This is Amendment 0002 to Solicitation 36C25526R0070 for the St. Louis VA Project 657-18-115JCA, issued by the Department of Veterans Affairs Network Contracting Office (NCO) 15 in Leavenworth, Kansas. The amendment, effective March 23, 2026, provides responses to three pre-bid questions and closes the questions and answers window. All other terms of the solicitation remain unchanged.

The project scope involves replacing various Air Handling Units and Variable Air Volume Units at the St. Louis VA facility. Key clarifications from the questions and answers include: (1) ductwork must be cleaned and inspected prior to installation; contractors may supply new wrapped and sealed ductwork or use owner-furnished ductwork cleaned to VA standards with no dust or smear residue; all ductwork cleaning must occur within the stated construction period with no time extensions granted; ductwork will be cleaned with alcohol and clean rags approved by the Architect/Engineer and VA via shop drawing submittal; VA personnel including the Contracting Officer's Representative (COR), Construction Control Inspector, HVAC Shop Supervisor, HVAC Shop personnel, Maintenance & Operations Foreman, and Infection Prevention Personnel will inspect ductwork within two hours of cleaning, and failed inspections require recleaning; (2) no shop drawings showing stored ductwork installation locations exist—contractors must refer to construction drawings; and (3) the fabricated ductwork has not been confirmed to fit in its intended installation locations. Contractors must account for all required ductwork in their bids and ensure installations meet design intent, with any deficiencies corrected at no additional cost to the government.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

0002 04-27-2026

657-18-115JC

36C255

Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

36C255

Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

To all Offerors/Bidders

36C25526R0070

03-23-2026

X

X X

St. Louis VA Project 657-18-115JCA, CON: Replace Various Air Handling Units and Variable Air Volume Units The purpose of this amendment is to:

1. Provide answers to all submitted questions. See Responses to Questions 1- 3 on pages 2 and 3 of this document.

2. All other terms of the solicitation remain unchanged.

3. This ends the questions and answers window.

CONTINUATION PAGE

Replace Various Air Handling Units and Variable Air Volume Units

Solicitation_36C25526R0070

Project 657-18-115JCA

Pre-Bid RFI’S

General Questions

1. During the walk through we noticed that none of the ductwork was wrapped and sealed.

The standard for not only the hospitals but the sheet metal unions is to wrap the ends on every piece of ductwork to prevent dust and debris from contaminating ductwork.

a. Will ductwork need to be cleaned and inspected prior to installation. Yes. The contractor may choose, in lieu of owner furnished ductwork, to supply new wrapped and sealed ductwork as part of their bid. Regardless, the contractor must account for, and the installation of, all required ductwork in their bid whether it is new wrapped and sealed, or owner furnished and cleaned per VA approved standards. All installed ductwork, whether owner furnished or contractor furnished, shall be installed to meet the intent of the design. If the installed ductwork does not meet the design intent, VA inspections, final TAB report, or other failures to perform, the contractor shall repair and replace at no additional cost to the government. A pre-bid meeting on site was performed to allow all interested contractors to inspect existing conditions of the site and any owner furnished equipment.

b. If the ductwork will need to be cleaned, what is the requirement for cleaning it.

The duct work is required to be visibly clean without any dust or smear residue present.

i. All ductwork will be inspected for compliance by one of or all of the following VA personnel.

1. COR

2. Construction Control Inspector

3. HVAC Shop Supervisor

4. HVAC Shop personnel

5. Maintenance & Operations Foreman

6. Infection Prevention Personnel

ii. The Contractors shall clean all the ductwork within their approved ICRA barrier construction footprint.

iii. Ductwork will be cleaned with alcohol and clean rags.

iv. Whitin 2 hours of the cleaning process, VA personnel will inspect the ductwork then it is to be immediately wrapped.

v. If the ductwork fails the inspection, it shall be recleaned and a new VA inspection will be set.

vi. The contractor shall show the cleaning process on their construction schedule and shall set up VA approved meeting times for the VA to inspect.

vii. Type of alcohol used to clean shall be approved by the A/E and the VA via a shop drawing submittal.

viii. Cleaning ductwork must happen within the stated construction period of performance. No time extensions or adjustments will be granted based on time needed to clean ductwork per the VA standards.

2. Are there shop drawings showing where the stored ductwork is to be installed. No, Refer to construction drawings.

3. Was the fabricated ductwork confirmed to fit in the locations where it was made to be installed. No.

------------------------------- End of Amendment 0002 ----------------------------------------------