This document is a set of questions and answers related to a Request for Quote (RFQ) for window washing services at a U.S. Department of Veterans Affairs (VA) facility. The key details are:

The solicitation number is 36C25624Q1371 for window washing services at the Alexander VA Health Care facility in Pineville, LA. This is a total small business set-aside with a North American Industry Classification System (NAICS) code of 561720 and a $22 million size standard. The period of performance is 45 days after award. Contractors had until September 11, 2024 to submit questions, and quotes are due by September 13, 2024. The questions cover topics such as permits, access to sensitive areas, equipment requirements, waste disposal, and scheduling. The VA provided responses to clarify these areas for potential offerors.

View the file

Other files

File Type Posted
36C25624Q1371 0002_1.docx DOCX document
36C25624Q1371 0002 Amend_.docx DOCX document
36C25624Q1371 0001_1.docx DOCX document
36C25624Q1371_P1.docx DOCX document
Copy of Window Cleaning Spreadsheet 2024.xlsx XLSX spreadsheet
36C25624Q1371.pdf PDF
36C25624Q1371_1.docx DOCX document
Attachment 1 - Alexandria Louisiana VA Medical.pptx PPTX presentation

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions Site Visit 12 Sept 24 36C25624Q1371 Window Washing Service

1. In reference to Section B-2, page 10, letter a,b,c,d,e & f. Is there a cost to obtain these permits?

ANS: These works permits are not needed if your company is certified bonded.

2. Are there specific restrictions or requirements for accessing sensitive areas, such as security clearances for our personnel or escort requirements for certain locations within the facility?

ANS: After getting identification, you will be escorted throughout the campus.

3. Some windows, particularly those in the corridors, may require special equipment such as scaffolding or lifts. Will these be provided by the facility, or should we include the cost of such equipment in our proposal?

ANS: Include it into your cost. He facility will not provide any equipment.

4. Could you confirm whether designated waste disposal areas will be provided, or if we need to arrange our own means of removing debris from the site?

ANS: We have dumpsters on site to be used at your convenance.

5. For permits such as Infection Control, Lift, and Confined Space, could you provide an estimate of the time required for these processes to assist us in planning the schedule accordingly?

ANS: You will not be in any confined spaces, but a lift or scaffolding might be needed. Yes, we will assist with planning and provide the times for areas that cannot be automatically accessed.

6. Are there any anticipated special events during the contract period that might necessitate additional window cleaning services outside of the routine work?

ANS: There are no events currently anticipated which will require you to work outside of normal business hours.

7. Specifically, confirm how often invoices should be submitted—whether weekly, biweekly, or monthly—and whether the invoicing should be based on the number of cleanings performed per week?

ANS: It's a onetime service, completed within 45 days (per the SOW, correct?). Then the invoice should be submitted upon the close of the services provided once COR inspects and accepts the work.

Upon reviewing the ADDENDUM to FAR 52.212-1 Instructions to Offerors, I noticed an error in the following sections:

8. Additionally, the addendum states: "Contractor shall deliver and install product in accordance with the delivery schedule of this order." Could you please confirm if this refers specifically to a prior schedule or if a new delivery schedule is forthcoming?

ANS: This it's a onetime service, completed within 45 days (per the SOW, correct?). Then the invoice should be submitted upon the close of the services provided once COR inspects and accepts the work.

The statement reads: "The contractor shall submit Offerors shall submit a copy of OEM authorization with the technical quote.

ANS: This only pertains to manufacturers who are the Original Equipment Manufacturer (OEM) of the product. You must submit the OEM authorization memo with the packet stating that you own the product.