36C25618U0231-0001000.docx
DOCX document 28 KB Posted
- Solicitation number
- 36C25618U0231
About this file
36C25618U0231 0001 36C25618U0231 0001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| -15115.docx | DOCX document | |
| 36C25618U0231-002.pdf | ||
| 36C25618U0231-001.docx | DOCX document | |
| 36C25618U0231-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF
CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV.
11/2016) is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR
43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14.
DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME
AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS
OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 08-29-2018
NONE
00502
ALEXANDRIA VA HEALTH CARE
SYSTEM
NETWORK CONTRACTING OFFICE 16
ALEXANDRIA VA HEALTH CARE SYSTEM
PO BOX 69004
ALEXANDRIA LA 71306-9004
00502
DEPARTMENT OF VETERANS AFFAIRS
NETWORK CONTRACTING OFFICE 16
ALEXANDRIA VA HEALTH CARE SYSTEM
SHREVEPORT HIGHWAY
PINEVILLE LA 71360-4004
To all Offerors/Bidders
36C25618U0231 08-29-2018
X X X 9-6-2018 @ 2:00P X THE PURPOSE OF AMENDMENT 0001 IS TO PROVIDE QUESTIONS AND ANSWERS AND TO EXTEND THE CLOSING DATE OF THE SOLICITATION.
THE CHANGES ARE AS FOLLOW:
A. SEE ATTACHED Q&A DOCUMENT. NO FURTHER QUESTIONS WILL BE ACCEPTED AFTER 12:00 NOON 8-30-2018.
B. THE CLOSING DATE OF
THIS SOLICITATION IS HEREBY CHANGED FROM 9-3-2018 TO 9-6-2018.
C. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
CONTINUATION PAGE
Attachment B
Questions Request Form
36C25618UO231
| # |
| Question |
| Answer |
| 1 |
| If the project is sales tax exempt can the government provide a sales tax exemption certificate? |
| N/A; not a construction project. |
| 2 |
| Where will the designated parking area be for workers accessing the construction site? |
| No Construction site, not a construction task or contract. |
See page 6 of the RFQ: Parking shall be limited to established concrete or improved rock parking lots, Using Service POC will advise which parking lots to use.
| 3 |
| Has the work area been checked for asbestos? |
| No asbestos on immediate temporary connection site. |
| 4 |
| What is the Governments’ policy if asbestos products are encountered during construction? |
| n/a |
| 5 |
| Does the Government currently have a 3rd party testing service for those items requiring testing or is the contractor free to locate and hire applicable testing firms? |
| VA does not have third party testers for this task. |
| 6 |
| Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin. |
| This is a firm fixed price supply buy. |
| 7 |
| There is space in the existing electrical panel for the new 3 phase 480 run to the boiler trailer? |
| Existing temporary connection capability is in place and will remain for this task. |
| 8 |
| All systems to be connected to the mobile boiler(fuel, electrical, steam, water, ect) are designated(marked and by distance) in the drawing provided to a point that has available space to tie into the existing facility system? |
| Yes |
| 9 |
| Is the mobile boiler being used to supplant a operational, existing system or replace a unit that is damaged or inoperable? |
| The unit is critical to supplement existing operations. |
| 10 |
| Is there a time limit(number of days) for the project as a whole? |
| See Delivery Schedule. |
| 11 |
| Is there a time limit for the installation of the new system once the unit arrives at the Pineville location? |
See Delivery Schedule.
| 12 |
| Will an time extension be granted if manufacturer issues cause delay in the arrival of the mobile unit as long as proof is provided that the unit was ordered in a timely manner for the agreed upon delivery? |
| This equipment is critical to the facility and is required 60 days ARO. |
| 13 |
| Please confirm project proposal is to be submitted digitally? |
| Quotes must be submitted electronically; See page 23 of the solicitation |
| 14 |
| Can the superintendent also serve as the SSO as long as proof of proper training can be provided? |
| This is not construction; All personnel in the contractors’ services will have certified or proper training on the tasks they perform as per page 6 of the RFQ. |
| 15 |
| In the document 36C25618U0231 36C25618U0231.docx; in the B.4 Price/Cost Schedule section; there is the following statement; Two (2) piston type pumps with stainless steel check valves, model #V-5-P15602, 0-6.2 gallons per hour pumping capacity, ? horsepower pump motors, Stainless steel strainer and suction piping… What is the required HP? |
| ¼ hp |
| 16 |
| Can you advise if the equipment purchased will need to comply with the VA equipment specs covered by VA spec 235011? |
| See page 6 of the RFQ - All work is to be performed within all OSHA, EPA, ASME, VA, and Federal, State and local codes and regulations. |
| 17 |
| Can the VA give us details on the installation? What about existing pipe hangers, rollers, restraints, pipe anchors, etc.? |
| Contractor will need pipe support mainly from the ground level vs hangers. |
The connections for all power supply and steam and condensate are in place already, as we’ve had several temp boilers on station.
| 18 |
| Is contractor required to provide electrical connection? |
| We would like a turn key product with electrical connection and a start-up technician provided by the contractor. |
Our electricians will be able to assist or instruct as to how our power is distributed
| 19 |
| Does the VA have existing infrastructure that will support the rental boiler system or is there a requirement to provide the needed engineering? |
| We have had a leased portable boiler parked on our grounds on the front side (laundry side of the boiler plant) and that has proven |
sufficient over the past rentals with some wood shoring under the tires of the trailer to help level
| 20 |
| There were no specs released with this requirement and the VA specs are very different than standard commercial market construction/boiler plant equipment specs. Can the VA give direction on the specs for the equipment? |
| The required specs are listed on page 4-5 of the solicitation |
| 21 |
| The solicitation states a 60-day delivery, but for new equipment this will have to be built from scratch and a 60-day delivery cannot be met. With the approval process of the trailer, it will likely be 4 months at the earliest and possibly up to 6 months. This trailer cannot be built and delivered before the start of this heating season. |
| This equipment is critical to the facility and is required 60 days ARO. |
| 22 |
| Are ALL pipe runs are straight, no obstacles in the way, existing pipe hangers, supports, anchors? |
| yes |
| 23 |
| The solicitation states that vendors shall be OEM authorized, but the trailers don’t have a specific OEM. Instead, they are custom build using many different manufacturers parts and equipment. There is no OEM that builds these in-house. As such, there is no list of “approved vendors”. Warranties will be maintained and provided regardless. Is there a more specific requirement the VA is searching for? We can and will provide a warranty. |
| The vendor’s warranty will be sufficient. Please submit boiler manufacturer’s information with quote as requested in Instructions to Offerors. |
| 24 |
| Is electrical connection is within 20 feet? |
| +/- 25 ft |
| 25 |
| Are we physically modifying existing pipes, flanges, steel, electrical breakers, adding pipe hangers? |
| The contractor will be connecting to EXISTING TEMPORARY BOILER CONNECTION POINTS |
| 26 |
| Will there be a site visit for this requirement? |
| There will not be a site visit for this requirement. |