Statement of Work Summary
This is a Statement of Work (SOW) for construction services related to contract 657-26-102JC, issued by the VA Saint Louis Health Care System for the John Cochran Division. The project requires a construction contractor to replace various roofs on Building 1 that have exceeded their useful life. Twelve roof areas (R01, R02, R03, R18, R23, R26, R27, R28, R30, R31, R36, and R37) totaling approximately 44,000 square feet of modified bitumen roofing require replacement. The contractor must furnish all supervision, tools, labor, materials, equipment, transportation, and testing necessary to complete the work in accordance with solicitation/contract terms and conditions, project specifications and drawings, VA Technical Information Listings (TIL), and applicable local and national codes.
The project has a performance period of 180 calendar days after the Notice to Proceed (NTP) issue date. The contractor must conduct site investigations to fully understand project conditions and limitations, including working hours restrictions, allowable equipment and materials storage areas, Infection Control Risk Assessment (ICRA) requirements and containment barriers, and Interim Life Safety Measures (ILSM). The SOW is intended as an outline only; in cases of conflict between this SOW and the final project drawings and specifications, the drawings and specifications take precedence. All work must conform to Records Management and Privacy Language requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
657-26-102JC : FCA - Replace Various Roofs on Bldg 1, JC
STATEMENT OF WORK (SOW)
for
CONSTRUCTION PROJECT:
1. This contract is for CONSTRUCTION services for the work required to replace various roofs on Building 1 at the John Cochran VA.
2. Description: VA Saint Louis Health Care System, John Cochran Division, requires a Construction
Contractor to replace various roofs identified through FCA report. Project will replace existing roofing beyond its useful life at JC. Roofs: R01, R02, R03, R18, R23, R26, R27, R28, R30, R31, R36, and R37; totaling approximately 44,000 SF.
3. The following roof areas are modified bitumen roofs that have exceeded their useful life and should be replaced soon: R01, R02, R03, R18, R23, R26, R27, R28, R30, R31, R36, and R37.
All work shall be performed in accordance with solicitation/contract terms and conditions, specifications and drawings, and all applicable VA TIL and local and National codes. Contractor shall furnish all supervision, tools, labor, materials, equipment, transportation and testing necessary. Contractor will perform site investigations to fully inform themselves of the conditions and limitations applied to the work.
The drawings and specifications include guidance on:
Working hours allowed on this project.
Allowable storage of contactor equipment and materials.
ICRA (Infection Control Risk Assessments) requirements and containment barriers.
ILSM (Interim Life Safety Measures).
4. Note: This SOW is intended as an outline and is not a detailed summary of the work the contractor will be required to perform. In the event of conflict between this SOW and the project drawings and specifications, the drawings and specifications will take precedence over this SOW.
Contractor to abide by all work & requirements set in the final “release for construction” project drawings and specifications.
5. Project shall conform to all Records Management and Privacy Language.
6. The period of performance for this project will be 180 calendar days after NTP issue date.