This statement of work and pre-solicitation notice describe a construction services contract opportunity for the Department of Veterans Affairs. The Central Arkansas Veterans Healthcare System intends to select a contractor to provide professional construction services for corrective actions to the HVAC, medical gas, CO2, and WAGD systems for the OR 2F surgical suites at the John L. McClellan Memorial Veterans Hospital in Little Rock, Arkansas. The scope of work involves renovating approximately 2,621 square feet of interior space for mechanical systems and 9,453 square feet for the surgical suites. The performance period is 365 calendar days from notice to proceed. This is a 100% service-disabled veteran-owned small business set-aside with a North American Industry Classification System code of 236220. The response deadline is not provided.

36C25619R0152 36C25619R0152_2.docx

View the file

Other files

File Type Posted
36C25619R0152-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Corrective Actions for OR 2F Mechanical Systems @ JLM John L. McClellan Memorial Veterans Hospital

FedBizOpps Sources Sought Notice

CLASSIFICATION CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

RESPONSE DATE (MM-DD-YYYY)

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

* = Required Field FedBizOpps Sources Sought Notice Rev. March 2010 Y 598-20-1-1111-0001, Project Number: 598-391 Title of Project: Corrective Actions for OR 2F Mechanical Systems 72114 1706 36C25619R0152 N 236220 Department of Veterans Affairs Chief, A&MM (90C/NLR) Central Arkansas Veterans HCS 2200 Fort Roots Drive, Bldg 41, Room 200 North Little Rock AR 72114 1706 Jack Caperton Jack.Caperton@va.gov 72012 Jack.Caperton@va.gov

EXAMPLE

1. PROJECT OVERVIEW

1.1. The Central Arkansas Veterans Healthcare System (CAVHS) intend to select a contractor to provide professional construction services for the “Corrective Actions for OR 2F Mechanical Systems” at their VAMC facilities in Little Rock, Arkansas.

1.2. This project is for renovation of the general corrective actions to the HVAC system for the OR 2F surgical suites, the Medical Gas system in the PCAU (2B-181) and new design drawings and specifications for new CO2 system and WAGD system in the OR 2F surgical suites.

1.3. Work consists of the contractor providing all labor, equipment, transportation, materials, quality control and supervision necessary to conduct construction in accordance with the project specifications and drawings.

1.4. The magnitude of construction per VAAR Part 836.204 is more than $250,000.00. This is a 100% SDVOSB set-aside.

1.5. North American Industrial Classification Standard (NAICS) code assigned to this construction project is 236220.

2. PROJECT ACTIVITIES

2.1. The entire activity of the project will follow the following sequence of events:

a. Pre-proposal Site Visit

b. Request for Proposal Submission

c. Selection

d. Award

e. Post Award Kick-off Meeting

f. Notice to Proceed

g. Bonding & Insurance

h. Submittals

i. Daily Reports

j. Weekly Progress Reports and Weekly Project Schedule

k. Permits (asbestos abetment)

l. Demolition, Construction, Installation and Commissioning

m. Final Inspection

n. Acceptance

o. Operations and Maintenance Manuals

p. AutoCAD Drawings (Design, Construction, As Built)

q. Payment

r. Warranty

3. SCOPE OF WORK

3.1. The Contractor shall provide all necessary services to meet the project objectives and requirements and to provide the required outcome in terms of overall quality, timeliness and documentation. The Contractor shall be responsible for obtaining and coordinating the services of any and all third-party Contractors performing other services on site and other entities as part of the contract to ensure the expected quality, timely, and documented final product.

3.2. Location: John L. McClellan Memorial Veterans Hospital, 4300 West 7th Street, Little Rock, Arkansas 72205.

3.3. Normal work hours for VA sites are 7:00AM to 4:30PM Monday through Friday except for Federal Holidays. If the Contractor desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working hours the contractor must submit a written request for approval to the Contracting Officer Representative (COR) at least seven (7) working days prior to the proposed start.

4. DESCRIPTION OF WORK

4.1. The plan is to renovate approximately 2,621-GSF of interior space for Mechanical Space on the Ground Floor and 9,453-GSF of interior space for OR 2F Surgical Suites on the 2nd Floor.

5. DELIVERIES

5.1. The Performance Period for this project is three hundred sixty-five (365) calendar days after receiving the Notice to Proceed.

5.2. The Notice to Proceed will be issued within 30 days after award of the solicitation.

5.3. Performance and Payment bonds: Due on Post Award Kick-off meeting.

5.4. Proof of Insurance: Due on Post Award Kick-off meeting.

5.5. All personnel assigned on the project and works on the construction site must complete a one-hour CAVHS Safety training.

6. ACCEPTANCE

6.1. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all of the following:

6.1.1. The Contractor has demonstrated/verified that the implemented ECMs function as intended at commissioning. All punch list items identified during the commissioning have been resolved.

6.1.2. The Contractor has provided O&M manuals.

6.1.3. The Contractor has provided Record drawings to include a CD with all as builds CAD files and PDF, and one full set on bond paper.

7. CONFIDENTIALITY AND NONDISCLOSURE

7.1. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.

7.2. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.

8. SECURITY.

8.1. All employees of general contractor and subcontractors shall comply with the VA security management program, be identified by through project and employer badges, and restricted from areas of unauthorized access.

8.2. Each Contractor shall be vetted by VA Security and each worker will have their ID issued by VA. Issued ID must be worn at all times.

8.3. General Contractor’s employees shall not enter the project site without appropriate badging/identification. They may also be subject to inspection of their personal effects when entering or leaving the project site.

8.4. No photography of VA premises is allowed without written permission of the Contracting Officer. The Contractor and workforce personnel shall not post or discuss government facility activities on unauthorized public media.

8.5. General Contractor’s employees are subject to rules of CAVHS Medical Center applicable to their conduct. However, the contractor personnel shall not be considered government employees for any purpose under this contract.

8.6. Execute work to interfere as little as possible with normal functioning of CAVHS Medical Center, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required.