to working order prior to leaving the job site or must furnish an around-the-clock watch subject to COR written approval until the system is functional. If the Contractor fails to do so, the Contractor must reimburse the Government a fee equal to the amount of costs incurred by the Government to furnish around-the-clock watch and/or repair the system(s).

G. Parking: Contractor on-site parking is limited to availability of designated Contractor parking. Contractor must have prior COR written approval of on-site Contractor parking.

H. Vehicles and Construction Equipment: Contractors’ key(s) to unattended vehicle(s) and construction equipment must be removed and vehicle(s) locked.

I. Unloading and Loading: Contractor must unload and load materials, including but not limited to, equipment, tools, supplies, parts, and construction debris at the loading dock. Contractor must not leave vehicle(s) or construction equipment unattended at the loading dock. No materials, including but not limited to, equipment, tools, supplies, parts, and construction debris are permitted through the front entry.

J. Storage and Staging: Contractor storage and staging is limited to availability of designated on-site Contractor storage and staging. Contractor must submit a written request for storage or staging to the COR for consideration a minimum of seven (7) business days prior to the storage or staging. Contractor must have prior COR written approval of on-site Contractor storage and staging. Contractor must relocate or remove on-site storage and staging, including but not limited to, Contractor’s office trailer(s), dumpster(s), storage container(s) and construction materials a maximum of seven (7) business days after written notification by the COR without additional expense to the Government.

K. Equipment and Tools: Contractor must furnish construction equipment and power and hand tools, including but not limited to, ladders, scaffolds, lifts, backhoes, and forklifts to complete Contractor’s work.

L. Radios and Mobile Devices: Contractor must use mobile devices at low volume or outside. Contractor must not carry on conversations in hallways or near any patient areas. AM/FM radios and other media producing devices must not be used on VHSO property.

M. Noise: Contractor must coordinate and schedule with COR noise making activities. Contractor must submit to the COR a written request for consideration and written approval a minimum of seven (7) business days prior to activity. Contractor must have COR written approval to proceed.

N. Hot Work: Contractor must perform and safeguard hot work operations in accordance with OSHA 1910 Subpart Q, NFPA 241, and NFPA 51B. Contractor must coordinate and schedule with COR Hot Work Operations. Hot work operation is defined as operations including, but not limited to, open flame, producing heat and/or sparks, burning, welding, processes such as arc welding, oxy-fuel gas welding, open-flame soldering, brazing, thermal spraying, cutting, oxygen cutting, arc cutting, chipping, grinding, heat treating, sand blasting, torch-applied roofing, chemical welding, thawing pipe, and light horizontal welding, or an operation that is capable of initiating fires or explosions. Contractor must obtain Hot Work Permit from COR prior to activity.

O. Utility interruption: Contractor must coordinate and schedule with COR. Contractor must submit to the COR a written request for consideration and written approval a minimum of seven (7) days in advance of the proposed interruption. Work must be planned in advance to give as much time as possible to schedule a utility interruption. There may be times when a utility interruption request is denied because of insufficient lead-time or interference with ongoing VHSO activities and must be rescheduled at no additional cost to the Government. Contractor must have COR written approval to proceed three (3) business days prior to activity.

P. Disposal: Contractor must coordinate and schedule with COR. Contractor must have COR written approval to proceed three (3) business days prior to activity. Contractor must submit a written request to dispose of any government owned materials, equipment, or property in advance to the COR for COR written approval. Contractor must remove and properly dispose construction debris, materials, equipment, and substances from this project and the VHSO property daily into the Contractor supplied containers. Contractor must coordinate disposal container location with COR contingent upon available space and any future COR directed relocation(s) must be at no additional cost to the Government. Construction debris created from the project must not be disposed of in VHSO dumpsters or on VHSO property. Disposal of construction debris, materials, equipment, and substances from the project must be in accordance with applicable Federal, State, and Local laws, rules, and regulations. The Contractor must ensure and furnish appropriate documentation to the CO and COR that all hazardous waste handlers, haulers, and disposal facilities are properly licensed. The Contractor must furnish shipping manifest and documentation of disposal of construction debris, materials, equipment, and substances from the project prior to final payment.

Q. Fumes: Contractor must coordinate and schedule with COR. Contractor must submit to the COR a written request for consideration and written approval a minimum of seven (7) business days prior to activity. The Contractor must schedule fume producing work activities, including but not limited to, painting or heat produced fumes after regular business hours. Contractor must be responsible for ventilation necessary to exhaust and prevent fumes from entering adjoining areas, outside air intake ductwork, and re-entering the VHSO healthcare facilities at no additional cost to the Government. Contractor must have COR written approval to proceed three (3) business days prior to activity.

R. Photography: Contractor must coordinate and schedule with COR. Contractor must be escorted by VHSO personnel to take job site related photos. Contractor must not photograph any patients, personnel, visitors, and others on VHSO property.

VI. OTHER REQUIREMENTS:

A. Contractor must make every reasonable effort to protect VHSO property from damage.

B. The Contractor must furnish adequate protection for VHSO property before any construction activities occur. Contractor moved items must be put back by the Contractor to original locations and conditions as work is completed at no additional cost to the Government.

C. Anything remaining in place that is damaged or defaced by the Contractor must be restored by the Contractor to the pre-existing damaged or defaced condition at no additional cost to the Government.

D. The Contractor must coordinate work of different trades so that interference between mechanical, electrical, architectural, and structural work including existing services must be avoided and within limits indicated the required space for operation, repair, removal, maintenance, and testing of equipment. Utilities, including but not limited to, conduit, ducts, and pipes must be arranged to ceiling slab, walls, and columns to take up a minimum footprint of space. Conduit, ducts, pipes, and equipment must not interfere with intended use of eyebolts and other lifting devices.

E. Contractor must locate existing utilities in area of work. Contractor must furnish adequate means of support and protection to utilities that remain in place. Any property, including but not limited to, electrical, natural gas, medical gas, communication and utility lines, landscaping, walkways, roads, and curbs damaged by Contractor must be repaired or replaced at no additional cost to the Government. Government property, including but not limited to, walls, ceilings, floors, furniture, must be protected from damage at no additional cost to the Government. Areas must be cleaned after coring, sawing, and other construction activities by the Contractor at no additional cost to the Government.

F. No unauthorized Contractor work to be initiated without the prior written approval of the CO. The CO must approve any request, or proposal for changes in project scope or additional requirements, in writing prior to the Contractor proceeding with any work. Any Contractor changes without prior written approval by the CO, must be done at the Contractor’s risk and at the Contractor’s expense. Contractors must visit the job site and visit the facility in order to determine the nature and location of the work to be performed in general and the local conditions which can affect the work. Failure to do so must not relieve the Contractor of responsibility for estimating the difficulty or cost to perform the work. Contractor must comply with applicable Federal, State, Local laws, codes, regulations, and ordinances. Contractor must obtain permits and licenses required by Federal, State, Local law, code, regulation, and ordinance(s) at no additional cost to the Government.

564-24-601 SOW 4 Page 11 of 11