AMENDMENT 0002 to 36C25526Q0102.pdf
PDF 787 KB Posted
- Attached to
- 36C25526Q0102 CAT6a Cable Pull - KC VAMC Federal contract opportunity
- Solicitation number
- 36C25526Q0102
About this file
This document is an Amendment to a Solicitation for a CAT6a Cable Pull project at the Kansas City VA Medical Center (VAMC), issued by the Department of Veterans Affairs Network Contracting Office. The solicitation (RFQ 36C25526Q0102) seeks a contractor to perform cable installation and related work, with a base period of 12 months and four 12-month option periods. Key project details include:
The cable installation involves 50-unit work blocks, with patient monitoring cables in orange and other drops in blue. Contractors must use CAT6a cable, Hilti 4-inch sleeves for penetrations, and perform work in occupied patient care areas, potentially restricted to nights and weekends. The project requires daily ICRA (Infection Control Risk Assessment) inspections, contractor-furnished HEPA carts, and work potentially in both existing facilities and future construction areas. Contractors will be responsible for cable pulls, demolition of existing cables, new installations, and core drilling, with an estimated 4 penetrations per floor. The contract is firm-fixed-price, with monthly payments based on completed work, and requires coordination in high-risk areas with 2 weeks' advance notice.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0001 to 36C25526Q0102.pdf | ||
| Solicitation 36C25526Q0102.pdf | ||
| Solicitation 36C25526Q0102.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 12
0002 01-15-2026
589-26-1-1829-0027
36C255
Department of Veterans Affairs
Network Contracting Office (NCO) 15
3450 S 4th Street Trafficway
Leavenworth KS 66048
36C255
Department of Veterans Affairs
Network Contracting Office (NCO) 15
3450 S 4th Street Trafficway
Leavenworth KS 66048
To all Offerors/Bidders
36C25526Q0102
12-17-2025
X
X X
X 1
CAT6a Cable Pull | Kansas City VAMC
The purpose of this Amendment is to provide Questions & Answers on the continuation pages (see also attached documents).
The solicitation ends January 20, 2026, at 11:00 a.m. Central. Quotes are due on or before January 20, 2026, by 11:00 a.m. Central.
Teresa Cabanting
Contracting Officer
QUESTIONS & ANSWERS
• Will monthly invoicing be fixed at the awarded rate in section B.3 regardless of the amount of cable actually installed?
ANSWER: No Cable will be assigned in a 50 unit block, Contractor will be paid in 12 payments/monthly for work completed each month.
• Will there be an allowance for making adjustments to the invoiced amount if the actual installed amount is significantly more than the estimated average in a given month?
ANSWER: Yes.
• If cabling is done in 50 unit blocks of work, and there is 250 units of work the first year, how will 5 blocks of work be performed over 12 months (for the base year)?
ANSWER: Cable will be assigned in a 50 unit block, Contractor will be paid in 12 payments/montly for work completed each month.
• The government estimates that : “50% of cable pulls will include demolition of existing cables, and 10% will require completely new installations including raceway, penetrations, and fire protection measures.”
ANSWER: Yes
• Will there be an allowance for making adjustments to the invoiced amount if the actual demolition and new installations amounts are significantly more than the estimated average?
ANSWER: This will be a Firm-Fixed-Price contract
• Do you have a specified firestop provider we need to work with?
ANSWER: Hilti
• What type and color of Cat6a cable needs to be installed?
ANSWER: Section 3.1 of the SOW has a bullet that covers this; however, Yes. Patient monitoring is orange. Blue for all other drops.
• Are we installing new patch panels?
ANSWER: No.
• At what phase of installation do the new raceways need to be installed?
ANSWER: Prior/during the pulling of cable.
• Does the Government have intentions of selecting more than company for this Contract?
• Will the Government Guarantee a minimum number of Task Orders per year?
ANSWER: There will be a Base Period and 4, 12-month, Option Periods and that is all. There are no guarantees for exercising an option.
• Is this a Time and Material or a Firm Fixed Price Contract or a Time and Material.
ANSWER: This will be a Firm-Fixed-Price contract.
• When can the company that has been awarded this contract expect to be offered a Task Order for work?
ANSWER: When evaluations are complete and a winner is chosen.
• Please confirm the required cable type (Category 6 vs Category 6A).
ANSWER: 6A.
• Will existing cable tray and J-hook infrastructure be reused, or should replacement be anticipated?
ANSWER: Reused if able.
• Are hard-lid ceilings present in any areas included in the scope?
