Questions and Responses 36C25621Q1739 Food Tray Line Equipment.pdf
PDF 105 KB Posted
- Attached to
- 7310--Combined Synopsis/Solicitation 36C25621Q1739 Food Tray Line Equipment and Installation
- Solicitation number
- 36C25621Q1739
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25621Q1739_4.docx | DOCX document | |
| Site Visit Sign In.pdf | ||
| 36C25621Q1739_3.docx | DOCX document | |
| 36C25621Q1739 0001 Amendment.pdf | ||
| 36C25621Q1739_2.docx | DOCX document | |
| Wage Determination 2015-5175 Rev 14 Dated 7-21-21.pdf | ||
| Additional Requirements 36C25621Q1739.pdf | ||
| 36C25621Q1739_1.docx | DOCX document | |
| Attachment - Trayline Diagram.pdf | ||
| Combined Synopsis Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Responses 36C25621Q1739 Food Tray Line Equipment and Installation
1. I was wondering if we could perhaps have some photos of the old system?
Response: No photographs will be provided.
2. Also if possible, when disposing of the old system:
All electrical and mechanical connections be disconnected by the customer?
Response: Yes, this will be completed by the Alexandria VA engineering staff.
3. Will the customer be ordering a scrap bin for pick up ? It is stainless steel and a local person can take it for free once we dismantle the system?
Response: After tray line has been disassembled, the scraps will be taken to the bone yard located on station.
4. Also is the customer ok if we dismantle and install the same day?
Response: The new unit will need to be brought up modular, so install will be dependent on the contractor getting all of the unit in place.