36C25624Q1378 0006.docx
DOCX document 119 KB Posted
- Attached to
- 6515--564-25-1-082-0001 Patient Lifts, Station 564. VHSO Fayetteville AR (VA-24-00051228)
- Solicitation number
- 36C25624Q1378
About this file
This document is an amendment to a solicitation for patient lifts and related services. The purpose of the amendment is to provide answers to a question regarding the reduction in project scope from 37 to 26 systems, and to provide an updated price/cost schedule.
The revised scope includes 19 motor swaps, 1 new lift system, and 6 remove and replace existing rails and motors. The reduction in scope is due to an ongoing construction project that will address the replacement of the lift systems in one of the rooms. The updated price/cost schedule provides details on the 12 ceiling-mounted patient lifts, 7 additional ceiling-mounted patient lifts, 1 trolley and rail system, 1 trainer module lift, and 5 lifts with 1 higher capacity lift for a specific location. The amendment also includes details on sling kits, warranty packages, training, and installation services. The performance period is from November 4, 2024 to November 4, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25624Q1378 0005 Question and Answer.docx | DOCX document | |
| Installation or Relocation Checklist for Ceiling Mounted Patient Lifts.pdf | ||
| Scope of Work Drawings.pdf | ||
| 36C25624Q1378 0004.pdf | ||
| 36C25624Q1378 0003.pdf | ||
| Question and Answer.docx | DOCX document | |
| 36C25624Q1378 0829.docx | DOCX document | |
| Technical Specifications Guldmann GH3 - Ceiling Lifts.pdf | ||
| 36C25624Q1378_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
10N16 Department of Veterans Affairs Network Contracting Office 16
715 S. Pear Orchard Road Ridgeland MS 39157
10N16 Department of Veterans Affairs Network Contracting Office 16
715 South Pear Orchard Road Ridgeland MS 39157 To all Offerors/Bidders
36C25624Q1378
X x x
10/16/2024 at 4:00 P.M.
See CONTINUATION Page
The purpose of this amendment is to answer the question asked in reference to the update solicitation and extended the close date to 10/16/2024 at 4:00 P.M.
1. Please see page 2 for question and answer.
2. Please see page 3 for updated price cost/schedule.
CONTINUATION PAGE
QUESTIONS AND ANSWERS
1. Firstly, we noticed that the project scope was reduced from 37 systems to 33 systems. Could you provide insight into the reasoning behind this reduction? Additionally, we are concerned about the removal of the system with the medical grade Class III scale. Could you clarify why this system was excluded from the project scope?
Project scope was reduced to 26 new improvements (19 motor swaps, 1 new lift system (rails and motor), and 6 remove and replace existing rails and motors). The reduction in scope is primarily due to project overlap. A construction project is currently underway on the 2nd floor and replacement of existing lift systems is in the scope of that project. Installation of a new lift system in room 266 (the room proposed to have the Class III scale) is in the scope of the current construction project.
1. Furthermore, we are seeking guidance on which price/cost schedule we should use for our bid submission. The price/cost schedule provided in the updated SOW appears to be missing several key items, such as the CLM management system, training, and, most importantly, the installation of the patient lifts themselves. Should we assume that the installation has been removed from the project scope, or was this an oversight in the updated SOW?
Updated price/cost schedule is provided on Page 3 of this amendment. Please review quantity and description for correct price/cost schedule information. Installation is not removed from the project scope. Patient Lifts have been updated to reflect reduction.
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 12.00 |
| EA |
| __________________ |
| __________________ |
PATIENT LIFT, GH3+ 550 SWL WITH SCALE, CEILING MOUNTED, WIFI CAPABLE, CLM AND SERVICE MODULE, HANGER BAR, FOR LOCATIONS: BUILDING 1- PC148, PC149, PC152, PC157, PC158, 207, 222, 345 (OR-3), 341, 345 (HPCU), 347, 348 (BEDROOM) Contract Period: Base POP Begin: 11-04-2024 POP End: 11-04-2025
| 7.00 |
| EA |
| __________________ |
| __________________ |
PATIENT LIFT, GH3+ 550 SWL, WIFI CAPABLE, CEILING MOUNTED, CLM AND SERVICE MODULE, HANGER BAR, FOR LOCATION: BUILDING 1- 025, 306, 317, 319, 348 (BATHROOM) BUILDING 21: 1245, 2314
| 1.00 |
| EA |
| __________________ |
| __________________ |
TROLLEYS, RAILS, WALL MOUNTED, EXISTING CEILING IS HARD PAN, 3 METER BY 3 METER FOR LOCATION: BUILDING 1- 348 (BATHROOM)
| 1.00 |
| EA |
| __________________ |
| __________________ |
PATIENT LIFT, GH3+ 550 SWL, CEILING MOUNTED, TRAINER MODULE, SCALE, WIFI CAPABLE, CLM AND SERVICE MODULE, HANGER BAR, FOR LOCATION: BUILDING 21- L149
| 1.00 |
| EA |
| __________________ |
| __________________ |
PATIENT LIFT, 5 EACH GH3+ 550 SWL AND 1 EACH GH3+ 825 SWL ALL WITH SCALE, CEILING MOUNTED, WIFI CAPABLE, CLM AND SERVICE MODULE, HANGER BAR, TROLLEYS, RAILS, INCLUDES REMOVAL OF EXISTING CEILING LIFTS, FOR LOCATION: BUILDING 1- 373-01, 374-01, 384-01, 385-01, 386-01, 387-01 (825 LB LIFT TO BE INSTALLED IN ROOM 387-01)
| 26.00 |
| EA |
| __________________ |
| __________________ |
SLING KIT, CEILING MOUNTED PATIENT LIFT, BASIC SEATED, REPOSITIONING, LIMB AND TURNING, FOR ALL LOCATIONS
| 26.00 |
| EA |
| __________________ |
| __________________ |
WARRANTY PACKAGE, GULDMANN CARE 3, THREE YEARS INCLUDING PARTS AND LABOR, ANNUAL PREVENTATIVE MAINTENANCE
| 5.00 |
| EA |
| __________________ |
| __________________ |
USER EDUCATION TRAINING, 8 HOURS DURING ONE DAY
| 1.00 |
| EA |
| __________________ |
| __________________ |
BIOMED ONSITE TROUBLESHOOTING TRAINING, 8 HOURS DURING ONE DAY, UP TO SIX TECHNICIANS
| 26.00 |
| EA |
| __________________ |
| __________________ |
CLM CARELIFT MANAGEMENT ONLINE ACTIVATION, WIFI ENABLED
| 20.00 |
| EA |
| __________________ |
| __________________ |
INSTALLATION, ALL LOCATIONS EXCEPT ICU
| 6.00 |
| EA |
| __________________ |
| __________________ |
INSTALLATION, FOR LOCATION: ICU (BUILDING 1: 373, 374, 384, 385, 386, 387)
| GRAND TOTAL |
| __________________ |
End of Document
File details come from the government source that posted it. Updated .