36C25526R0058 0005.pdf

PDF 148 KB Posted

Attached to
Y1DA--589A6-26-448, ADD LIGHTNING PROTECTION TO HOSPITAL
Solicitation number
36C25526R0058
Issued by

About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract issued by the Department of Veterans Affairs Network Contracting Office (NCO) 15 in Leavenworth, Kansas. The amendment number is 0005, effective March 5, 2026, for solicitation 36C25526R0058 (Project Number 589A6-26-448). The amendment extends the deadline for receipt of proposals to March 26, 2026 at 2:00 p.m. CDT. Offerors must acknowledge receipt of this amendment prior to the extended deadline by completing Items 8 and 15 and returning the required copies, by acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication that references the solicitation and amendment numbers. Failure to acknowledge receipt may result in rejection of the offer.

The amendment promulgates three changes to the original solicitation: (1) addition of RFI clarifications provided by the engineering staff referenced in the Amendment P0005 attachment; (2) confirmation that proposals are due March 26 by 2:00 p.m. CST; and (3) confirmation that all other terms and conditions remain unchanged. The attachment specifies four technical clarifications regarding lightning protection system design and installation, including that the system must receive a UL numbered master label, a ground loop and/or counterpoise is not required, a new surge protection system is not included in scope, and downleads can be located on the exterior of the building.

View the file

Other files

File Type Posted
36C25526R0058 0004.pdf PDF
RFIs ADD 589A6-26-448 LIGHTNING PROTECTION TO HOSPITAL.pdf PDF
36C25526R0058 0002.pdf PDF
S06 PRE-BID SIGN-IN SHEET.pdf PDF
S02 36C25526R0058.pdf PDF
S02 36C25526R0058.pdf PDF
36C25526R0058.docx DOCX document
P09 Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

0005 03-11-2026

589A6-26-448

36C255

Department of Veterans Affairs

Network Contracting Office (NCO) 15

3450 S 4th Street Trafficway

Leavenworth KS 66048

36C255

Department of Veterans Affairs

Network Contracting Office (NCO) 15

3450 S 4th Street Trafficway

Leavenworth KS 66048

To all Offerors/Bidders

36C25526R0058

03-05-2026

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 03-26-2026 2:00pm CDT

THIS AMENDMENT IS TO PROMULGATE THE FOLLOWING CHANGES.

1. This amendment is to add RFI clarifications provided by the engineering staff. See Amendment P0005 attachment.

2. Proposals due 03/26 by 2:00pm CST.

3. All other terms and conditions remain the same.

Timothy Fitzgerald

Contracting Officer

1. The lightning protection system design and installation must receive a UL numbered master label.

2. A ground loop and/or counterpoise is not a requirement.

3. A new surge protection system is not part of this scope.

4. Downleads can be located on the exterior of the building.

File details come from the government source that posted it. Updated .