• Are lifts required for any work areas, and will lift access be provided by the facility?
• Will work occur in occupied patient care areas?
• Are any areas restricted to nights or weekends only?
• Will work be phased by department or geographic area?
ANSWER: Yes when possible.
• What advance notice is required for access to high-risk areas (OR, ICU, ER)?
ANSWER: 2 weeks.
• Please confirm the estimated quantity of existing cabling drops to be removed.
ANSWER: See section 3.1 of the SOW.
• Will any active systems require coordination prior to removal?
• Please confirm the ICRA classification required for this scope.
ANSWER: Level 3 or higher.
• Will infection control requirements vary by department?
• What is the required frequency of ICRA inspections?
ANSWER: Daily.
• Will the facility provide negative air machines, or are they contractor-furnished?
ANSWER: Contractor-furnished.
• Please confirm the anticipated number of core drills and rated penetrations.
ANSWER: Rough estimate per floor is 4.
• Are Hilti systems required, or are equivalent systems acceptable?
ANSWER: All pass throughs are to be Hilti Sleeve 4 inch. Rough estimate per floor is 4 sleeves.
• Will firestopping inspections be performed by hospital staff or third-party inspectors?
ANSWER: Hospital staff.
• Please confirm Fluke DSX certification is acceptable.
ANSWER: Certified results must be able to be presented to HTM and readable without any special software or device.
• Are test results required per drop or per work package?
ANSWER: Work package.
• Is as-built documentation required at project closeout or per phase?
ANSWER: Per phase.
• Will pricing be adjusted for changes in scope, access, or infection control requirements?
ANSWER: This will be a Firm-Fixed-Price contract.
• Are materials owner-furnished or contractor-furnished?
ANSWER: Contractor.
• Is there a preferred invoicing structure (monthly vs per phase)?
ANSWER: See Cost/Price Schedule in the Solicitation and fill it out – in accordance with FAR Clause 52.212-1 Instructions to Offerors.
• Section B.2 indicates cable runs will occur “once monthly, for however many days are required,” while overall quantities are defined annually. The SOW also references monthly work and 50-unit blocks. Can the Government clarify whether work under this contract is expected to be performed on a recurring monthly basis, or issued on an as-needed basis when requirements arise? Will the Government provide monthly tasking estimates or minimum/maximum quantities per month, or should contractors assume highly variable monthly workloads? When a new cable work bundle is identified, can the Government clarify the typical lead time between notification to the contractor and the expected start of work?
ANSWER: Cable will be assigned in a 50 unit block contractor will be paid in 12 payments for work completed each month 15 working days.
• The SOW states that 50% of cable pulls include demolition of existing cables. Please clarify whether demolition includes only removal of abandoned cabling, or if it also includes removal of active cables requiring coordination, downtime, or system cutovers.
ANSWER: Some cable removal may require coordination, downtime, or system cutovers.
• The SOW requires PCRA for each work area and ICRA compliance per VHA Directive 7715 and references the use of HEPA carts. Can the Government clarify whether HEPA carts and containment materials are Government-furnished or Contractor-furnished, and provide typical approval timelines for PCRA/ICRA per work area? Please clarify the typical review and approval timeline for PCRAs and ICRAs once submitted. Is there an established SLA for approvals to prevent schedule impacts?
ANSWER: Contractor supplied carts and containment materials. 6 working days for PCRA/ICRA approval.
• The solicitation lists NAICS 517111 (Wired Telecommunications Carriers).
ANSWER: The NAICS is correct.
• The SOW notes that HEPA carts may minimize the need for ICRA issuance when removing one ceiling tile at a time. Please confirm whether use of HEPA carts formally waives ICRA requirements, or if approval is still required on a case-by-case basis.
ANSWER: PCRA and ICRA are required.
• The contract includes a monthly service CLIN. In months where no cable bundle is issued, can the Government clarify what constitutes acceptable performance for purposes of monthly invoicing and acceptance? Would the Government be open to a quarterly CLIN breakout vs.
monthly?
ANSWER: If no cables are needed for that month then no invoices will need to be submitted.
• Is there an area to store company equipment on site?
ANSWER: Minimal storage.
• Is there an estimated number of fire penetrations required?
ANSWER: 4 to 8 from a typical closet and depending on the length of the run but vendor can use existing penetration if they are Hilti Sleeve 4 inch.
• Are new CAT6A keystone jacks required as part of the quote?
• Are new patch panels, patch cables and/or switches required as part of the quote?
• Are drawings/blueprints available for the floors/areas that will be renovated or for the new construction areas?
ANSWER: Drawings will be made available upon request to the awardee.
• What are the specific brand specs (e.g. Panduit, Hubbell, Eaton, Chatsworth, etc.)?
ANSWER: Depending on system there will be Leviton or Tech Choice.
• What are the color codes for the cable?
ANSWER: Section 3.1 of the SOW has a bullet that covers this; however, Patient monitoring is orange. Blue for all other drops.
• For the areas that are being renovated, will the whole area be closed off?
• Will any infection mitigation (e.g. dust extraction/control, HEPA carts, etc.) be required?
• For areas where EMT conduit pathways will be required, will that be installed by the low voltage contractor?
• Or will that work be completed by an electrical contractor?
• The SOW references monthly work and 50-unit blocks. Can the Government clarify whether work under this contract is expected to be performed on a recurring monthly basis, or issued on an as-needed basis when requirements arise?
ANSWER: Cable will be assigned in a 50 unit block contractor will be paid in 12 payments for work completed each month.
• When a new 50-cable work bundle is identified, can the Government clarify the typical lead time between notification to the contractor and the expected start of work?
ANSWER: 15 working days.
• Can the Government confirm whether all anticipated cabling work locations are within existing facilities, or whether some work is expected to align with future building construction or renovation during the contract period?
ANSWER: It will be both.
• The SOW requires PCRA for each work area and ICRA compliance per VHA Directive 7715 and references the use of HEPA carts. Can the Government clarify whether HEPA carts and containment materials are Government-furnished or Contractor-furnished, and provide typical approval timelines for PCRA/ICRA per work area?
ANSWER: Contractor supplied carts and containment materials. 6 working days for PCRA/ICRA approval.
• The contract includes a monthly service CLIN. In months where no cable bundle is issued, can the Government clarify what constitutes acceptable performance for purposes of monthly invoicing and acceptance?
ANSWER: Cable will be assigned in a 50 unit block contractor will be paid in 12 payments for work completed each month.
• The solicitation includes FAR 52.219-14 Limitations on Subcontracting, which provides multiple options for the measurement period. Can the Contracting Officer confirm which limitation-on-subcontracting measurement period applies to this award (e.g., base period, option period, or contract term)?
ANSWER: The award will be for a 12-Month Base Period and four, 12-month, Option Periods.
That Clause covers ALL of the Periods of Performance.
• Do contractors get storage space on site?
ANSWER: Minimal storage.
• Do we need to purchase Data racks + patch panels?
ANSWER: Will be provided by Government.
• Anchor cable troth on concrete walls where needed?
• Access: PIV cards and keys?
ANSWER: After award is made, and Contractor has attended training, there will be access cards issued, depending on security or Contractor employees will be escorted.
• Delivery location at facility?
ANSWER: Building 1 Main dock.
• Where to store Hepa carts?
ANSWER: Yes, as needed.
• 10ft slack loops?
• Can the facility provide a guide for ICRA requirements per departments.
ANSWER: Yes, most will be level III or level IV.
• Requesting the following drawings: is there a contract number for a previous contract for this type of work?
ANSWER: No previous contract. AGAIN, drawings will be provided upon request from the awardee.
a. Electrical_ Telecommunications for entire building
b. Fire Protection_ Fire walls
c. Philips Patient Monitoring - ATTACHMENT A-Monitoring is attached to this Amendment.
• Does the facility have a Color Code scheme for the required data drops?
ANSWER: Section 3.1 of the SOW has a bullet that covers this; however, Yes. Patient monitoring is orange. Blue for all other drops.
• For the new construction areas, will the awarded vendor be required to install conduits and boxes?
ANSWER: Yes, when required by building code.
• Will the awarded vendor be required to work off hours and weekends?
• Do we have guidance on the number of firestop sleeves required, including conduit size, or should we plan for a worst case scenario?
ANSWER: All pass throughs are to be Hilti Sleeve 4 inch. Rough estimate per floor is 4 sleeves.
• Is there an estimate for the total length of raceway that will be required?
ANSWER: Use preexisting trays or J hooks when needed.
• How does the customer define a 50-unit block of work (stated in the Project Schedule of the
SOW)?
ANSWER: 50 individual runs listed on a standardized pull list. Covering entire hospital depending on need.
• Is it 50 cable runs completed?
See attached document: ATTACHMENT A-Monitoring.
See attached document: ATTACHMENT B-Site Visit Attendees.
ATTACHMENT A
ATTACHMENT B