Questions and Answers.pdf

PDF 132 KB Posted

Attached to
F109--Underground Storage Tank Inspections | St. Louis VA HCS
Solicitation number
36C25525Q0215
Issued by

About this file

This document is an Addenda #1 Questions and Answers (Q&A) for RFQ 36C25525Q0215 related to Underground Storage Tank Inspections for the St. Louis VA Medical Center. The Q&A addresses three specific clarifications: (1) the contract ceiling of $57,960.00 is based on past contract costs and subject to change, (2) triennial spill bucket hydro testing will be conducted on the initial year and then every three years (despite contract showing annual entries with zero quantity), and (3) labor calculations involve 3 inspectors working 16 hours over 2 days, totaling 48 hours of labor based on previous contract practices. The document is dated March 20, 2025 and provides operational and pricing detail clarifications for potential offerors, helping to standardize understanding of the contract requirements before submission.

View the file

Other files

File Type Posted
36C25525Q0215 0002.pdf PDF
36C25525Q0215 0001.pdf PDF
36C25525Q0215_1.pdf PDF
SOW.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDA #1 March 20, 2025

RFQ 36C25525Q0215

Underground Storage Tank Inspections for the St. Louis VAMC

QUESTIONS AND ANSWERS

1. Question #1: They have a contract ceiling for life of contract is $57,960.00 .... is this accurate?

Answer #1: The Dollar amount entered was based on past contract costs. We understand that the cost was subject to change.

2. Question #2: They have triennial spill bucket hydro test on every year ... do they actually want that? We typically do not see that.

Answer #2: Triennial testing is to be done on the initial year, then every three years. The contract shows it on every year but with a qty/amount of 0.

3. Question #3: And the first line item every year states " Labor (3 inspectors over 4 days) and a qty of 48 ... I’m assuming that is 48 hours? This is just unclear.

Answer #3: It was calculated for 3 persons over 2 days (16 hours) = 48 hours of labor. This was based on past contracts.

4. Question #4:

Answer #4:

5. Question #5:

Answer #5:

6. Question #6:

Answer #6:

7. Question #7:

Answer #7:

8. Question #8:

Answer #8:

9. Question #9:

Answer #9:

10. Question #10:

Answer #10:

11. Question #11:

Answer #11: